GRE Renew Enertech Q2 FY27 earnings call
In brief
H1 FY27 revenue rose 217% to ₹139 crore; a low-margin 50MW AC/65MW DC project accounted for 48% of revenue and EBITDA margin was 9.52%.
- Management's tone
- Mixed
- What was said
- Mixed
- Guidance
- First guidance issued
- Analyst pushback
- Low
- Stock, next session
- −10.62% (Nifty 50 +0.14%)
- H1 FY27 consolidated revenue was Rs. 139 crore, up approximately 217% from Rs. 44 crore in H1 FY26.
- EBITDA rose 132% to Rs. 13 crore and PAT rose about 128% to Rs. 9 crore, while EBITDA and PAT margins fell year on year.
- The 50MW AC/65MW DC back-to-back EPC project contributed about 48% of H1 revenue at a lower margin through H2 FY27 and H1 FY28.
- The order book was Rs. 229 crore at September 30, and management expected 70%-80% conversion in H2 FY27.
- RESCO power sales contributed Rs. 3.33 crore, with 15MW-16MW running and almost 10MW-11MW in capital work in progress.
An AI read of the company's transcript · the filing
The numbers
The quarter, Q2 FY27
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹139 cr | — | — | |
| EPS (₹) | ₹0.00 | — | — |
From the company's filed results for the quarter ended 30 Sept 2026 (consolidated), not from the call.
What moved the numbers, as management explained it
- The large back-to-back EPC order for 50MW AC/65MW DC accounted for approximately 48% of H1 revenue and was a major driver of the revenue increase.
- That order carried a lower margin because GRE was the fourth-layer back-to-back subcontractor; this execution mix compressed EBITDA and PAT margins.
- RESCO added Rs. 3.33 crore of H1 power-sale revenue alongside EPC, providing a longer-duration revenue stream for up to 25 years.
- Trade receivables and payables increased together to fund the 65MW project; management said the net working-capital impact would not be major.
The numbers management led with
- EPC order book: ₹229 crore as of September 30, 2026
- MAHAGENCO back-to-back order: ₹175 crore for 50 MW AC/65 MW DC, comprising ₹170 crore project cost and ₹5 crore O&M
- IPP portfolio: Approximately 25-26 MW, including a 1 MW Rashtrapati Bhawan project awaiting commissioning
- Tracker generation advantage: 19-19.5 lakh units per MW versus 15-16 lakh units for fixed-panel systems
Guidance
Guidance on this call
| What | For | What management said |
|---|---|---|
| Order book conversion (Solar EPC) | H2 FY27 | We can expect conversion up to 70% to 80% of the order book. |
| Overall margins | H2 FY27-H1 FY28 | Until the execution of this particular project is completed in the second half of FY27 and the first half of FY28, you will see pressure on the overall margins. |
| Healthy margin | — | I am taking it on a healthy margin. And from earlier I have maintained my healthy margin and I will keep maintaining it going forward also. |
| Bank finance (RESCO) | — | 75% of the funding for the project is done from bank finance. |
| Own accruals (RESCO) | — | 25% of the funding is done from own accruals. |
| RESCO debt | — | As my RESCO profile will increase, the debt will definitely increase over there. |
| BESS entry in Gujarat | — | As soon as BESS is introduced in Gujarat, we will immediately come to BESS in Gujarat. |
| Higher margins (Solar EPC) | — | Whenever we bid in the tender and we come L1 in the future, there will be higher margins. |
| Operational maintenance revenue (O&M) | — | Every year, its revenue increases. |
The business
By business
Solar EPC
Solar EPC generated Rs. 129 crore, approximately 93% of H1 FY27 consolidated revenue; the 50MW AC/65MW DC back-to-back project accounted for about 48% of revenue.
Revenue Rs. 129 crore · Share of consolidated revenue approximately 93% · Year-on-year revenue growth approximately 228% · Large project capacity 50MW AC · Large project capacity 65MW DC · Large project revenue contribution approximately 48% · Order book Rs. 229 crore at September 30 · Maharashtra order Rs. 175 crore · Project cost Rs. 170 crore · O&M component Rs. 5 crore
Outlook: Margins should remain under pressure until execution of the large project is completed in H2 FY27 and H1 FY28; management plans to pursue larger EPC opportunities.
RESCO / IPP
RESCO power sales contributed Rs. 3.33 crore in H1 FY27; 15MW-16MW was running and almost 10MW-11MW was in capital work in progress.
H1 FY27 power-sale revenue Rs. 3.33 crore · Running IPP capacity 15MW to 16MW · Capital work in progress almost 10MW to 11MW · IPP portfolio approximately 25-26MW · SECI tender capacity 3MW · Third-party Reliance Jio project 500KW · Third-party Futaba project 300KW · Rashtrapati Bhawan project 1MW · Ongoing IPP project approximately 10.5MW
Outlook: Management plans to expand RESCO, expects associated debt to rise, and will fund projects 25% from own accruals and 75% through bank finance.
Operations & maintenance
O&M is kept in-house for company-developed and captive projects; the Solarium order includes Rs. 5 crore for three years at one site.
Solarium O&M contract Rs. 5 crore · O&M term 3 years · Contract sites 1 site · Recurring O&M revenue horizon 25 years
Outlook: Management expects O&M to provide recurring fixed income for up to 25 years and will not pursue independent third-party O&M contracts.
BESS
Management discussed BESS as a planned opportunity; its team was ready to pilot it and enter Gujarat once the draft policy is finalised.
Outlook: Management plans to pilot BESS in Gujarat and then pursue opportunities across Indian states after policy finalisation.
LED and US subsidiary
The LED segment generated around Rs. 1.5 crore of turnover; a US subsidiary's revenue and margins were consolidated within Other.
LED turnover around Rs. 1.5 crore
Outlook: Management does not plan to develop LED further and will focus on solar; US subsidiary performance may determine future Other growth.
Balance sheet, capex and funding
- IPO proceeds of Rs. 39.56 crore were fully utilised by September 30, including Rs. 29.85 crore for the Himmat Nagar solar RESCO project.
- An unsecured loan of Rs. 8.50 crore was raised during H1 FY27.
- The cash rate limit was enhanced to Rs. 5 crore.
- A new term loan of Rs. 2.58 crore was obtained for the Rashtrapati Bhawan project.
- Trade receivables and payables increased together for 65MW project funding; management said the net working-capital impact would not be major.
- RESCO projects are funded 25% from own accruals and 75% through bank finance; management expects RESCO debt to increase.
The industry, as management sees it
Management sees ground-mounted solar and RESCO as less competitive and more attractive than rooftop, where bidding pressure is intense. It views BESS as a major Indian-market opportunity, but immediate deployment depends on finalization of Gujarat policy.
Risks management named
- Low-margin fourth-layer EPC order expected to pressure margins through H1 FY28
- Rising receivables require project working capital, partly offset by higher payables
- RESCO expansion is expected to increase debt as 75% of project cost is bank financed
- BESS commercialization timing depends on finalization of Gujarat policy
Q&A
Five analyst turns focused on the RESCO roadmap, order conversion, margins and working capital, funding, BESS, O&M strategy and geographic opportunities. Scrutiny was constructive, with management most guarded on FY28-FY29 capacity targets and quantified geographic opportunities; it was comparatively direct on project economics, funding mix and the rationale for in-house O&M. No repeated questioning or material management pushback emerged.
Not answered directly
- FY28-FY29 RESCO capacity and land/grid pipeline
- Quantified geographic pipeline and project timing
Asked for a number, answered without one
- RESCO capacity for FY28 and FY29: Management gave 15MW-16MW running and almost 10MW-11MW in capital work, but said futuristic figures could not be provided right now.
- EBITDA margin trajectory: Management said margins would stay under pressure through H2 FY27 and H1 FY28 and new projects would carry a healthy margin, without quantifying a recovery.
- RESCO project return threshold: Management compared roof and ground-mount generation, including 20%-25% higher ground-mount output, but gave no return or IRR threshold.
- O&M revenue and margin contribution: Management quantified only Rs. 5 crore of O&M for three years at one site and gave no margin contribution.
- Trade-receivable breakup and drivers: Management attributed the increase to a project-specific working-capital arrangement for 65MW and said higher payables offset it at net working-capital level.
Every question, with its answer
1. RESCO capacity and working capital
Tahir Hyderabadwala, Grobis Fund
Question. With a RESCO portfolio of 15.5 MW projected for FY27 versus 3.8 MW in FY26, what capacity targets and identified land/grid pipeline support FY28-FY29? How much of the ₹220 crore EPC order book is expected to execute in H2 FY27? Why did trade receivables rise from ₹10 crore to ₹80 crore and receivable days reach 106, and what is the breakup?
Answer, Alpeshkumar Agrawal, Chief Financial Officer. Agrawal said 15-16 MW of IPP capacity was running and almost 10-11 MW was capital work in progress, but declined to provide FY28-FY29 capacity or pipeline figures: "we cannot comment right now." He expects 70%-80% of the order book to convert in H2 FY27. On receivables, he said the increase was tied to working capital for the 65 MW project and was accompanied by a similar rise in payables; net working capital was not materially affected and the balance was in line with the prior year.
Follow-up. How much of the EPC order book converts in H2 FY27, and what drove the sharp increase in receivables and receivable days?
Answer. The CFO expects 70%-80% order-book conversion and attributes the receivables increase to the 65 MW project's working-capital requirement, noting a corresponding increase in payables.
Not answered directly.
2. Margins and RESCO unit economics
Rahul Singhania, Individual investor
Question. Was the H1 EBITDA-margin pressure mainly caused by the large 50 MW project or other factors, and how should investors view the margin trajectory over coming quarters? How do rooftop and ground-mounted RESCO economics compare, and what return hurdles does GRE apply before committing capital?
Answer, Alpeshkumar Agrawal and Kamleshkumar Patel, Chief Financial Officer and Managing Director. Agrawal said the pressure is temporary and specific to the low-margin, fourth-layer 50 MW project, whose execution extends into H2 FY27 and H1 FY28; projects being pursued thereafter are at healthy margins. Patel said ground-mounted RESCO is preferred despite higher project cost because tracker generation is 20%-25% higher and remains under GRE's supervision, while rooftop has intense competition and weaker bid pricing. Management did not quantify a return threshold.
Follow-up. How do rooftop and ground-mounted RESCO economics compare, and what capital-return threshold is used for new projects?
Answer. Patel preferred ground mount for higher tracker generation and closer operational control despite higher upfront cost, but gave no quantified return hurdle.
Partly answered.
3. RESCO funding and BESS entry
Sampreeti, Individual investor
Question. As EPC and RESCO expand, what funding requirements are expected, and how will upcoming RESCO projects be financed through internal accruals, debt or project-level finance? Will GRE also evaluate BESS and hybrid renewable opportunities, and would it enter through EPC or own those assets?
Answer, Alpeshkumar Agrawal and Kamleshkumar Patel, Chief Financial Officer and Managing Director. Agrawal said RESCO projects normally follow a 25:25 funding structure, with 25% funded from internal accruals and 75% from bank finance; debt is therefore expected to rise as the RESCO profile expands. Patel said BESS is a major opportunity for India and that GRE follows a pilot-first approach for new technology. Its team is prepared to enter immediately once Gujarat finalizes its BESS policy, using existing GRE projects as initial pilots and then targeting opportunities across Indian states.
Follow-up. Does GRE plan to enter BESS and hybrid renewables, and will it pursue EPC work or own these assets?
Answer. Patel confirmed a pilot-first BESS strategy, beginning at GRE's own sites after Gujarat's policy is finalized before expanding across states.
4. Other segments and O&M strategy
Devansh Shah, Eternal Capital
Question. What activities drive the company's other segments and how is their contribution expected to evolve? Will O&M primarily service GRE-developed projects, or does the company also intend to secure independent O&M contracts from third-party asset owners?
Answer, Alpeshkumar Agrawal and Kamleshkumar Patel, Chief Financial Officer and Managing Director. Agrawal said the 'Others' line includes a US subsidiary and a legacy LED business with about ₹1.5 crore of turnover; GRE does not plan to develop LED further and expects limited growth in this segment apart from any US subsidiary performance. Patel said O&M is restricted to GRE's own and captive customer projects because an in-house team, dedicated SOPs and direct operating data protect output, improve future designs, strengthen customer confidence and provide recurring income for up to 25 years. GRE is not seeking unrelated third-party O&M contracts.
Follow-up. Will GRE seek independent O&M contracts from third-party solar asset owners?
Answer. Patel said no; O&M is confined to GRE-developed and captive customer projects under a dedicated team and SOP.
5. O&M scale, asset funding and geographic expansion
Vishal Singh, Individual investor
Question. How is the O&M business expected to scale over the next two to three years in terms of revenue and margin? How will GRE hold RESCO assets through PPA tenure, and is it considering partnerships or asset monetization to release capital? How has expansion outside Gujarat performed, and is a larger project likely in those markets?
Answer, Kamleshkumar Patel, Managing Director. Patel said the ₹175 crore MAHAGENCO order includes ₹5 crore for specialized O&M over three years at a single site, but gave no broader two-to-three-year O&M revenue or margin forecast. He said there are currently no strategic partnerships or asset-monetization plans for the RESCO portfolio. Geographic response was described as very good and the pipeline as substantial, but management provided no project value, award timing or quantified regional target.
Follow-up. How will GRE hold and finance RESCO assets through their PPA tenure, and what is the scale and timing of the geographic pipeline?
Answer. Patel confirmed no current partnership or asset-monetization plan and described geographic demand as strong, but gave no quantified pipeline or award timing.
Not answered directly.
What was said
Topic by topic, in the order it was spoken
Company Evolution and Solar Focus · Kamleshkumar Patel (Managing Director)
- GRE began in 1999 as a partnership manufacturing CFL products and earth-leakage circuit breakers, converted to a private company in 2008 and a public company in 2024.
- Management entered LED in 2012, then residential solar in 2017-18 before moving into industrial and utility-scale solar for larger, scalable projects.
- The company was renamed GRE Renew Enertech in 2023 and completed its IPO in 2026; this was its first earnings conference call.
EPC and RESCO Business Models · Kamleshkumar Patel (Managing Director)
- Under the EPC model, customers finance the assets while GRE designs, engineers, procures, commissions and receives project revenue, with additional ground-level O&M revenue.
- Under RESCO, GRE invests through equity, debt or wholly owned funds and sells power from rooftop or ground-mounted assets to government buyers or third-party industries.
- Management distinguishes captive projects serving participating industries from non-captive IPP projects selling power into the grid or to unrelated customers.
Turnkey Solar Park Model · Kamleshkumar Patel (Managing Director)
- GRE positions itself as a solar-park developer that aggregates fragmented farmland, negotiates 27- or 29-year leases and handles land purchases, leveling and common facilities.
- The company coordinates with DISCOM and GENCO authorities to identify substations and build connectivity lines, extending the network within the permitted five-kilometre distance.
- Typical clusters are 5 MW or 10 MW and can require 30-35 acres; capacity is allocated according to each customer's historical consumption and electricity bills.
Tracker Technology and Product Quality · Kamleshkumar Patel (Managing Director)
- GRE's specialized tracker follows the sun from east to west instead of leaving panels fixed to the south, capturing radiation for longer than conventional ground-mounted systems.
- Management claims generation of 19-19.5 lakh units per MW versus 15-16 lakh units for fixed-panel systems, supporting higher utilization of installed capacity.
- Projects use branded modules, inverters, transformers, switchgear and cabling to improve durability and reduce lifecycle performance risk.
Captive O&M and Recurring Revenue · Kamleshkumar Patel (Managing Director)
- GRE performs O&M for its own and captive customer projects, stating that service can continue for 25 years and provides recurring revenue with periodic appreciation.
- In-house O&M is intended to protect output, support preventive maintenance and feed operating data into future plant designs.
- GRE began charging new third-party RESCO customers a PPA management fee of 20-25 paise, with 15 paise possible for large groups.
Third-Party Power and IPP Portfolio · Kamleshkumar Patel (Managing Director)
- A 3 MW SECI rooftop IPP portfolio at a stated PPA of ₹5 provides contracted revenue visibility for 25 years across government buildings.
- GRE also operates third-party pilots of 500 kW with Reliance Jio and 300 kW with Futaba, a Maruti Industries subsidiary.
- A 1 MW rooftop project at Rashtrapati Bhawan was under execution and expected to be commissioned in the coming months.
Major Order and Order Book · Kamleshkumar Patel (Managing Director)
- Management secured a ₹175 crore MAHAGENCO order for 50 MW AC and 65 MW DC, comprising ₹170 crore of project cost and ₹5 crore for three years of O&M.
- The order was accepted as a fourth-layer back-to-back sublet with lower margin to satisfy tender qualification criteria and establish utility-scale credentials.
- GRE described its completed and ongoing portfolio as approximately 197 MW and its September 30 order book as ₹229 crore.
H1 FY27 Financial Mix · Alpeshkumar Agrawal (Chief Financial Officer)
- Consolidated revenue from operations rose to ₹139 crore from ₹44 crore, while EBITDA increased to ₹13 crore from ₹6 crore and PAT to ₹9 crore from ₹4 crore.
- EBITDA margin declined to 9.52% from 13.01% and PAT margin to 6.56% from 9.13%, primarily because of the low-margin 50 MW AC/65 MW DC project.
- Solar EPC contributed ₹129 crore, or approximately 93% of consolidated revenue, while RESCO power sales contributed ₹3.33 crore.
- Management cited three-year revenue, EBITDA and PAT CAGRs of 33%, 131% and 141%, with FY26 ROE of 24.53% and ROCE of 31.80%.
IPO Proceeds and Funding · Alpeshkumar Agrawal (Chief Financial Officer)
- All ₹39.56 crore of IPO proceeds had been utilized by September 30, including ₹29.85 crore allocated to the Himmat Nagar solar project.
- GRE raised an additional ₹8.50 crore through an unsecured loan, increased its cash-credit limit to ₹5 crore and secured a ₹2.58 crore term loan for Rashtrapati Bhawan.
- Management stated that funding arrangements were strengthened to support project execution and working-capital requirements.
Forward Operating Priorities · Alpeshkumar Agrawal (Chief Financial Officer)
- Management's immediate priorities are prudent working-capital management, improved execution efficiency and stronger profitability as operations scale.
- Project margins and capital deployment will be monitored closely while GRE pursues larger EPC opportunities.
- Expansion of the RESCO portfolio remains a priority, alongside increased attention to project-level funding and profitability.
In their words
The project accounted for approximately 48% of the first half year revenue, which was executed at a lower margin to establish our execution credentials in the utility-scale solar segment.
We can expect conversion up to 70% to 80% of the order book.
As soon as BESS is introduced in Gujarat, we will immediately come to BESS in Gujarat.
To check next time
What management committed to on this call, or the dates they gave.
- Check whether 70%-80% of the Rs. 229 crore order book converts during H2 FY27.
- Track EBITDA and PAT margin pressure from the 50MW AC/65MW DC project through H2 FY27 and H1 FY28.
- Monitor receivables and payables on the 65MW project as H2 execution increases funding needs.
- Check commissioning of the 1MW Rashtrapati Bhawan and approximately 10.5MW ongoing IPP projects in the coming months.
- Watch the 10MW-11MW RESCO capital work in progress moving into operating capacity.
- Track Gujarat's BESS policy finalisation and the planned pilot; management said entry would follow immediately.
Transcript
We have not transcribed this call's recording. Read the company's transcript (PDF).
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Mon 16 Nov 2026 | ₹210.05 | −10.62% | +0.14% |
From the close of Wed 11 Nov 2026, ₹235.00: the call began at 17:00 IST, after the market closed, so that day's close is the base. Adjusted daily closes; the move includes everything else that happened in those sessions.