Caliber Mining and LOG Q2 FY27 earnings call
In brief
FY27 guidance reiterated: 45%+ revenue growth, 35%+ EBITDA/PAT growth; Q3-Q4 each target 60 million cubic meter of overburden removal.
- Management's tone
- Confident
- What was said
- Leaned positive
- Guidance
- Guidance held
- Analyst pushback
- Medium
- Stock, next session
- +0.74% (Nifty 50 +0.58%)
- Management reiterated FY27 guidance of 45%+ revenue growth and 35%+ EBITDA and PAT growth year on year.
- Q2 normalized revenue grew more than 90%, normalized EBITDA was INR73.2 cr and margin 16.60%, but net loss was INR7.51 cr.
- H1 overburden removal reached 76.49 million cubic meter, coal extraction grew 41%, and coal loading rose 50%.
- The order book spans nine sites for about 2.5 years, while bids worth over INR11,000 crores await results.
- Q3 and Q4 are each targeted at 60 million cubic meter of overburden removal.
An AI read of the company's transcript · the filing
The numbers
The quarter, Q2 FY27
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹519 cr | — | −20.9% | |
| EBITDA (excl. other income) | ₹73.1 cr | — | −34.0% | 14.1% |
| Net profit | ₹0 cr | — | — | 0% |
| EPS (₹) | ₹-1.19 | — | — |
From the company's filed results for the quarter ended 30 Sept 2026 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.
Where management's figures differ from the filing
- Revenue: said Consolidated normalized Q2 revenue INR441 crores; filed Revenue ₹519.45 cr. Management's 441 figure was normalized after removing INR78.39 crores of diesel pass-through; filed revenue includes that pass-through.
- EBITDA margin: said Consolidated normalized Q2 EBITDA margin 16.60%; filed EBITDA ex-other income ₹73.09 cr (margin 14.1%). Management calculated margin on normalized revenue after removing diesel pass-through; the filed margin uses reported revenue, which includes it.
What moved the numbers, as management explained it
- Rain damaged haul roads, reduced workable days and raised repair costs, making Q2 seasonally weaker and H2 historically stronger.
- Higher activity—Q2 overburden removal of 33 million cubic meter versus 16 million and coal extraction of 0.76 million ton versus 0.03 million—drove revenue and EBITDA growth.
- Diesel pass-through of INR78.39 crores was included in reported revenue, lowering the reported margin; normalized figures remove it. (accounting)
- Depreciation and finance costs were largely fixed and rose with fleet expansion, resulting in a Q2 net loss of INR7.51 crores despite normalized EBITDA of INR73.2 crores.
- Q2 revenue was down 21% sequentially, but the decline was smaller than the more-than-42% seasonal drop in Q2 FY26.
The numbers management led with
- Quarterly overburden-removal target: About 60 million cubic meter in each of Q3 and Q4 FY27
- New tender pipeline: INR11,000 crores plus of net-new tenders bid on
- H1 capex: INR584.88 crores
- Net debt-to-equity: 0.95x at September 30, 2026 versus 1.48x at March 31, 2026
Guidance
Guidance on this call
| What | For | What management said |
|---|---|---|
| Consolidated revenue growth | FY27 | A growth of 45% plus in revenue on a year-to-year basis. |
| Consolidated EBITDA growth | FY27 | 35% plus in EBITDA on a year-to-year basis. |
| Consolidated PAT growth | FY27 | 35% plus in PAT on a year-to-year basis. |
| PAT | FY27 | PAT of approximately INR205-210 crores. |
| Quarterly overburden removal (Coal mining services) | H2 FY27 | About 60 million cubic meter in each of Q3 and Q4. |
| Volume output on some contracts (Coal mining services) | — | Targeting 105%, 110% and plus volume growth in some contracts. |
| Diesel cost pass-through | FY27 | 100% of diesel consumed is reimbursed by customers. |
| EBITDA margin | H2 FY27 | Expected to maintain a very good EBITDA margin in Q3 and Q4. |
| PAT margin | H2 FY27 | Expected to maintain a very good PAT margin in Q3 and Q4. |
| H2 capex | H2 FY27 | Capex for existing 100% volumes is mostly complete; additions depend on above-100% volumes or a new contract. |
| Caliber Pulse 2 live status | FY27 | Pulse 2 is expected to be live by month-end. |
| Tender pipeline participation | FY27 | INR4,000-plus crores of tenders to be participated in over the next 10 days. |
The business
By business
Coal mining services
Q2 overburden removal rose 109% to 33 million cubic meter and coal extraction rose 78% to 0.76 million ton; coal mining services generated 88% of revenue.
Q2 overburden removal 33 million cubic meter · Q2 FY26 overburden removal 16 million cubic meter · Q2 overburden removal growth 109% YoY · Q2 coal extraction 0.76 million ton · Q2 FY26 coal extraction 0.03 million ton · Q2 coal extraction growth 78% YoY · Coal mining services 88% of Q2 revenue
Outlook: About 60 million cubic meter of overburden removal is targeted in each of Q3 and Q4; some contracts are targeted at 105%, 110% and above.
Logistics
H1 coal loading rose 50% to 9.83 million ton, while Q2 coal transportation rose 42% to 2.44 million metric ton; logistics contributed 10% of revenue.
H1 coal loaded 9.83 million ton · H1 coal loading growth 50% YoY · Q2 coal transported 2.44 million metric ton · Q2 transportation growth 42% YoY · Logistics 10% of Q2 revenue
Ancillary services
Ancillary services accounted for the balance of Q2 revenue after coal mining services and logistics; no separate operating figures were provided.
MDO opportunities
Management is exploring MDO opportunities with private players, but no bid win, LOA, contract scale or operating result was disclosed.
Outlook: Management will update the exchange once an LOA is obtained; contract-specific financial impact is not yet knowable.
Balance sheet, capex and funding
- Net debt-to-equity fell to 0.95x from 1.48x as at March 31, 2026.
- Net worth rose 77% to INR1148.42 crores post-IPO.
- H1 capex was INR584.88 crores to mobilize three new contracts and meet demand beyond targeted volumes.
- Of INR377.16 crores net IPO proceeds, INR371 crores had been utilised as per the objects of the issue.
- Capex for current 100% contracted volumes was largely completed in H1; additions depend on above-100% volumes or new work.
The industry, as management sees it
Coal demand was expected to keep rising with power demand through the decade, with contractors executing a growing share of production. Management cited projected power-generation growth of 6.8% annually to FY30, with coal still about 60% of the mix.
Risks management named
- Monsoon rainfall damages haul roads, cuts working days and raises repair costs
- Fixed depreciation and finance costs have risen with fleet expansion
- Capex and execution could increase if customers require 105-120% of contracted volumes
- Customer-site hindrances can interrupt output and require contract extensions
Q&A
Q&A focused on H2 execution, normalized margins and converting the order pipeline into contracts rather than challenging the reiterated FY27 guidance. Analysts pressed most on the INR11,000 crore tender pipeline, MDO economics and AI benefits; management was detailed on operations but deferred FY28 guidance, MDO financial impact and quantified AI gains. The tone remained cooperative, with limited pushback and no material change to guidance.
Not answered directly
- Quantified win rate for the INR11,000 crore tender pipeline
- MDO working-capital, cash-flow, debt and margin impact
- FY28 fleet, order-book and cash-flow guidance
- Quantified financial benefit of the AI rollout
- Bid-pricing strategy for forthcoming coal tenders
Asked for a number, answered without one
- FY27 EBITDA margin: Management gave no margin percentage; it said PAT would be about INR205-210 crores and EBITDA growth would remain 35%+.
- H2 FY27 capex amount: Management said capex for existing 100% volumes was mostly complete; additions depend on 105%, 110% or 120% volume requests or a new contract.
- MDO financial impact: Management declined until contract scale and terms were known; INR500 crores and INR1,000 crores annual business were illustrative examples.
- AI benefit: Management declined to quantify benefits, pointing to Caliber Pulse 1 and the beta version of Pulse 2 and offering a facility demonstration instead.
- FY28 fleet and order-book plan: Management said FY28 guidance would be provided at the end of Q3 once order additions and contract economics were clearer.
- INR11,000 crores tender wins: Management said it hoped to win all but acknowledged that this was not practically possible, without giving a number or win rate.
- October sales and margins: Management gave October volumes—over 180 million cubic meter and 6.4-6.5+ lakh metric ton of coal—but no sales or margin figures.
- Future tender pricing: Management declined to disclose pricing or bidding tactics, citing competitor confidentiality.
Every question, with its answer
1. Margins and H2 execution
Pawan Kumar, Shade Capital
Question. Despite the sharp revenue increase, why was EBITDA margin lower, and what caused the sequential decline?
Answer, Nikhil Kamalkishor Karwa, Chief Financial Officer. Management said the margin did not decline: normalized Q2 revenue rose 92% to INR441 crore, while normalized EBITDA margin increased 446 basis points from 12.14% to 16.60%. Rain disrupted activity, but despite the seasonal headwind, management said FY27 guidance remained intact.
Follow-up. Why should H2 margins improve; can you quantify FY27 EBITDA and PAT guidance; how will the larger order book be executed; and what capex remains for H2?
Answer. H2 should benefit from the monsoon ending, about INR4,000 crore of H1 order additions entering execution, and full diesel pass-through. Management repeated 60 million cubic metres of overburden removal in each of Q3 and Q4, implied FY27 PAT of about INR205-210 crore versus INR157 crore, and 35% plus EBITDA growth. It said capacity was in place and October execution was strong; customers were seeking 105-110% plus volumes, requiring possible pre-capex. Capex for the current book was mostly complete, with additions only for above-contract volumes or new awards.
Partly answered.
2. Diesel pass-through and margin protection
Dhananjai Bagrodia, Alchemy Capital Management Private Limited
Question. With crude now fully passed through, what happens to margins if diesel prices move materially, and are reported revenue and EBITDA margins comparable with the prior period?
Answer, Mohit Satishkumar Chadda, Chairman and Managing Director. Management said 100% pass-through removed commodity-price exposure, with average LOA rates of INR89-92; diesel at INR80, INR100 or INR120 would not alter margins or the Q1 guidance. H1 and Q2 pass-through were INR184 crore and INR78.39 crore, respectively, and were excluded from normalized revenue and EBITDA; Q2 normalized margin was 16.60% versus 12.14%.
Follow-up. Are private and government mine owners seeking more work, and how is Caliber positioned against competitors in bidding?
Answer. Management cited power-generation growth of 6.8% annually to FY30 with coal around 60% of the mix, and said private and government mining customers were generating a high volume of inquiries. It described coal contracting as exceptionally hot and expected Caliber to benefit. Competition remains intense, but post-IPO liquidity and AI-led operating efficiency should improve win rates and margins.
3. Tender conversion and MDO pipeline
Rahil Bohra, Vyom Partners LLP
Question. Of the more than INR11,000 crore of tenders bid on, how many bids are expected to be won as L1, given the company's earlier tender-conversion record?
Answer, Mohit Satishkumar Chadda, Chairman and Managing Director. Management declined to promise a win rate, saying it was not practical to expect all INR11,000 crore of bids to be won. It said IPO proceeds broadened Caliber's financial capacity to bid beyond the prior limit of about two contracts a year, while AI-driven efficiency and financial strength would improve competitiveness.
Follow-up. Are the INR11,000 crore of tenders limited to non-MDO work, have MDO bids been submitted, and what was the Q2 revenue split by segment?
Answer. The INR11,000 crore pipeline was described as non-MDO; management separately referenced about INR500 crore of MDO opportunities with private players, but said no LOA had been awarded and it would update the exchange after any award. For Q2, revenue mix was 88% coal mining services, 10% logistics and the balance ancillary services.
Not answered directly.
4. Seasonality and H2 ramp-up
Nachiket Kale, Individual Investor
Question. What drives the expected Q3 and Q4 ramp-up, and is the seasonal improvement sustainable beyond this year?
Answer, Mohit Satishkumar Chadda, Chairman and Managing Director. Management said H2 is normally stronger because it offers six months of largely uninterrupted mine operations; monsoon rain damages haul roads, reduces available working days and raises restart and repair costs. It reiterated that Q3 and Q4 guidance remained achievable.
Follow-up. How should the tender pipeline be viewed against the current order book, and will the post-IPO balance sheet support larger contracts?
Answer. Management said Caliber added more than INR4,000 crore of order book in H1 and had bid on more than INR11,000 crore, with another INR4,000 crore-plus of tenders to be addressed in the next 10 days. It viewed the IPO-funded balance sheet as enabling larger and longer-term contracts, while noting that bidding is a daily operating process.
5. October execution and Q3-Q4 outlook
Unnamed Individual Investor, Individual Investor
Question. What drove the EBITDA-margin improvement from 12% to 16%, how did October sales and margins perform, and what is expected in Q3 and Q4?
Answer, Mohit Satishkumar Chadda, Chairman and Managing Director. Management attributed the margin improvement to higher-scale execution and said October overburden volume exceeded 180 million cubic metres, with coal output of about 6.4-6.5 lakh metric tonnes. It described Q3 and Q4 as the strongest quarters, said all H1 orders had begun execution at 100% efficiency, and noted customer requests to exceed contracted volumes; capex had been pulled forward from H2 to H1. No October margin figure was provided.
Partly answered.
6. Fleet expansion and acquisitions
P.K., Spectra
Question. Is the fleet expected to increase beyond 2,226 units, and does management plan to acquire an engineering or equipment company?
Answer, Mohit Satishkumar Chadda, Chairman and Managing Director. Management said new awards would justify adding vehicles beyond the current 2,226-unit fleet. It did not plan to acquire an engineering or equipment company and said it would remain focused on its existing mining and logistics model while deploying available growth capital.
7. FY28 guidance and fleet plan
Smitesh, Unknown
Question. What are the expected FY28 fleet size, quality of orders, order-book pipeline and deployment of incremental cash flow?
Answer, Mohit Satishkumar Chadda, Chairman and Managing Director. Management explicitly deferred FY28 guidance to the Q3 earnings call at the end of December. It said the plan for FY28 fleet additions, order quality, execution pipeline and deployment of incremental cash flow will be based on December availability, with management first assessing new-business margins and payment security.
Not answered directly.
8. Contract extensions, diesel and MDO economics
Rahil Bohra, Vyom Partners LLP
Question. Why was INR63 crore of work still pending at the Jayant project after its stated September completion, and was the delay customer-driven or internal?
Answer, Mohit Satishkumar Chadda, Chairman and Managing Director. Management extended Jayant at existing rates and conditions after customer-site hindrances delayed completion and the customer needed more uninterrupted coal work. It said site obstructions can reduce daily output and lead to extensions.
Follow-up. Are 105-110% volumes based on original contracts; how does retrospective diesel pass-through work; what would MDO change for working capital, cash flow, debt and margins; and what capex remains for H2?
Answer. Management said 105-120% extensions arise when performance is good and the customer has additional work at existing rates. Customers revised tender estimates and reimburse diesel at actual cost minus the LOA rate, restoring full pass-through. MDO economics cannot be quantified until award and scale are known; management cited INR500 crore and INR1,000 crore annual examples and said it would disclose liquidity and capital impact with the award. Capex for existing orders was already complete, including the maximum H2 requirement, with additions only for 105-120% volumes or new contracts; it affirmed the roughly INR8,000 crore current order book was largely covered.
Not answered directly.
9. AI productivity, bid pricing and billing
Pawan Kumar, Shade Capital
Question. At what stage is Caliber's AI implementation, and can its productivity or margin benefits be quantified?
Answer, Mohit Satishkumar Chadda, Chairman and Managing Director. Management said Caliber Pulse 1 centralizes maintenance data for more than 200 mobile and web users and provides minute-by-minute vehicle-breakdown visibility from the CMD downward. Pulse 2, live in beta from November 1, integrates MIS and HR with real-time AI prompts and separate maintenance, MIS and HR war rooms; management expected it to be fully live by month-end. It declined to quantify benefits, offering a site visit instead.
Follow-up. Will Caliber quote better pricing in shortage tenders, and is diesel pass-through billed contemporaneously or with a lag?
Answer. Management declined to disclose bid-pricing strategy so competitors would not learn its approach, but pledged 100% efficiency and repeat orders. It said diesel is billed in the same month for some customers and on 15-day or monthly cycles for others, with no current impact; diesel prices of $80 or $110 would not matter under full pass-through.
Not answered directly.
What was said
Topic by topic, in the order it was spoken
Seasonality and H1 Operating Record · Mohit Satishkumar Chadda (Chairman and Managing Director)
- Q2 FY27 was characterized as the seasonally weakest quarter because monsoon conditions interrupt mine operations and should be considered when assessing results.
- H1 FY27 overburden removal reached 76.49 million cubic meter versus 44.40 million in H1 FY26, which management called the highest-ever half-year volume growth.
- H1 coal extraction grew 41% year on year; management said this operational performance drove significant growth across key financial parameters.
- H1 coal loading reached 9.83 million ton, up 50%; Q2 coal transportation was 2.44 million metric ton, up 42% year on year.
Q2 Mining and Logistics Execution · Mohit Satishkumar Chadda (Chairman and Managing Director)
- Q2 FY27 overburden removal reached 33 million cubic meter versus 16 million in Q2 FY26, a stated increase of 109% year on year.
- Management reported Q2 coal extraction of 0.76 million ton versus 0.03 million ton in Q2 FY26 and described growth as 78%.
- The logistics vertical continued expanding as Caliber sought to become an end-to-end coal logistics provider.
- Management said Q2 profitability remained seasonally weak but was much better than the prior-year quarter because of higher overburden removal and coal extraction.
Coal Demand and Customer Pull · Mohit Satishkumar Chadda (Chairman and Managing Director)
- Rising power demand was expected to continue supporting coal demand, and customers were urging Caliber to produce beyond contracted volumes.
- Management said coal production should keep growing through the decade, with contractors expected to execute a rising share.
- Coal, iron ore and critical minerals were described as foundational to India's growth and energy-security requirements.
- Operational improvement initiatives included technology upgrades, AI, qualified personnel, senior manpower and greater family involvement in day-to-day mine activities.
H2 Volume Target and FY27 Guidance · Mohit Satishkumar Chadda (Chairman and Managing Director)
- Management targeted about 60 million cubic metres of overburden removal in each of Q3 and Q4 FY27.
- The CEO said fleet capacity and contracts were already in place to deliver the H2 volume target.
- FY27 guidance was reiterated at 45% plus revenue growth and 35% plus growth in both EBITDA and PAT.
- Management expected H2 to benefit from the absence of the heavy monsoon season and full diesel-cost pass-through.
Order Book and Tender Pipeline · Mohit Satishkumar Chadda (Chairman and Managing Director)
- The existing order book covered nine sites with an average tenure of about 2.5 years.
- Management had participated in net-new tenders worth more than INR11,000 crore and was awaiting their results.
- The company intended to continue bidding for opportunities in coal, iron ore and critical minerals.
- IPO proceeds strengthened net worth, reduced leverage, funded fleet deployment and enabled bidding for larger contracts with longer-tenure customers.
AI and Fleet Productivity · Mohit Satishkumar Chadda (Chairman and Managing Director)
- Caliber operated a fleet of 2,226 units, making even modest productivity and vehicle-availability improvements financially material.
- AI deployment was being pursued across the business, with management calling it the next level of core efficiency.
- The immediate focus was on productivity and vehicle availability within mining and logistics operations.
- Management was upgrading technology and adding qualified and senior manpower alongside the AI initiative.
H1 Financial Performance · Nikhil Kamalkishor Karwa (Chief Financial Officer)
- Consolidated H1 FY27 revenue from operations rose 89% year on year and included INR184.10 crore of diesel pass-through.
- After removing diesel pass-through, normalized revenue was INR992 crore, up 59.5%, and normalized EBITDA was INR183.57 crore, up 48.7%.
- Cash profit rose 59.3% to INR100.83 crore from INR63.29 crore, using the same definition as Q1.
- FY26 seasonality showed H2 revenue at 1.7 times H1 and H2 EBITDA at 2.5 times H1, which management used to support H2 expectations.
Q2 Profitability and Seasonal Loss · Nikhil Kamalkishor Karwa (Chief Financial Officer)
- Normalized Q2 revenue grew more than 90% year on year, with normalized EBITDA of INR73.2 crore.
- Sequential Q2 revenue fell 21%, a materially smaller decline than the more than 42% seasonal drop in Q2 FY26.
- Fixed depreciation and finance costs contributed to a Q2 net loss of INR7.51 crore versus INR14.23 crore a year earlier.
- Cash profit was INR32.29 crore, about 4.7 times INR6.82 crore in Q2 FY26.
Balance Sheet, Capex and Funding · Nikhil Kamalkishor Karwa (Chief Financial Officer)
- Post-IPO net worth increased 77% to INR1,148.42 crore, while net debt-to-equity improved to 0.95x from 1.48x at March 31, 2026.
- H1 capex was INR584.88 crore to mobilize the Dhoptala II, Dudhichua II and Jayant II contracts and meet customer demand above targeted volumes.
- The fleet expanded to 2,226 units from 2,033 at June 30, 2026.
- Of INR377.16 crore in net IPO proceeds, INR371 crore had been utilized for the stated objects of the issue without deviation.
- CRISIL upgraded the company's long-term rating to A minus with a positive outlook.
- Management closed the prepared remarks by committing to strong H2 numbers.
In their words
We reiterate that FY27 guidance we gave you in quarter 1. A growth of 45% plus in revenue, 35% plus both in EBITDA and PAT on year-to-year basis.
Our strong order book and pipeline gives a clear visibility of our future growth in years to come.
At that scale, even a small gain in productivity or vehicle availability makes a real difference to margin.
To check next time
What management committed to on this call, or the dates they gave.
- Q3 FY27 overburden removal against the 60 million cubic meter target, with Q4 carrying the same target.
- FY27 revenue, EBITDA and PAT delivery against the 45%+, 35%+ and 35%+ growth commitments.
- FY27 PAT against management's INR205-210 crore range and the stated 35%+ PAT growth.
- New order awards from the INR11,000 crores bid pool and INR4,000-plus crores of tenders targeted for participation.
- Pulse 2's move from beta to live by month-end and evidence of AI-driven efficiency or margin gains.
- The promised December/Q3-call FY28 guidance on fleet size, order additions and next-year operating targets.
Transcript
We have not transcribed this call's recording. Read the company's transcript (PDF).
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Mon 16 Nov 2026 | ₹532.45 | +0.74% | +0.58% |
From the close of Fri 13 Nov 2026, ₹528.55: the call began at 17:00 IST, after the market closed, so that day's close is the base. Adjusted daily closes; the move includes everything else that happened in those sessions.