NTPC Limited has informed the Exchange regarding 'Declaration of COD of second partcapacity of 125 MW out of 500 MW Bhadla Solar PV Project of NTPC Renewable Energy Limited'.
NTPC · price
▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.
Awaiting price reaction for this filing.
NTPC has announced the commercial operation date (COD) for the second part of 125 MW capacity from its 500 MW Bhadla Solar PV Project, located in Rajasthan. The project is being executed by NTPC Renewable Energy Limited, a subsidiary of NTPC. This is a phased commissioning — the remaining 375 MW capacity is yet to be declared commercially operational. With this 125 MW now operational, NTPC's renewable energy portfolio expands further and will start contributing to power generation revenue.
Mildly positive for shareholders — adds 125 MW of operational renewable capacity, supporting incremental revenue from the solar segment. Remaining 375 MW commissioning will be the next key milestone to track.