Insolation Energy Q2 FY27 earnings call

Mon 16 Nov 202615:30 ISTINA

In brief

Q2 revenue was ₹836.69 crore; management targets 4.5 gigawatt cell commissioning in Q4 FY27 and expects H2 EBITDA margin to improve.

Management's tone
Mixed
What was said
Mixed
Guidance
Guidance cut
Analyst pushback
Medium
Stock, next session
−0.34% (Nifty 50 +0.38%)
  • Management reported Q2 revenue of ₹836.69 crore (+96.45% YoY), EBITDA of ₹63.44 crore and PAT of ₹25.06 crore, with a 3% PAT margin.
  • H1 revenue was ₹1,582 crore (+100.56%), EBITDA ₹140 crore and PAT ₹63.08 crore; EBITDA margin was 8.87%.
  • Management expects H2 FY27 EBITDA margin to improve and FY27 margin to return to FY26 levels.
  • The order book was approximately 2.2 gigawatt, with 1.3 gigawatt scheduled for delivery by March 2027.
  • The 4.5 gigawatt TOPCon cell line targets first commercial operations in Q4 FY27.

An AI read of our transcription of the recording · the filing

The numbers

The quarter, Q2 FY27

This quarterA year agoLast quarterMargin
Revenue₹837 cr+7.7%+12.9%
EBITDA (excl. other income)₹63.3 cr−37.8%−12.3%7.6% (13.1% a year ago)
Net profit₹26.1 cr−67.4%−29.6%3.1% (10.3% a year ago)
EPS (₹)₹1.14−68.6%−34.1%

From the company's filed results for the quarter ended 30 Sept 2026 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

Where management's figures differ from the filing

  • Q2 revenue YoY growth: said 96.45% YoY from a stated Q2 FY26 base of ₹425.90 crore; filed ₹836.53 crore; +7.7% YoY. Management compared Q2 FY27 with ₹425.90 crore and cited broad demand; it did not reconcile this base with the filed +7.7% comparison.
  • Q2 EBITDA YoY growth: said 13.32% YoY from a stated Q2 FY26 base of ₹59.55 crore; filed -37.8% YoY. Management compared with a stated Q2 FY26 EBITDA of ₹59.55 crore; no reconciliation to the filed -37.8% comparison was provided.
  • Q2 net profit: said ₹25.06 crore; filed ₹26.08 crore; margin 3.1%. No reconciliation was provided; management only linked the 3% PAT margin to higher depreciation and finance costs.
  • Q2 net profit YoY comparison: said ₹25.06 crore versus ₹36.95 crore in Q2 FY26; filed -67.4% YoY. Management gave current and prior-year PAT but no growth rate; it did not reconcile its comparison with the filed -67.4% decline.

What moved the numbers, as management explained it

  • Q2 revenue rose 96.45% YoY to ₹836.69 crore, supported by demand across government programs, utility, EPC, commercial and industrial, and B2C rooftop solar.
  • Q2 EBITDA margin was 7.5% as prevailing industry pricing dynamics pressured profitability; H1 margin was 8.87% versus 14.43% a year earlier.
  • Elevated input costs were also cited as a driver of H1 EBITDA-margin compression, alongside lower industry pricing.
  • Q2 PAT margin was 3% because depreciation and finance costs increased; H1 PAT was ₹63.08 crore versus ₹80.07 crore.
  • Management could not quantify how much margin compression came from lower realisations versus higher input costs because of global market dynamics.

The numbers management led with

  • Total order book: Approximately 2.2 GW
  • Proposed order pipeline: Approximately 2.5 GW under evaluation
  • Top-con cell capacity: 4.5 GW, with commercial operations targeted for Q4 FY27
  • Aluminium frame plant capacity: 18,000 metric tons per annum, with commercial operations targeted for Q3 FY27

Guidance

Guidance on this call

WhatForWhat management said
Full-year FY27 EBITDA and marginFY27EBITDA margin should recover over the next two quarters; full-year FY27 EBITDA and margin are expected to return to FY26 levels.
4.5 gigawatt TOPCon cell commercial operations (TOPCon cell manufacturing)Q4 FY27First commercial operations for the 4.5 gigawatt TOPCon cell facility are targeted for Q4 FY27.
Cell-line utilization (TOPCon cell manufacturing)FY28The cell line is expected to reach full utilization in FY28, with 60-65% utilization in its first full year.
EBITDA margin at full cell-line operationFY28When fully operational, the cell facility is expected to take EBITDA margin up to around 20%.
IPP portfolio capacity (IPP projects)FY27The IPP portfolio is targeting more than 400 megawatt by FY27.
Scheduled order-book delivery (Module manufacturing)FY27Orders worth 1.3 gigawatt are scheduled for delivery by March 2027.
Annual IPP revenue (IPP projects)FY28Completed IPP projects are expected to generate ₹180-200 crore of annual revenue from FY28.
IPP project investment (IPP projects)FY27The 300 megawatt IPP project is expected to cost ₹800-900 crore by March 2027.
Aluminium frame commercial operation (Aluminium frame manufacturing)Q3 FY27Commercial operation of the 18,000 metric ton per annum aluminium plant is targeted for Q3 FY27 and before December 31, 2026.
Aluminium frame-set saving (Aluminium frame manufacturing)—The aluminium frame plant is expected to save ₹50-60 per frame set.
Ingot/wafer plant capex (Ingot and wafer integration)FY28Ingot and wafer integration is planned after about one year at a total cost of ₹700-900 crore.
Ingot/wafer machinery cost with utilities (Ingot and wafer integration)FY28Ingot/wafer machinery with utilities is currently expected to cost ₹450-500 crore per gigawatt.
Hybrid tandem module efficiency (Hybrid tandem modules)CY29The Kellogg's partnership targets module efficiency of up to 29% by end-2029.
Cell-factory machinery dispatch (TOPCon cell manufacturing)Q3 FY27Cell-factory machinery dispatch is expected by the end of November 2026.
Long-term debt-to-equity ceiling—Debt-to-equity may temporarily reach 2:1-2.5:1; longer term it is expected to be 2:1 or lower.

What changed since the Wed 27 May 2026 call

WhatOn the Wed 27 May 2026 callOn this call
FY27 EBITDA margin (cut)FY27 EBITDA margin guided at 14-15%.Management said 14% was unlikely and would guide after Q3; H2 should be better than H1's 8.87%.
4.5 gigawatt cell line commissioning (held)COD pushed to Q4 FY27, with full 4.5 gigawatt ramp by Q1 FY28.First commercial operations remain targeted for Q4 FY27; full utilization was described for FY28.
FY28 EBITDA margin (held)FY28 EBITDA margin guided to expand to 20%+ post the cell ramp.Management said EBITDA could reach around 20% when the cell plant is fully operational.
FY28 revenue guidance (not repeated)First-time FY28 guidance: revenue above ₹5,000 crore.Not mentioned
IPP portfolio (raised)Scale IPP/KUSUM portfolio to 400 MW by FY27.Portfolio target remained 400 MW+ by FY27; approximately 70 MW was executed in H1 FY27.
Distribution network (raised)700+ channel partners and 25,000+ customers.More than 1,000 channel partners and over 40,000 customers.
FY27 capex plan (not repeated)FY27 capex ~₹2,500 crore: ₹1,500 crore cell line and ₹1,000 crore KUSUM/IPP.No equivalent total was stated; aluminium capex was ~₹100 crore and the 300 MW IPP project was ₹800-900 crore.
Aluminium frame commercialisation (new)Aluminium frame was included in the integrated manufacturing-stack priority.Trials were underway; commercial operation was targeted from Q3 FY27 and before December 31, 2026.

The business

By business

Module manufacturing

Q2 revenue rose 96.45% YoY to ₹836.69 crore and H1 revenue rose 100.56% to ₹1,582 crore; H1 dispatch was close to 1 gigawatt, with 20% DCR and 80% non-DCR.

Q2 revenue ₹836.69 crore · Q2 revenue growth 96.45% YoY · Q2 EBITDA ₹63.44 crore · Q2 EBITDA growth 13.32% YoY · Q2 EBITDA margin 7.5% · H1 revenue ₹1,582 crore · H1 revenue growth 100.56% YoY · H1 EBITDA ₹140.31 crore · H1 EBITDA growth 23.3% YoY · H1 EBITDA margin 8.87% · H1 module dispatch close to 1 gigawatt · DCR mix approximately 20% · Non-DCR mix approximately 80% · Capacity utilization over 60% · Order book approximately 2.2 gigawatt · Delivery scheduled 1.3 gigawatt by March 2027

Outlook: Management expects H2 FY27 EBITDA margin to improve; the 1.3 gigawatt order tranche is scheduled for delivery by March 2027, with new orders arriving on a rolling basis.

TOPCon cell manufacturing

The 4.5 gigawatt TOPCon facility at Nelamaduram had completed civil work and PV building erection; utilities were ordered and machinery installation was underway.

Capacity 4.5 gigawatt · Proposed pipeline 2.5 gigawatt · FY28 first-year utilization 60-65% · Current cell price ₹13.25-13.75 per watt

Outlook: First commercial operations are targeted for Q4 FY27; full utilization is expected in FY28, with 60-65% utilization in the first full year.

Aluminium frame manufacturing

The 18,000 metric ton per annum project had completed civil work and building construction; machinery was installed and trials were underway.

Capacity 18,000 metric ton per annum · Allocated capex approximately ₹100 crore · Expected savings ₹50-60 per frame set · Captive-use share initially 65% · Market-sale share initially 35%

Outlook: Commercial operation is targeted from Q3 FY27 and before December 31, 2026; the plant is expected to save ₹50-60 per frame set.

Hybrid tandem modules

INA entered a five-year Kellogg's USA partnership to develop 3 gigawatt of hybrid tandem modules at Jaipur's Savardha facility, combining N-type TOPCon with energy-producing glass.

Planned module capacity 3 gigawatt · Module efficiency up to 29% by end-2029

Outlook: The partnership targets module efficiency of up to 29% by end-2029, with tandem modules expected to start in India in 2029.

IPP and KUSUM projects

Management said approximately 70 megawatt of solar projects were executed in H1 FY27 while the company continued developing a 400 megawatt-plus IPP portfolio.

H1 project execution approximately 70 megawatt · Portfolio target 400+ megawatt by FY27 · Project scale 300 megawatt · Project cost ₹800-900 crore by March 2027 · Annual revenue ₹180-200 crore from FY28

Outlook: The portfolio targets 400+ megawatt by FY27; the 300 megawatt project is expected to cost ₹800-900 crore by March 2027 and contribute ₹180-200 crore annually from FY28.

Distribution network

The network expanded beyond 1,000 channel partners and 40,000 customers; a Ujja 4 partner meet drew more than 700 partners, and 40,000 homes were solarized under PM Surya Ghar Yojana.

Channel partners more than 1,000 · Customers over 40,000 · Ujja 4 partner-meeting attendance more than 700 · Homes solarized 40,000

Balance sheet, capex and funding

  • Manufacturing-expansion funding lines were described as fully secured; no amount was stated.
  • Funding limits for IPP projects were also described as secured; no amount was stated.
  • Aluminium-frame capex was allocated at approximately ₹100 crore and funded through internal accruals.
  • Debt-to-equity may temporarily exceed 2:1 or 2.5:1 during expansion; management expects 2:1 or lower longer term.
  • The 300 megawatt IPP project was expected to cost ₹800-900 crore by March 2027.
  • Ingot/wafer integration was planned after about one year at ₹700-900 crore, with machinery at ₹450-500 crore per gigawatt with utilities and internal-accrual funding.

The industry, as management sees it

Management expects global supply-chain and freight pressure to ease over the next two quarters, supporting a recovery in solar manufacturing margins. It also expects greater domestic value addition and possible industry consolidation in FY28, while India's power demand remains structurally strong over the next decade.

Risks management named

  • Industry pricing, input-cost and freight volatility could delay EBITDA margin recovery
  • Chinese export controls could affect future equipment orders and new cell supplies
  • Cell and aluminium plant commissioning, ramp-up and utilization execution
  • Debt and finance costs are rising with the expansion programme
  • Wafer and ingot capex estimates remain unsettled and future funding depends on accruals

Q&A

Margin recovery and commissioning dates dominated the discussion, with management repeatedly pressed on whether FY27 EBITDA margin could reach 14% but declining to provide a numerical range before Q3 results. Follow-ups concentrated on cell utilization and IPP economics, Chinese equipment dispatch, capex funding, leverage and industry consolidation. Management generally offered operational detail, although revenue targets, the margin bridge and several capital-allocation questions were only partially answered.

Not answered directly

  • FY27 EBITDA margin range
  • ₹4,000 crore revenue target
  • Realization-versus-input-cost margin bridge
  • Final utility-inclusive ingot and wafer capex

Asked for a number, answered without one

  • FY27 EBITDA margin: Management would provide background after Q3 results; H2 should exceed H1's 8.87%, but an FY26-like margin was not assured.
  • Q2 module dispatch volume: Management gave H1 dispatch as close to 1 gigawatt and a 20% DCR/80% non-DCR mix, but did not provide a Q2 volume.
  • Margin compression attribution: Management said it was very difficult to quantify because of global market dynamics over the prior three to four months, and only hoped margins would recover in H2 FY27.
  • Consolidated revenue target: Management asked how that level would be achieved and did not confirm a revenue target or provide a replacement figure.
  • Ingot/wafer funding split: Management said internal accruals from better cell-line margins would be reinvested and net worth would improve, without specifying a funding split or debt quantum.

Every question, with its answer

  1. 1. Cell commissioning schedule

    Mukesh Agarwal, Turbo

    Question. Will the full 4.5 GW cell line be commissioned and commercially operational by month-end, as suggested?

    Answer, Management. Management corrected that the entire 4.5 GW line would be brought in together, but not in the current month. First commercial operations are targeted for Q4 FY27.

  2. 2. FY27 EBITDA margin and finance costs

    Lakshmi Kant Rathiya, NERI

    Question. Can FY27 EBITDA margin close near 14%, matching FY26, despite the H1 FY27 margin of 8.87%?

    Answer, Ravi Dusad, Chief Financial Officer. The CFO said a 14% margin appears unlikely because of international market disruption, dollar prices, freight and raw-material costs. H2 FY27 should improve over H1 FY27, but management indicated the full-year close could be between current levels and FY26 rather than fully matching FY26. A precise range was deferred until after Q3 results.

    Follow-up. Can you give a rough FY27 margin number, confirm how much of the PAT-margin erosion came from depreciation and finance costs, and clarify the contingent liability attributed to INA Green Energy?

    Answer. Management reiterated that H2 FY27 would be better than H1 and said Q3 results would provide a better basis for guidance. Depreciation plus finance costs were close to 3% of revenue. The CFO said INA Green Energy had no long-term contingent liability; reported amounts were surety bonds and LCBGs tied to open tenders that close when projects are completed or awards lapse.

    Not answered directly.

  3. 3. Backward-integration economics

    Rajesh Verma, JK Capital

    Question. What cost savings and margin benefits are expected from backward integration into solar cell manufacturing?

    Answer, Management. Management said the cell plant primarily serves the DCR market and should improve margins when its output is used in captive modules. It also said external cell sales and captive module sales should generate similar overall margin because the latter adds module revenue instead of cell revenue. At full operation, the cell plant's EBITDA margin was expected to reach up to around 20%.

    Follow-up. When will the aluminium frame plant become operational, and how much manufacturing cost will it save?

    Answer. The aluminium plant was expected to become operational before December 31, 2026. Management estimated savings of approximately ₹50-60 per frame set.

  4. 4. External cell sales economics

    Saurabh Khara, BT Capital

    Question. What margin is available if the company sells approximately 2.5 GW of external cell capacity rather than using it captively?

    Answer, Management. Management said overall margin should be similar whether cells are sold externally or used in modules: external sales add cell revenue, while captive use adds module revenue. Current cell pricing was put at roughly ₹13.25-13.75 per watt, DCR module realization at ₹21-23 per watt, and non-DCR margin at approximately 12.25%-12.75%.

    Follow-up. What FY27 and FY28 utilization is expected for the 4.5 GW cell line, and what revenue, EBITDA contribution and timing should investors expect from the 400 MW-plus IPP portfolio?

    Answer. The cell line starts by FY27-end and was expected to reach full utilization in FY28; management also indicated first-year utilization around 60%-65% for slightly more than one operating quarter. The ₹800-900 crore associated with the IPP portfolio was clarified as project investment rather than revenue. Annual revenue of approximately ₹180-200 crore was expected from the following year as projects mature, with positive EBITDA and Rajasthan government receipts.

    Partly answered.

  5. 5. China equipment export controls

    Sachin Rajpurohit, Individual investor

    Question. How will China's restrictions on exporting cell-manufacturing technology to India affect the company's equipment procurement and future operations?

    Answer, Management. Management said machinery orders and advance payments had been completed before the notification, its factory-acceptance team was in China, and dispatch was expected by month-end. The existing project was therefore not expected to be affected, although management acknowledged that new orders or supplies could be affected if Chinese suppliers stopped accepting orders.

    Follow-up. What is management doing to rebuild shareholder confidence while the share price remains near an all-time low, and are roadshows or foreign-investor meetings planned?

    Answer. Management reiterated its ambition to become a top-ten Indian solar panel and cell manufacturer and said its committed expansion projects remained on track. Sumit Jain said roadshows, investor meetings and broader Mumbai-market coverage were planned, with growing FII and DII interest in the company.

    Partly answered.

  6. 6. Industry consolidation and scale

    Harsh Mantri, Chola Securities

    Question. Will solar-industry consolidation favor only manufacturers with at least 10 GW of capacity, or can smaller integrated players remain competitive?

    Answer, Management. Management said there was no formal definition of a large player, but an integrated configuration of at least 1.5 GW each for panel, cell and inverter-wafer could remain competitive. Insolation was described as the 11th-largest solar panel manufacturer on the ALMM list, and its 4.5 GW cell facility was expected to support a top-ten position. Management said there was no significant top-line, EBITDA or PAT-margin difference between a 4.5 GW and a 10 GW configuration.

    Follow-up. Do you expect industry consolidation to play out in Insolation's favor?

    Answer. Management said consolidation remained difficult to predict and could become clearer in FY28, when it expected more structural change in the market.

    Not answered directly.

  7. 7. China factory acceptance

    Lakshmi Kant Paradiya, An Iner Eye

    Question. Can you provide visibility on the China factory-acceptance test and machinery release that would address concerns about the cell-plant schedule?

    Answer, Management. Management said it expected the factory-acceptance and dispatch process to be completed by the end of November 2026.

  8. 8. Tandem technology and capital allocation

    Ankur Tyagi, Trio Credit Limited

    Question. What technology milestones will support the 29% tandem-module efficiency target, how will the technology differentiate Insolation's products, and how will capital be allocated between manufacturing and IPP expansion?

    Answer, Management. Management said tandem technology was still at development or lab scale, but Kellogg's had trialed 29%-efficient modules in the United States and was expected to supply from India by 2029. Insolation would be positioned to offer these higher-efficiency modules. On capital allocation, manufacturing funding lines were said to be fully secured, while IPP projects required limited seed funding and were expected to service their obligations from project cash flows after setup.

    Not answered directly.

  9. 9. Revenue ambition

    Saurabh Kala, ET Capital

    Question. Can the company achieve the stated revenue ambition of around ₹4,000 crore this year or next year at current pricing?

    Answer, Management. Management linked achievement of the ₹4,000 crore ambition to current pricing and said year-by-year targets were still being planned. It did not validate a specific revenue range for FY27 or FY28.

    Not answered directly.

  10. 10. Module volumes and margin bridge

    Anand Ahuja, AA Capital

    Question. What were H1 FY27 module sales volumes and the DCR versus non-DCR mix, and how much of the margin decline came from lower realization versus higher input costs?

    Answer, Management. H1 FY27 module dispatches were close to 1 GW, with an approximate mix of 20% DCR and 80% non-DCR. Management said quantifying the margin decline between lower realization and higher input costs was difficult because of rapidly changing global market conditions, although it still expected recovery in H2 FY27.

    Follow-up. How much capex was allocated to the aluminium frame plant, and will its output cover captive module requirements or also be sold to other manufacturers?

    Answer. Approximately ₹100 crore was allocated to the aluminium plant through internal accruals. It was designed for one-to-one integration with 5.5 GW of module capacity; initially about 65% was expected to support captive consumption and 35% could be sold externally.

    Not answered directly.

  11. 11. Ingot and wafer expansion funding

    Nikhil Sangli, Individual investor

    Question. How will the proposed ingot and wafer lines be funded, what is the capex per gigawatt, and when will the investment begin?

    Answer, Management. Management said it had not presented ₹600-700 crore per gigawatt and revised the estimate to approximately ₹150 crore per gigawatt without utilities, or ₹700-900 crore for the total planned capacity. Funding was expected to come mainly from higher internal accruals and balance-sheet improvement after the cell plant ramps. The investment was planned before ALMM Part III becomes effective in June 2028.

    Partly answered.

  12. 12. Investor engagement, margins and solar demand

    Krishna Regupathan, Individual investor

    Question. What is management doing to attract institutional investors, can H2 FY27 EBITDA margin reach 14%-15%, and can imports threaten India's long-term solar demand?

    Answer, Management. Management attributed limited institutional interaction partly to the company's recent main-board listing and said roadshows and mutual-fund and FII meetings were planned. It rejected the 14%-15% H2 margin framing, saying H2 should improve versus H1 and follow FY26's H2 trajectory, without providing an exact number. Management was bullish on Indian power demand over the next decade, arguing that energy security and industrial growth support solar demand despite short-term price fluctuations.

    Not answered directly.

  13. 13. Debt, wafer capex and overcapacity

    Tarin Rajan, Individual investor

    Question. What is the debt-reduction roadmap and target leverage ratio, what is the correct ingot and wafer capex per gigawatt, and is overcapacity emerging across solar manufacturing?

    Answer, Management. The CFO said historical growth was largely funded through internal accruals, but expansion would create temporary debt. Leverage could temporarily reach 2:1-2.5:1 and was expected to return to 2:1 or lower as the cell facility improves EBITDA and margin to around 20%. For ingot and wafer capex, management called the earlier presentation figure a typo, but gave current estimates of roughly ₹450-500 crore per GW with utilities and about ₹150 crore per GW without utilities, with the final utility-inclusive number due after December. It saw panel overcapacity but not yet cell overcapacity and expected inverter-wafer competition to intensify ahead of the June 2028 ALMM deadline.

    Follow-up. What is the correct ingot and wafer capex per gigawatt, and do you see overcapacity in modules, cells or inverter-wafer capacity over the next two to three years?

    Answer. Management described the earlier per-GW figure as a typo and gave estimates of approximately ₹450-500 crore per GW with utilities and ₹150 crore per GW without utilities, with a final number after December. It saw panel overcapacity but not yet cell overcapacity; inverter-wafer commissioning was expected only ahead of ALMM Part III from June 2028.

    Not answered directly.

What was said

Topic by topic, in the order it was spoken

H1 FY27 Business Expansion · Manish Gupta (Chairman)

  • H1 FY27 revenue from operations increased 100.56% YoY to ₹1,582.09 crore.
  • Demand came from government-led programs, utility-scale projects, EPC, commercial and industrial distributed solar, and B2C rooftop installations.
  • EBITDA increased 23.3% to ₹140.31 crore, while margin declined to 8.87% from 14.43%.
  • Management attributed margin pressure to industry pricing dynamics and elevated input costs.

Margin Recovery Outlook · Manish Gupta (Chairman)

  • Global supply-chain disruption was described as gradually easing and input prices as beginning to correct.
  • The Chairman initially expected EBITDA margins to recover over the next two quarters.
  • Initial commentary indicated full-year FY27 EBITDA and margin could return to FY26 levels.
  • The captive cell and aluminium frame projects were expected to improve efficiency, cost competitiveness and margins.

Order Book and Pipeline · Manish Gupta (Chairman)

  • The total order book was approximately 2.2 GW, with production slots allocated and new orders arriving on a rolling basis.
  • Orders worth 1.3 GW were scheduled for delivery by March 2027.
  • Ongoing supplies to NTPC, MEIL and Rais Power supported capacity utilization of more than 60%.
  • Approximately 2.5 GW of proposed business across strategic MOUs, partnerships and direct orders was under internal evaluation.

Cell and Aluminium Expansion · Manish Gupta (Chairman)

  • The 4.5 GW top-con cell facility was nearing commissioning.
  • The 18,000 TPA aluminium frame plant had completed civil and pre-engineering construction, with machine installation completed and trials underway.
  • Commercial operation of the aluminium plant was targeted for Q3 FY27.
  • The backward-integration objective was greater control over inputs, improved manufacturing efficiency and lower external sourcing dependence.

Hybrid Tandem Technology Partnership · Manish Gupta (Chairman)

  • The company entered a five-year strategic partnership with Kellogg's Corporation USA.
  • The partnership is intended to develop 3 GW of hybrid tandem modules at the Jaipur Savardha facility.
  • The proposed technology combines Kellogg's energy-producing glass with Indian N-type top-con technology.
  • Module efficiency was targeted at up to 29% by end-2029, supporting the industry's shift toward domestic value addition.

Cell Facility Commissioning · Vikas Jain (Managing Director)

  • Civil work and PV building erection for the 4.5 GW Nelamaduram cell facility were completed.
  • Major utilities were ordered, machinery installation was underway, and power and industrial water supply had been secured.
  • A turnkey solution provider, technical consultants and owner engineers were engaged to oversee execution and quality.
  • First commercial operations were targeted for Q4 FY27.

IPP Execution and Dispatch · Vikas Jain (Managing Director)

  • Approximately 70 MW of solar IPP projects were executed during H1 FY27.
  • The IPP portfolio was targeting more than 400 MW by FY27.
  • On November 4, 2026, the company recorded its highest single-day dispatch of approximately 16 MW.
  • The dispatch comprised 226,660 modules transported across 40 trailers.

Distribution and Rooftop Reach · Vikas Jain (Managing Director)

  • The distribution network included more than 1,000 channel partners and over 40,000 customers.
  • More than 700 partners attended the company's Ujjain channel-partner meeting.
  • The company solarized 40,000 homes under the PM Surya Ghar Yojana.
  • Management's operating focus remained on completing expansion projects, strengthening capacity and executing the order book.

Q2 and H1 Financial Performance · Ravi Dusad (Chief Financial Officer)

  • Q2 FY27 revenue from operations was ₹836.69 crore, up 96.45% YoY, while EBITDA was ₹63.44 crore, up 13.32%.
  • Q2 EBITDA margin was 7.5%, compared with 8.87% for H1 FY27.
  • H1 net profit was ₹63.08 crore versus ₹80.07 crore in the prior-year period.
  • Higher depreciation and finance costs were identified as the main reason for the lower PAT margin.

Incentives and Financial Discipline · Ravi Dusad (Chief Financial Officer)

  • The company received an incentive certificate under the 2022 policy for Phase I investment of ₹179.12 crore at Savardha.
  • The incentive provides a 1.98% tariff-linked benefit of up to ₹224 crore over approximately nine years and a 100% electricity-duty exemption.
  • At current consumption, the electricity-duty exemption is expected to save more than ₹1 crore annually.
  • Management's priorities were cost control, better operating performance and financial discipline while funding expansion.

In their words

We expect a recovery in EBITDA margins over the next two quarters, with full-year FY27 EBITDA and margin expected to return to FY26 levels.
Manish Gupta (Chairman, Insolation Energy Limited)
Targeting module efficiency of up to twenty-nine percent by end of twenty twenty-nine.
Manish Gupta (Chairman, Insolation Energy Limited)
So, sir, it's Sumit here. Just like for building the market coverage also and investor awareness also, we are planning for the roadshows also. We are personally meeting with the investors also, and definitely we are inviting good investors on the cap table.
Sumit Jain (Head of Strategy, Insolation Energy Limited)

To check next time

What management committed to on this call, or the dates they gave.

  • Q3 FY27 EBITDA margin: check whether it improved from H1's 8.87% and whether FY27 guidance was quantified after Q3 results.
  • Cell line: verify machinery dispatch by end-November 2026, installation progress and the Q4 FY27 commercial-operations target.
  • Aluminium frames: check trials and commercial operation by December 31, 2026, plus the stated ₹50-60 per-set savings.
  • IPP: track execution toward 400+ megawatt by FY27 and the 300 megawatt project cost of ₹800-900 crore by March 2027.
  • Orders: track delivery of 1.3 gigawatt by March 2027 and conversion of the proposed 2.5 gigawatt pipeline as cell capacity comes online.
  • Tandem modules: check progress toward up to 29% efficiency and an India start in 2029.

Transcript

Read along with the recording

The whole call, 329 lines from 4 speakers over 57:07. Click any line to hear it, jump to the Q&A, or find a word. Free with an account.

Sign up freeLog in

The stock after the call

After the callCloseStockNifty 50
Next session Tue 17 Nov 2026₹69.77−0.34%+0.38%

From the close of Mon 16 Nov 2026, ₹70.01: the call began at 15:30 IST, after the market closed, so that day's close is the base. Adjusted daily closes; the move includes everything else that happened in those sessions.