One DRI plant kiln taken for about 30 days maintenance

Capex & Operations View source PDF

Price

Loading chart…

▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.

Price reaction · full curve 14 horizons · vs prior close
-3.4%1-day move
₹227.85
prior close
₹228.95
base price
In-mkt
timing
5m10m15m30m1D2D3D4D5D7D15D1M2M3M
+0.0+0.0+0.0+0.0-3.4-0.4-1.3-1.8-5.2
Up moveDown movePending
AI summary

Suraj Products has taken one kiln of its DRI (Direct Reduced Iron) Plant at Rajgangpur, Odisha for maintenance. The company expects the work to take about 30 days and will update the stock exchanges once operations resume. The intimation is filed under SEBI LODR Regulation 30. No financial impact or cost details were disclosed.

Likely market impact

Around 30 days of reduced output from one kiln may marginally dent production and revenue. No accident or capex flagged.