Greenleaf Envirotech Q2 FY27 earnings call
In brief
Management reported H1 FY27 revenue of ₹28.62 crore, up 35.8%, and targeted April 2027 commissioning of the 10 MLD CETP Phase 1.
- Management's tone
- Confident
- What was said
- Mixed
- Guidance
- Guidance cut
- Analyst pushback
- Medium
- H1 FY27 revenue rose 35.8% YoY to ₹28.62 crore, but EBITDA rose 13.8% to ₹4.74 crore and PAT rose 5.5% to ₹3.04 crore.
- CETP Phase 1 was about 50% complete; commissioning moved from March to April 2027 due to monsoon and equipment delivery.
- The order book was ₹122 crore at 30 September 2026; about 50% was planned for execution in H2 FY27.
- Management targeted recurring revenue at about 25% of total revenue over the next three to four years.
- The spent-acid pilot achieved about 80% acid recovery and 80% metal removal; first revenue was expected in FY28.
An AI read of our transcription of the recording · the filing
The numbers
The quarter, Q2 FY27
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹28.6 cr | +35.8% | — | |
| EPS (₹) | ₹5.13 | −17.8% | — |
From the company's filed results for the quarter ended 30 Sept 2026 (consolidated), not from the call.
Where management's figures differ from the filing
- Revenue period basis: said H1 FY27 revenue from operations: ₹28.62 crore, up 35.8% YoY; filed Q2 FY27 Revenue: ₹28.62 cr (+35.8% YoY). The amount and growth rate match, but management called it H1 FY27 while the filed figure is for the quarter ended 30 September 2026.
What moved the numbers, as management explained it
- Revenue rose 35.8% YoY to ₹28.62 crore as management said it scaled the business and executed projects; no volume or price bridge was provided.
- EBITDA rose 13.8% to ₹4.74 crore: project-level margins did not fall, but OPEX increased after employee investment, development of a sales team and hiring of a project head.
- PAT rose 5.5% to ₹3.04 crore; higher assets increased depreciation, which management said also reduced the PAT margin.
The numbers management led with
- CETP Phase 1 project cost: Approximately ₹35 crore
- Live bidding pipeline: Approximately ₹185 crore of projects bid with results pending
- Order book: Approximately ₹122 crore as of September 30, 2026, with about 50% planned for execution in H2 FY27
- Recurring revenue target: Approximately 25% of total revenue over the next three to four years
Guidance
Guidance on this call
| What | For | What management said |
|---|---|---|
| CETP Phase 1 commissioning (Science Excel CETP) | FY28 | Management targeted commissioning of CETP Phase 1 in April 2027. |
| CETP revenue at 100% capacity (Science Excel CETP) | — | At 100% capacity, CETP Phase 1 was expected to earn revenue of around ₹80 lakh per month. |
| CETP EBITDA margin (Science Excel CETP) | — | CETP Phase 1 EBITDA margin was expected to be about 40%. |
| Phase 1 estimated project cost (Science Excel CETP) | — | The estimated cost of CETP Phase 1 is approximately ₹35 crore. |
| Phase 1 remaining project spend (Science Excel CETP) | — | Around ₹22 crore will remain and will be invested before commissioning. |
| CETP project IRR (Science Excel CETP) | — | CETP Phase 1 project IRR was expected to be around 18-20%. |
| Recurring revenue in total revenue | — | Recurring revenue was targeted at around 25% of total revenue over the next three to four years. |
| New projects bid or acquired (Environmental EPC and project execution) | — | Management targeted bidding for or acquiring around ₹200 crore of new projects over the next six months. |
| Order book execution (Environmental EPC and project execution) | H2 FY27 | Around 50% of the ₹122 crore order book was planned for execution in H2 FY27. |
| Spent acid first revenue (Spent acid regeneration and purification) | FY28 | First revenue from spent acid regeneration was expected in FY28. |
| Phase 2 planning trigger (Science Excel CETP) | — | Phase 2 planning was to start once Phase 1 utilization reached about 90%. |
| Phase 2 construction start (Science Excel CETP) | FY28 | Phase 2 construction was planned after three to four months of FY28. |
| EBITDA margin match-up | — | EBITDA margin was expected to match up over the next one year as revenue grows. |
| PAT margin match-up | — | PAT margin was expected to match up over the next one year as revenue grows. |
| CETP Phase 1 capacity booking (Science Excel CETP) | — | All 100% of CETP Phase 1 capacity was expected to be booked within four to five months. |
The business
By business
Environmental EPC and project execution
Core projects generated about 90% of revenue, mostly from government projects; management also reported a ₹122 crore order book and capacity to run 8-10 large projects in parallel.
Revenue mix ~90% · Order book ₹122 crore as of 30 September 2026 · Live bids ₹185 crore · Parallel execution capacity 8-10 large projects · Project focus ₹10-50 crore
Outlook: Management planned continued wastewater EPC growth, selective pursuit of larger projects and about ₹200 crore of new bids or orders over the next six months.
O&M
O&M supplied around 5% of revenue and was one of the three services management planned to build into recurring revenue.
Revenue mix ~5%
Outlook: Management planned to raise recurring revenue from O&M, laboratory/consulting and CETP to around 25% of total revenue over the next three to four years.
Laboratory and consulting
Laboratory and consulting activities together supplied around 5% of revenue and were being positioned as a recurring-revenue service.
Combined revenue mix ~5%
Outlook: Management planned to raise recurring revenue from O&M, laboratory/consulting and CETP to around 25% of total revenue over the next three to four years.
Science Excel CETP
Phase 1 of the 10 MLD Science Excel CETP was about 50% complete; 60 member units had committed 75% of capacity, with commissioning targeted for April 2027.
Total proposed capacity 20 MLD · Phase 1 capacity 10 MLD · Phase 2 capacity 10 MLD · Estimated Phase 1 cost ₹35 crore · Construction progress ~50% at September 2026 · Member commitments 60 units · Committed Phase 1 capacity ~75% · Revenue at 100% capacity ₹80 lakh/month · Expected EBITDA margin ~40% · Expected project IRR 18-20%
Outlook: Phase 1 commissioning was targeted for April 2027; Phase 2 construction was planned in FY28 after about 3-4 months and once Phase 1 utilization reached about 90%.
Technology-led solutions
GAC SBR was deployed in two government projects with its patent draft about 99% frozen; the spent-acid pilot achieved about 80% acid recovery and 80% metal removal.
Government projects with GAC SBR deployment 2 · Patent draft ~99% frozen · Pilot acid recovery ~80% · Pilot metal and impurity removal ~80%
Outlook: GAC SBR patent filing and spent-acid commercialization were next steps; first spent-acid revenue was expected in FY28, while MBR and activated-carbon regeneration remained at pilot stage.
Balance sheet, capex and funding
- CETP Phase 1 cost was estimated at ₹35 crore; about ₹13 crore had been invested by September 2026 and about ₹22 crore remained.
- The remaining ₹22 crore was to come from about ₹11.5 crore of bank funding, ₹5.5 crore from existing business or equity and ₹5 crore of member deposits.
- Around ₹3.5 crore had been collected from members; the balance of committed deposits was still due.
- Trade receivables were ₹26 crore at September 2026; around 10% was older than 120 days and management said none was disputed.
- Management said cash conversion and working-capital efficiency would remain priorities as the business scaled.
- Phase 2 required additional capital, planned from bank loans, member units and current Greenleaf and WaterTech businesses; no new equity plan was stated.
The industry, as management sees it
Management expects evolving environmental-compliance requirements and the need for resource recovery to sustain demand for environmental engineering and treatment solutions, with technology becoming increasingly important for industrial clients.
Risks management named
- CETP commissioning slipped one month to April 2027 due to monsoon and equipment delivery timing.
- Phase 2 needs more capital, planned from bank loans, member funds and internal cash; no new equity plan was stated.
- Around 20% of projects may be delayed by government approvals, land allocation or funding delays.
- About 10% of September receivables were over 120 days old due to final handover and final-billing formalities.
- GAC SBR patent and commercial validation remain pending; MBR and activated-carbon regeneration are at pilot stage.
Q&A
Detailed investor scrutiny focused on CETP economics, timing, funding and Phase 2 requirements, followed by order-book execution and receivables quality. Management was direct and numeric on most topics, although it did not quantify existing laboratory and O&M profitability or the exact Phase 2 capital requirement; no strong management pushback was visible.
Not answered directly
- Profitability of the existing laboratory and O&M businesses
Asked for a number, answered without one
- O&M and laboratory/consulting profitability: Management quantified revenue mix at about 5% for each business but gave no separate profit or margin figures.
- Year-ago employee count: Management gave the current count as around 165 but did not provide the prior-year count.
- Historical bid-to-order conversion rate: Management said about ₹40 crore of a roughly ₹200 crore bid pool had converted in six months and cited a new ₹200 crore target, but gave no conversion rate.
Every question, with its answer
1. Margin compression
Vin Straphalia, Individual Investor
Question. You reported exceptional revenue growth but much slower EBITDA and profit after tax growth. What caused the margin compression, and how should EBITDA and PAT margins develop?
Answer, Kalpesh Ghoti, Managing Director and Chairman. Management said project-level margins did not fall; the pressure came mainly from operating expenditure as the company invested in employees, a sales team and a project head to improve execution and win new projects. Higher asset additions also increased depreciation. Management expects EBITDA and PAT margins to catch up as revenue grows over the next year.
2. Revenue mix and headcount
Vin Straphalia, Individual Investor
Question. Please provide the revenue breakup across EPC or projects, laboratory, consultancy and other activities, along with employee count at the end of last year and currently.
Answer, Kalpesh Ghoti, Managing Director and Chairman. Approximately 90% of revenue came from projects, with the majority from government projects. O&M contributed about 5%, while laboratory and consultancy together contributed about 5%. Management did not provide a prior-year headcount comparison.
Follow-up. What is the total employment count as of now?
Answer. Management said the current total employment count was around 165.
Partly answered.
3. Competitive differentiation
Vin Straphalia, Individual Investor
Question. Greenleaf is much smaller than larger environmental companies. What is its competitive edge or moat, and how can it compete with those larger players?
Answer, Kalpesh Ghoti, Managing Director and Chairman. Management highlighted an integrated in-house value chain covering testing, design engineering, civil construction, electromechanical design and supply, operation and maintenance, and compliance services. It also cited lower management and operating costs than larger EPC firms, a focus on projects of roughly ₹10–50 crore, and differentiation through GAC SBR and spent-acid regeneration technologies.
4. Order bidding and execution capacity
Rudra Butka, Dhanalakshmi Financial Advisors
Question. What is the company's current live bidding pipeline, bidding capacity and realistic capacity to execute multiple projects simultaneously?
Answer, Kalpesh Ghoti, Managing Director and Chairman. Management said projects with results pending totalled approximately ₹185 crore. It has about 45 project managers and engineers and believes it can execute approximately eight to ten large projects in parallel.
Follow-up. Sorry, I did not hear the number. How many projects can be executed simultaneously?
Answer. Management reiterated that approximately eight to ten large projects can be handled in parallel with teams led by the 45 engineers and managers.
5. Project timelines and delays
Rudra Butka, Dhanalakshmi Financial Advisors
Question. What has been the historical order-to-completion timeline, and what percentage of projects typically experiences delays from issues such as land availability or funding?
Answer, Kalpesh Ghoti, Managing Director and Chairman. Management said smaller projects generally take around six months, larger projects around 24 months, and the average order-to-completion period is 12–18 months. Around 20% of projects may be delayed because of government approvals, land allocation or funding delays.
6. Order book and execution schedule
Rudra Butka, Dhanalakshmi Financial Advisors
Question. What is the current order book and how much is expected to be executed during the remainder of the financial year?
Answer, Kalpesh Ghoti, Managing Director and Chairman. Management said the order book was approximately ₹122 crore as of September 30, 2026. Around 50% was planned for execution in H2 FY27, with the balance expected to be executed in FY28 and FY29.
7. Recurring revenue mix
Himanshu Bhati, Individual Investor
Question. What are the present scale and profitability of the laboratory and O&M businesses, and how much does management plan to increase their contribution to recurring revenue?
Answer, Kalpesh Ghoti, Managing Director and Chairman. Management said laboratory and consultancy contribute about 5% of revenue and O&M another 5%. It plans to increase recurring revenue through O&M, laboratory and consultancy, and the CETP, targeting approximately 25% of total revenue over the next three to four years. It did not quantify the profitability of the existing laboratory and O&M activities.
Not answered directly.
8. CETP unit economics
Himanshu Bhati, Individual Investor
Question. Please explain Phase 1 CETP economics, including expected revenue, operating expenses, EBITDA margin, payback period and project IRR.
Answer, Kalpesh Ghoti, Managing Director and Chairman. Management estimated Phase 1 cost at around ₹35 crore. At full capacity, the project should generate approximately ₹80 lakh per month, with power, chemicals and manpower expenses of roughly ₹45–48 lakh per month. Expected EBITDA margin is about 40%, payback is around five years and project IRR is approximately 18–20%.
9. CETP funding mix
Naman Garg, Individual Investor
Question. How much of the ₹35 crore project cost has already been invested, what remains to be funded, and what is the funding mix between internal accruals, debt and member deposits?
Answer, Kalpesh Ghoti, Managing Director and Chairman. Management said approximately ₹13 crore had been invested by September, leaving about ₹22 crore to be spent before commissioning. The remaining funding was planned as approximately ₹11.5 crore from a bank, ₹5.5 crore from the existing business or equity, and around ₹5 crore from committed member deposits still to be collected.
10. Member deposits
Naman Garg, Individual Investor
Question. How much of the previously indicated member deposits has actually been collected in cash, and how much remains represented by commitments from industrial members?
Answer, Kalpesh Ghoti, Managing Director and Chairman. Management said approximately ₹3.5 crore had been received from members and the remaining committed deposits were still due for collection.
11. CETP utilisation assumptions
Naman Garg, Individual Investor
Question. What assumptions underpin the expected ₹80 lakh monthly CETP revenue, and what EBITDA margin should be achievable at 75% and 100% capacity utilisation?
Answer, Kalpesh Ghoti, Managing Director and Chairman. Management said 60 members had committed about 75% of Phase 1 capacity and that, with roughly four to five months remaining, it expected to cover almost the full capacity. It reiterated an expected EBITDA margin of around 40%.
12. CETP commissioning timeline and progress
Siddharth Kumar, Nodstar Capital
Question. The June call indicated March 2027 commissioning for the 10 MLD CETP, while the November presentation shows April 2027. What is current progress and what caused the change?
Answer, Kalpesh Ghoti, Managing Director and Chairman. Management said overall construction was 50% complete as of September. The target moved by one month because of the monsoon and equipment-delivery schedule. Remaining work includes equipment supply and installation, collection and supply-network links, and GPCB consent to operate; management sees no regulatory obstacle and still plans to commission in April 2027.
Follow-up. How does 70% civil-work completion reported in June reconcile with 50% overall construction progress in September?
Answer. Management clarified that 70% referred only to civil work, while the 50% overall figure included civil work plus electromechanical equipment supply and installation.
13. CETP Phase 2 plan and funding
Siddharth Kumar, Nodstar Capital
Question. What conditions and utilisation thresholds must be met before Phase 2 is commissioned, and when might Phase 2 construction begin?
Answer, Kalpesh Ghoti. Management said Phase 2 planning would begin once Phase 1 utilisation reached approximately 90%. It expects to start Phase 2 construction around three to four months into FY28 if opportunities and demand remain favourable.
Follow-up. Would Phase 2 require additional capital expenditure, and how does management plan to fund it?
Answer. Management confirmed that additional capital would be required. Phase 2 funding is planned from bank loans, existing and future member units, and internal business cash; management stated that it has no new equity plan for Greenleaf or WaterTech.
14. Order-book conversion and bidding target
Siddharth Kumar, Nodstar Capital
Question. What has been the conversion rate from the roughly ₹200 crore of projects bid on, and what further order target is management setting?
Answer, Kalpesh Ghoti, Managing Director and Chairman. Management said approximately ₹40 crore of the recently bid projects had been converted into orders during the last six months. Another order of about ₹16.7 crore was pending after receipt of an LOI. Management targeted about ₹200 crore of new project bids or orders during the next six months.
15. Receivables quality
Siddharth Kumar, Nodstar Capital
Question. What is the current trade-receivable position after the collections reported during April and May 2026?
Answer, Kalpesh Ghoti, Managing Director and Chairman. Management said almost ₹35 crore had been collected from the ₹38 crore March 2026 receivable balance during the last six months. Receivables stood at ₹26 crore as of September 2026, with around 10% older than 120 days and the remainder within 120 days.
Follow-up. Are there any significant disputed or overdue balances?
Answer. Management said nothing was disputed. The delayed portion related to projects in final handover or final-billing stages, where government formalities can take additional time.
16. GAC SBR patent and deployment
Sahil Gandhi, Individual Investor
Question. What is the latest status of the GAC SBR patent application, and has the technology been commercially validated through a live installation?
Answer, Kalpesh Ghoti, Managing Director and Chairman. Management said the patent draft was approximately 99% frozen and the application was expected shortly. The technology had already been applied in two government projects that were under execution.
17. Spent-acid commercialisation
Sahil Gandhi, Individual Investor
Question. What is the current commercial status of spent-acid regeneration and purification, and when can the technology make its first meaningful revenue contribution?
Answer, Kalpesh Ghoti. Management said the first pilot achieved approximately 80% acid recovery, 80% removal of metal impurities and a 75% reduction in lead-slag generation. Commercial discussions were ongoing, with the first revenue expected in FY28.
18. MBR and activated-carbon readiness
Sahil Gandhi, Individual Investor
Question. What is the current deployment stage of activated-carbon regeneration and MBR technology, and are there confirmed customers, orders or commercial deployments?
Answer, Kalpesh Ghoti, Managing Director and Chairman. Management said MBR and activated-carbon regeneration remained at the pilot stage and that it would update investors when confirmed orders were available.
What was said
Topic by topic, in the order it was spoken
Company Evolution and Market Positioning · Kalpesh Ghoti (Managing Director and Chairman)
- Greenleaf began in 2010 as an environmental testing laboratory in Surat and evolved into an integrated environmental engineering company.
- Its capabilities now cover testing, design, build, operation and maintenance across industrial and infrastructure environmental projects.
- The company is moving beyond EPC contracting towards owning and developing environmental infrastructure assets.
- A footprint across 12 Indian states reflects accumulated technical expertise, customer relationships and project-execution capability.
- The stated objective is to build on this base while moving into higher-value and more recurring business opportunities.
Science Excel CETP Phase 1 · Kalpesh Ghoti (Managing Director and Chairman)
- The CETP is being developed through wholly owned subsidiary Greenleaf EcoInfra Private Limited, with total planned capacity of 20 MLD in two 10 MLD phases.
- Phase 1 has an estimated project cost of approximately ₹35 crore and was about 50% complete as of September 2026.
- Sixty member units have committed to about 75% of Phase 1 capacity.
- Management targets April 2027 commissioning, with revenue expected from membership fees and recurring effluent-treatment charges.
- The immediate priority is disciplined completion and stabilisation, after which similar infrastructure opportunities may be evaluated.
Technology-Led Environmental Solutions · Kalpesh Ghoti (Managing Director and Chairman)
- The in-house GAC SBR wastewater technology has been deployed in two government projects and the patent application process is progressing.
- The spent-acid regeneration initiative aims to help industries recover and reuse acid instead of disposing of it as waste.
- The first Indian pilot achieved approximately 80% acid recovery and 80% removal of metals and impurities.
- Management sees specialised technology as a route to expanding beyond conventional project execution, subject to customer acceptance and commercial validation.
H1 FY27 Performance and Earnings Quality · Kalpesh Ghoti (Managing Director and Chairman)
- Management described FY26 as a strong year, attributing the performance to business scaling and project execution.
- H1 FY27 revenue from operations rose 35.8% year on year to ₹28.62 crore from ₹21.08 crore.
- H1 EBITDA rose 13.8% to ₹4.74 crore, while profit after tax increased 5.5% to ₹3.04 crore.
- Management said it is equally focused on earnings quality through project execution, operating efficiency, cost discipline and cash conversion.
Forward Priorities and Capital Discipline · Kalpesh Ghoti (Managing Director and Chairman)
- Management plans to continue growing core wastewater EPC and O&M while selectively pursuing large projects where it has a technical and execution advantage.
- Completing and stabilising CETP Phase 1 on schedule is central to the transition towards infrastructure ownership and recurring revenue.
- Margin improvement, operating efficiency, cash conversion and working-capital discipline remain priorities as the business scales.
- GAC SBR and spent-acid purification require further validation, customer acceptance and gradual commercialisation.
- Management framed sustainable growth around disciplined capital allocation, customer relationships and healthy returns on invested capital.
In their words
Overall, the project level margins did not fall, and the pressures came from mainly OPEX.
Target moved by one month because of monsoon and equipment delivery schedule.
For MBR and activated carbon regeneration, we are still at pilot stage, and we will update you when there are any confirmed orders.
To check next time
What management committed to on this call, or the dates they gave.
- Track Phase 1 construction, equipment installation, collection-network links and GPCB consent against the April 2027 commissioning target.
- Track deployment of the remaining ₹22 crore Phase 1 funding, including bank funding and collection of member deposits.
- Check H2 FY27 execution of ~50% of the ₹122 crore order book and progress toward the ₹200 crore six-month bidding target.
- Check whether OPEX and depreciation pressure begins to reverse in EBITDA and PAT margins over management's one-year horizon.
- Check GAC SBR patent filing and spent-acid commercial orders ahead of the FY28 first-revenue expectation.
- Check readiness to plan Phase 2 once Phase 1 utilization approaches 90% and the FY28 construction timing.
Transcript
Read along with the recording
The whole call, 167 lines from 10 speakers over 33:59. Click any line to hear it, jump to the Q&A, or find a word. Free with an account.
The stock after the call
No session has closed since the call yet.
From the close of Thu 19 Nov 2026, ₹99.85: the last close before the call, which began at 11:00 IST. Adjusted daily closes; the move includes everything else that happened in those sessions.