SOLARWORLDNSESOLARWORLD ENERGY SOL LTD· ConstructionHighNegative
Announced Fri, 18 Sept, 2026 · 20:52 IST

Solarworld wins partial DAB awards worth about 40 crore in SJVN disputes

Arbitration WonRegulatory & Legal View source PDFExplain this filing

SOLARWORLD · price

Loading chart…

▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.

Price reactionminutes from the announcement price · days from the prior close
+4.2%Reaction day
₹134.69
prior close
₹134.46
announcement price
After-mkt
timing
Nifty Microcap 250market · in no size index; the smallest one is used-0.1%+4.3% vs market
Civil Construction peers, median of 99sector-0.2%+4.4% vs sector

On the reaction day the stock moved 4.3 pts more than Nifty Microcap 250 and 4.4 pts more than its Civil Construction peers, over the same two closes: a difference in percentage points, not a measure of what the filing did.

Minutes after the announcementfrom the announcement price · no benchmark
Stock
5m
-0.7
10m
-0.5
15m
+0.0
30m
+0.6
Sessions after the filingfrom the prior close
StockMarketvs marketSectorvs sector
Reaction day
+4.2-0.1+4.3-0.2+4.4
Next day
+3.5+0.3+3.3-0.1+3.6
2d
+2.8+1.6+1.3+0.5+2.3
3d
-1.1+0.1-1.1-1.1+0.0
4d
-0.5+0.3-0.8-1.1+0.7
5d
-2.1-1.2-0.9-2.5+0.4
1w
-4.4-0.5-3.9-3.1-1.3
15d
-5.4-2.2-3.2-3.3-2.0
1m
-16.2-6.6-9.6-7.7-8.5
2m
—————
3m
—————
UpDownMarket · Nifty Microcap 250Sector · Civil Construction peers, median of 99Pending

Minute windows have no benchmark: there is no intraday index history to compare against.

AI summary

Solarworld won partial DAB awards in two EPC contract disputes against SJVN Green Energy. It claimed about 219 crore total and was awarded about 40 crore. The 100 MW project yielded 13.77 crore (claimed 56.50 crore) and the 260 MW project yielded 26.50 crore (claimed 162.83 crore). Awards include liquid cash and retention money release against bank guarantee substitution.

Likely market impact

Positive cash inflow expected, but awards are much lower than claims and SGEL may challenge in court, creating execution uncertainty.