NHPC partial win in arbitration; AT awards about half of contractor's claim

Arbitration WonRegulatory & Legal View source PDFExplain this filing

NHPC · price

Loading chart…

▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.

Price reaction · full curve 14 horizons · vs prior close
+0.6%1-day move
₹75.80
prior close
₹76.11
base price
After-mkt
timing
5m10m15m30m1D2D3D4D5D7D15D1M2M3M
+0.3+0.4+0.4+0.8+0.6-0.1+0.1+1.2+0.7+0.3+0.3-5.0——
Up moveDown movePending
AI summary

NHPC informs that the Arbitral Tribunal has awarded about INR 392.31 crore plus Euro 15.36 lakh to contractor M/s BGS-SGS-SOMA for construction of diversion tunnels and dam works at the 2000 MW Subansiri Lower Hydroelectric project. The contractor had claimed about INR 796.87 crore plus Euro 28.76 lakh. The awarded amount is roughly half of the claim. NHPC notes the amount is allowable as project cost and recoverable through tariff under CERC Tariff Regulations 2024.

Likely market impact

Partial win for NHPC as payout is nearly half of the contractor claim. Since cost is recoverable through tariff, near-neutral impact on shareholders.