Acme Solar Holdings Limited has informed the Exchange about update on commissioning of additional capacity of BESS project in Rajasthan
ACMESOLAR · price
▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.
ACME Solar Holdings Limited, through its wholly-owned subsidiary ACME Surya Power Private Limited, has commissioned an additional 34.598 MW / 155.493 MWh Battery Energy Storage System (BESS) project in Jaimalsar village, Bikaner district, Rajasthan. The project was commissioned on May 27, 2026, with Commercial Operation Date (COD) set for May 29, 2026. With this addition, the subsidiary has achieved a cumulative commissioned capacity of 245.536 MW / 1103.392 MWh. This represents continued expansion of the company's BESS portfolio in Rajasthan.
This announcement signals positive operational progress as the company adds significant BESS capacity. For shareholders, this demonstrates execution capability and growth in renewable energy assets, which could contribute to future revenue streams.