Data Patterns India Q2 FY26 earnings call

Thu 13 Nov 2025DATAPATTNS

In brief

Q2 FY26 revenue ₹308 cr (+238% YoY); ₹180 cr strategic contract diluted margins; FY26 guidance reiterated.

Management's tone
Confident
What was said
Leaned positive
Guidance
Guidance held
Analyst pushback
Medium
Stock, next session
+7.56% (Nifty 50 +0.01%)
  • Q2 revenue ₹308 cr (+238% YoY); H1 revenue ₹407 cr (+109% YoY) driven by strong execution across multiple programs.
  • EBITDA margin at 22% in Q2 vs guided 35-40%; ₹180 cr strategic low-margin contract weighed on margins; ex-strategic, margins would have been in guided range.
  • Q2 PAT ₹49 cr (+63% YoY); H1 EBITDA ₹101 cr (+41% YoY), H1 PAT ₹75 cr (+18% YoY).
  • Order book ~₹1,300 cr including negotiated pending; H1 inflows ₹351 cr with BrahMos and ECIL orders; export order book ~₹80 cr.
  • FY26 guidance maintained: 35-40% EBITDA margin confirmed; revenue growth flagged with slightly upward bias post strategic contract execution.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q2 FY26

This quarterA year agoLast quarterMargin
Revenue₹307 cr+237.8%+209.5%
EBITDA (excl. other income)₹68.5 cr+99.7%+113.5%22.3% (37.7% a year ago)
Net profit₹49.2 cr+62.5%+92.9%16% (33.3% a year ago)
EPS (₹)₹8.79+62.5%+93.2%

From the company's filed results for the quarter ended 30 Sept 2025 (standalone), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

What moved the numbers, as management explained it

  • Strategic ₹180 cr contract at competitive price diluted Q2 EBITDA margin to 22% vs guided 35-40%; ex-strategic, margins would have been in guided range. (one-off)
  • Strong execution across multiple programs drove Q2 revenue +238% YoY to ₹308 cr and H1 revenue +109% YoY to ₹407 cr.
  • H1 EBITDA ₹101 cr (+41% YoY) but H1 PAT growth lower at +18% YoY reflects margin dilution from strategic contract execution and prior-year base.
  • Substantial increase in salaries from headcount investment for future scaling; capex and training investments for production readiness ahead of anticipated orders.

The numbers management led with

  • Order book (including negotiated): INR1,300 crores
  • H1 order inflows: INR351 crores
  • Negotiated orders pending confirmation: INR552 crores
  • Strategic low-margin contract: INR180 crores executed in Q2 FY26

Guidance

Guidance on this call

WhatForWhat management saidFiled
EBITDA marginFY26On the bottom line guidance, we remain whatever we've told earlier; ex-strategic contract, Q2 EBITDA margin would have been in guided range of 35% to 40%.40.1%, above the range (standalone)
Revenue growthFY26There will be slightly upward movement on the revenue guidance because there is this contract which is executed.30.6%, above the range (standalone)
Order inflowFY26We expect more than that contracts in the next few months.—
Working capital days (FY26)FY26Aim to maintain the working capital days at the similar level for the full year.—
Working capital days (future target)—Going ahead, it will from 345 days come to 270 days and then maybe go down further depending on the kind of contracts we get.—

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

What changed since the Fri 8 Aug 2025 call

WhatOn the Fri 8 Aug 2025 callOn this call
Q2 revenue trajectory (achieved)Q1 FY26 revenue ₹99 cr, down 4.6% YoY due to ~₹27 cr customer-acceptance delays.Q2 FY26 revenue ₹308 cr, up 238% YoY driven by strategic contract execution.
FY26 revenue growth guidance (restated)FY26 revenue growth guidance of 20-25%.Slightly upward movement on revenue guidance post strategic contract execution; no new number given.
FY26 EBITDA margin guidance (held)FY26 EBITDA margin guidance of 35-40%.Confirmed guided range of 35-40% (analyst question reaffirmed); maintained for full year.
Order book size (raised)Order book at ₹1,079 cr with ₹320+ cr added since April.Order book ~₹1,300 cr including negotiated pending; H1 inflows ₹351 cr.
BrahMos seeker production contract (restated)Indigenous production contract expected in 1-2 months.Negotiations completed; contract expected to come soon; advanced product development stage.
Strategic systems contract (new)Not mentioned.₹180 cr strategic low-margin systems contract executed in Q2; capability validation for systems integrator transition.
AMCA consortium participation (new)Not mentioned.RFI response filed with BEML and Bharat Forge; avionics scope covering cockpit, radar, EW.

Guided on earlier calls, and what was filed

WhatForGuidedFiled
FY25 revenue growthFY2520–25% (on the Q4 FY24 call)36.3%, above the range (standalone)
FY25 EBITDA marginFY2535–40% (on the Q4 FY24 call)38.8%, within the range (standalone)
FY25 bottom line growthFY2530% (on the Q4 FY24 call)22.1%, below the figure guided (standalone)
Revenue growth rateFY2520–25% (on the Q1 FY25 call)36.3%, above the range (standalone)
EBITDA marginFY2535–40% (on the Q1 FY25 call)38.8%, within the range (standalone)
Bottom line growthFY2530% (on the Q1 FY25 call)22.1%, below the figure guided (standalone)
FY26 revenue growthFY2620–25% (on the Q4 FY25 call)30.6%, above the range (standalone)
FY26 EBITDA marginFY2635–40% (on the Q4 FY25 call)40.1%, above the range (standalone)
FY26 bottom-line growthFY2620% (on the Q4 FY25 call)22.3%, above the figure guided (standalone)
FY26 revenue growthFY2620–25% (on the Q1 FY26 call)30.6%, above the range (standalone)
FY26 EBITDA marginFY2635–40% (on the Q1 FY26 call)40.1%, above the range (standalone)

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

The business

By business

Strategic low-margin contract

₹180 cr contract executed in Q2 at competitive price to build capability for systems integrator transition; first large contract involving power, mechanical and electromechanical systems ~140-ton payload; future potential undisclosed.

₹180 cr contract value

Outlook: Future potential for multiple similar contracts; outcomes depend on competitive bidding.

BrahMos / Seeker

Negotiations completed for indigenous production contract; advanced stage of product development; AMC contracts (~31% of order book) for delivered fire control systems, launchers and test systems continuing under 5-year terms.

AMC contracts ~31% of order book

Outlook: Contract expected to materialise soon; production orders likely to follow.

EW & Avionics

Super Sukhoi jammer pod developed with Air Force evaluation ongoing; drone detection/jamming products maturing with 1-2 MOD orders won; AMCA consortium RFI filed with BEML and Bharat Forge covering cockpit, radar and EW.

Outlook: AMCA RFP expected in less than a year, possibly 6 months; SU-30 jammer pod assessment under way.

Exports

TPAR export to European customer completed client acceptance; export order book ~₹80 cr; UK ongoing volume orders; South America proposals; co-development with foreign multinationals under discussion.

Export order book ~₹80 cr

Outlook: New export team being set up; co-development for worldwide requirements progressing.

QIP-funded product development

₹122 cr deployed of ₹500 cr raised for product development across radars, EW, avionics, communications and seekers; products in advanced stage of development.

₹122 cr QIP utilised · ₹500 cr QIP raised

Outlook: More high-value orders expected as technology and products gain wider acceptance among customers.

Balance sheet, capex and funding

  • Working capital at 343 days; aim to maintain similar level for full year; most current receivables expected to be collected in H2.
  • Cash conversion cycle ~310-315 days excluding customer advances; expected to improve with more advances on new contracts.
  • Debt-free company; customer advances on contracts fund working capital needs.
  • ₹122 cr of QIP proceeds utilised for product development out of ₹500 cr raised.
  • Capex underway for future readiness; parallel build to deliver production orders quickly when received.
  • Working capital days targeted to gradually come down from 345 to 270 days and lower depending on contract mix.

The industry, as management sees it

Defence and aerospace demand environment is encouraging both in India and internationally. Requirement for indigenous IP-driven systems has intensified given geopolitical situation; DRDO and user-services increasingly want machine-mode project conversion. Export markets in Europe and South America are active with faster qualification-to-production cycles (1-2 years) versus India (3-5 years). Co-development opportunities opening up with large foreign multinationals in radar and EW. The share of indigenous products in India's defence procurement is expected to rise materially from current low base.

Risks management named

  • Strategic INR180 cr contract was margin-dilutive; future similar contracts may also be priced competitively
  • Working capital cycle remains elevated at 343 days; production-order conversion is the key to improvement
  • AMCA contract still in RFI stage; final RFP not yet published – consortium outcome uncertain
  • Foreign OEMs partnering with Indian companies continue to dominate 70–80% of defence imports
  • MOD contract finalisation timelines remain unpredictable; some negotiations have been postponed

Q&A

Discussion was dominated by three themes: (1) margin dilution and strategic contract rationale, which management deflected on specifics but confirmed would have been in 35-40% band ex-strategic contract; (2) AMCA consortium and large-platform opportunities, with management offering directional commentary but no quantification given RFI-stage; (3) export pipeline and product portfolio, where management was more forthcoming. Pushback was strongest on the strategic contract margin and order-book disclosures (Hardik Rawat, Dipen, Yash Poddar), and on receivables/working capital (Jyoti Gupta, Sumant Kumar). Multiple analysts probed whether margins would rebase higher in H2, with management committing to balanced product mix improvement without quantifying.

Not answered directly

  • Specific margin of strategic INR180 cr contract
  • Order-wise break-up of INR640 cr order book
  • AMCA contract value and Data Patterns' share
  • Exact receivables collection schedule for INR667 cr
  • Strategic contract margin if taken at regular pricing

Asked for a number, answered without one

  • Strategic contract margin: Said not at liberty to share exact margin in open call; only confirmed that excluding the strategic project, EBITDA margins would have been in the guided 35% to 40% range.
  • H2 receivables collection percentage: Said exact numbers not given; only most of current receivables expected to be collected in H2.
  • AMCA consortium value share: Said too early to comment; only RFI response filed, no RFP yet; scope covering cockpit, radar, EW.
  • ₹1,000 cr expected inflow mix: Said mostly product-related (development and production), not services or AMC; no further breakdown given.
  • Order book large-order composition: Said no list on hand and no specific contract prices shared; only referenced BrahMos and ECIL orders.

Every question, with its answer

  1. 1. Strategic order future

    Amit Dixit, Goldman Sachs

    Question. On the strategic INR180 cr order – do you expect more such orders going ahead? In which segments – radar, EW – and how do you see this playing through given it's margin-dilutive but revenue-accretive?

    Answer, S. Rangarajan, Chairman and Managing Director. Cannot discuss specifics of strategic order. Took it because of large potential for multiple such contracts; customer happy with execution. First time the company executed such a large contract involving power systems, construction, mechanical systems, ~140 ton payload – a complex electromechanical system. Capability development from smaller products to large systems is a key achievement. Will participate in similar contracts in radars, EW, and other avionics areas, subject to competitive environment.

    Not answered directly.

  2. 2. AMCA consortium

    Amit Dixit, Goldman Sachs

    Question. On the AMCA consortium with BEML and Bharat Forge – rationale, Data Patterns' scope, and any sense of the share we would get out of the total AMCA value?

    Answer, S. Rangarajan, Chairman and Managing Director. Too early – currently at RFI stage, RFP to follow, only one company gets the contract. Bharat Forge is large Indian player with systems capability aligned on India-build approach. Data Patterns has state-of-the-art avionics, cockpit solutions, radars, EW and electronic integration. Exact role allocation will depend on how the program pans out; will provide more clarity later.

    Partly answered.

  3. 3. DRDO programs and Super Sukhoi pod

    Jayakanth, Bandhan Alternatives

    Question. On DRDO's RFI for shared-aperture antennas merging radar/EW/comms for air force, navy and ground platforms – what is Data Patterns' approach? And the jammer pod for Super Sukhoi – is participation possible?

    Answer, S. Rangarajan, Chairman and Managing Director. Not aware of the specific shared-aperture RFI being referenced. On Super Sukhoi jammer pod – developed and in-house testing completed; offered to Air Force; full EW suite (not just pod) under evaluation. Pod is part of complete system; QIP funds to be used for further development. Wait for requirement specification.

    Follow-up. On the MiG-29 radar issues reported in the press – is Data Patterns going to be supplying some of these?

    Answer. Cannot comment on press articles. Data Patterns has internally-funded program for radars that can fit MiG-29 and Su-30; products in advanced stage of development. How it pans out depends on Air Force and Navy requirements.

    Not answered directly.

  4. 4. H2 order pipeline

    Dipen, Phillip Capital

    Question. H2 and beyond order wins – any large or high-value platform/subsystem expected given the INR1,000 cr H2 and INR2,000-3,000 cr 18-24 month guidance?

    Answer, S. Rangarajan, Chairman and Managing Director. Cannot discuss specific future contracts on open line. More orders expected in H2 to support guidance. Expect more contracts in next 3-4 months. Will consolidate and provide guidance on subsequent earnings call.

    Follow-up. Any update on BrahMos Seeker – were expecting a trial contract this quarter?

    Answer. Negotiations completed; contract to come. Already in advanced stage of product development. High focus given likelihood of production orders.

    Not answered directly.

  5. 5. Export pipeline

    Dipen, Phillip Capital

    Question. On export orders – beyond the European TPAR win, are other regions opening up – South America, others?

    Answer, S. Rangarajan, Chairman and Managing Director. Active proposals in Europe and South America. UK volume business expected to increase. Co-development agreements signed with some large foreign multinationals in radar and EW – developing for both India and global markets. Will form dedicated export team. Full systems more exportable than subsystems, so focus shifting to systems. TPAR redesigned from existing India radar for transportable application – India doesn't have this requirement yet but may adopt.

  6. 6. Export potential from TPAR

    Lavina Quadros, Jefferies

    Question. TPAR is the first fully developed radar exported by Data Patterns – does it change your export market potential? More inquiries expected?

    Answer, S. Rangarajan, Chairman and Managing Director. Subsystems vs full systems – large systems mostly exported. Full system opens up rest-of-world demand. Will focus on both subsystems and full systems. Once tested in India, additional markets pursued. Complex systems like TPAR have limited worldwide competition. Gradual path into exports.

  7. 7. Receivables, revenue guidance, margin

    Jyoti Gupta, Nirmal Bang

    Question. What % of INR667 cr receivables will be collected in H2? Should we revise revenue guidance from INR850 cr to INR1,000 cr? Will margins hold at ~40%? How low was the strategic contract margin – sub-20%?

    Answer, S. Rangarajan, Chairman and Managing Director. On collectibles: most will be collected in H2. On guidance: remain with earlier guidance; some upward movement on revenue due to the executed contract but bottom-line guidance unchanged. Cannot share exact margin of strategic contract on open call.

    Not answered directly.

  8. 8. Working capital cycle

    Sumant Kumar, Motilal Oswal

    Question. Working capital cycle at 343 days – what are the initiatives and targets over 2-3 years?

    Answer, S. Rangarajan, Chairman and Managing Director. A lot of development contracts in book – longer cash conversion due to delivery, testing, integration, field testing. Once mix shifts to production orders, cycle will improve. Targets: 343 days → 270 days → further reduction. Customer advances not included; debt-free company.

    Follow-up. If we consider customer advances, what is the cash conversion cycle?

    Answer. Excluding advances, ~310-315 days currently. New contracts expected to have more advances, so net cash conversion cycle should improve from current levels.

  9. 9. Strategic order margin impact

    Hardik Rawat, IIFL Capital

    Question. Without the strategic order, would Q2 EBITDA margin have been in the 35-40% guided range?

    Answer, S. Rangarajan, Chairman and Managing Director. Yes, definitely.

    Follow-up. Of the INR200 cr DRDO execution this quarter, is ~75% attributable to the large strategic order? Can you list 3-5 large orders in the INR640 cr order book?

    Answer. No, I don't want to share. We normally don't publish contract-wise details. Already mentioned large contracts from BrahMos and ECIL in opening remarks; more contracts expected in 3-4 months.

    Not answered directly.

  10. 10. Order inflow trajectory

    Hardik Rawat, IIFL Capital

    Question. On the INR550 cr negotiated orders not yet confirmed – should we expect confirmation in the next 1-2 months? And the FY26 order inflow trajectory – can we cross INR1,500 cr?

    Answer, S. Rangarajan, Chairman and Managing Director. Expect contracts in next 2-3 months; some MOD contracts are getting postponed. Yes, we expect more than that in the next few months.

  11. 11. New product pipeline and TAM

    Garvit Goyal, Nvest Analytics Advisory LLP

    Question. Color on new products in development for launch in 6-12 months? Are these for India + export? What's the expected TAM?

    Answer, S. Rangarajan, Chairman and Managing Director. Working on airborne fire control radars, ground radars (detection and fire control), EW programs (airborne podded/unpodded), drone detection (passive and active), jammer drones (1-2 MOD orders already), communication systems, glass cockpit/avionics, next-gen seekers. Building block approach enables various applications including exports. Not all products are exportable due to India-specific programs. TAM: INR15,000-20,000 cr. India imports 70-80% of requirements; foreign OEMs tie up with Indian partners to offer products – not just Data Patterns competing.

  12. 12. AMCA program timeline

    Vishal, Shareholder

    Question. If L&T and BEL consortium wins AMCA, is there a probability avionics portion flows back to Data Patterns? And the AMCA timeline?

    Answer, S. Rangarajan, Chairman and Managing Director. Believe so but cannot confirm – initial RFP unpublished. First 5 prototypes and avionics scope not visible. Customer wants to place contracts early – less than a year, maybe 6 months.

    Not answered directly.

  13. 13. AMC contracts nature

    Vandit Jain, SageOne Investments

    Question. On the 31% AMC contracts in order book – what is the nature, especially the BrahMos ones? Will they require further capex?

    Answer, S. Rangarajan, Chairman and Managing Director. Delivered BrahMos fire control systems, ground/airborne launchers, test systems since 2006. Maintenance contract with uptime guarantee; service engineers distributed across India. New 5-year contracts in continuation. No further capex required.

  14. 14. Strategic contract margin and inflow split

    Yash Poddar, Viansh Ventures

    Question. If strategic contracts are repeated at normalized pricing, what would the margin look like? And breakup of the INR1,000 cr expected inflow between production/development/AMC?

    Answer, S. Rangarajan, Chairman and Managing Director. On margins: not answerable now; will be negotiated case by case. On INR1,000 cr inflows (Subramanian clarified): includes INR552 cr already negotiated; mostly product-related, mix of development and production, not AMC. Sizable production contract expected in next 2-3 months. Will accomplish and exceed guidance contracts.

    Not answered directly.

What was said

Topic by topic, in the order it was spoken

Q2 & H1 FY26 Business Updates and Strategic Outlook · S. Rangarajan (CMD)

  • H1 FY26 revenue more than doubled YoY to INR407 cr; Q2 growth driven by execution of strategic INR180 cr contract taken at competitive pricing for long-term potential
  • EBITDA INR100 cr and PAT INR75 cr for H1; margins lower but profitability remains healthy
  • Total order book including negotiated/pending orders at INR1,300 cr; H1 inflows INR351 cr including significant orders from BrahMos and ECIL
  • Export order book at INR80 cr; TPAR (Transportable Precision Approach Radar) successfully completed client acceptance with European customer
  • QIP funds deployed: INR122 cr of product development spend so far; products at advanced stage of development
  • Strategy of developing systems ahead of formal MoD requirements; transitioning from subsystem supplier to full systems integrator across radar and EW
  • Continued focus on profitability over short-term expansion; investing in people and infrastructure

Q2 & H1 FY26 Financial Performance · Venkata Subramanian (CFO)

  • Q2 revenue INR308 cr (+238% YoY, +210% QoQ) on strong multi-program execution; H1 revenue INR407 cr (+109% YoY)
  • Q2 EBITDA INR69 cr (+100% YoY); H1 EBITDA INR101 cr (+41% YoY); H1 PAT INR75 cr (+18% YoY); Q2 PAT INR49 cr (+63% YoY)
  • Q2 gross margin 39%, EBITDA margin 22%, PAT margin 16% – margin drag attributed to low-margin strategic contract
  • Core profitability remains healthy; H2 margins expected to improve on more balanced product mix
  • Working capital days at 343; expect to collect most receivables in H2 and maintain similar levels for full year
  • Confident of achieving full-year revenue and EBITDA margin guidance

In their words

We've taken a different approach to build indigenous products with its IP-driven, capability-driven products. We continue to focus on such programs and products where there is a bottom line business also as we go along.
S. Rangarajan (CMD, Data Patterns India)
India actually imports more than 70%, 80% of our requirements. So you should not forget that. You can't say it's not made in India, only Data Pattern is doing it, so you'll get all the orders. That also doesn't happen. People tie up with foreigners, and we offer the products in India.
S. Rangarajan (CMD, Data Patterns India)
Big contract should happen maybe in another year, a couple of years, 2 years, 3 years. It will happen, which can really propel the growth of the company for far higher heights than what we've been able to do in the last 2 years. So we've been growing at 20%, 30% year-on-year. I think with the large markets, we should grow faster as we go along.
S. Rangarajan (CMD, Data Patterns India)

To check next time

What management committed to on this call, or the dates they gave.

  • Margin recovery to guided 35-40% range in H2 with more balanced product mix.
  • Conversion of ~₹552 cr negotiated pending orders expected within next 2-3 months.
  • BrahMos seeker indigenous production contract finalisation.
  • AMCA consortium RFP publication timeline (~6-12 months expected per management).
  • Strategic contract follow-on orders and repeat business from same customer.
  • Working capital collection in H2 and cash conversion cycle trend toward 270 days.

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Thu 13 Nov 2025₹3,003.40+7.56%+0.01%
5 sessions Wed 19 Nov 2025₹3,055.20+9.42%+0.68%
20 sessions Wed 10 Dec 2025₹2,543.20−8.92%−0.46%

From the close of Wed 12 Nov 2025, ₹2,792.20: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

Data Patterns India's other calls

  • Q2 FY27Mon 16 Nov 2026Tone: Optimistic
  • Q2 FY27Mon 9 Nov 2026Tone: Mixed
  • Q1 FY27Fri 31 Jul 2026Tone: Confident
  • Q4 FY26Fri 15 May 2026Tone: Confident
  • Q3 FY26Fri 6 Feb 2026Tone: Confident
  • Q1 FY26Fri 8 Aug 2025Tone: Confident
  • Q4 FY25Mon 19 May 2025Tone: Confident
  • Q3 FY25Thu 6 Feb 2025Tone: Mixed
  • Q1 FY25Tue 30 Jul 2024Tone: Confident
  • Q4 FY24Tue 21 May 2024Tone: Confident