Jupiter Wagons Q2 FY26 earnings call
In brief
Q2 FY26 revenue ₹786 cr, up 71% QoQ on wheelset normalization; FY26 ₹5,000 cr revenue target dropped, 14-15% margin guidance held.
- Management's tone
- Confident
- What was said
- Mixed
- Guidance
- Guidance cut
- Analyst pushback
- Medium
- Stock, next session
- −0.34% (Nifty 50 +0.70%)
- Q2 FY26 consolidated revenue ₹786 cr, up 71% QoQ on wheelset normalization; EBITDA ₹104 cr at 13.2% margin, PAT ₹45 cr.
- FY26 ₹5,000 cr top-line target explicitly dropped citing Q1-July wheelset disruption; 14-15% EBITDA margin guidance maintained.
- Order book stands at ₹5,538 cr; wagon order book at ~12,000 wagons / ~₹4,000 cr providing revenue visibility.
- Orissa forged wheel/axle plant (₹2,500 cr capex): axle line to start in CY2026, wheel line in CY2027; 100,000 wheelsets/year capacity.
- Jupiter Electric Mobility guided ~₹100 cr FY26, doubling FY27; EBITDA positive FY27; ~10 dealerships, 4-5 more planned.
An AI read of the company's transcript · the filing
The numbers
The quarter, Q2 FY26
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹786 cr | −22.1% | +71.1% | |
| EBITDA (excl. other income) | ₹93.2 cr | −33.2% | +55.8% | 11.9% (13.8% a year ago) |
| Net profit | ₹46.6 cr | −48.1% | +42.4% | 5.9% (8.9% a year ago) |
| EPS (₹) | ₹1.10 | −48.1% | +42.9% |
From the company's filed results for the quarter ended 30 Sept 2025 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.
Where management's figures differ from the filing
- EBITDA: said EBITDA ₹104 cr, 13.2% margin (Q2 FY26); filed EBITDA excl. other income: ₹93.18 cr, 11.9% margin. Management's stated EBITDA appears to include ₹10.26 cr other income per filed results; ₹93.18 + ₹10.26 ≈ ₹104 cr.
What moved the numbers, as management explained it
- Wheelset supply normalization from late July drove Q2 revenue recovery (₹786 cr, +71% QoQ); supply disruption in Q1 and first month of Q2 cost the full-year revenue versus ₹5,000 cr target. (one-off)
- EBITDA margin recovered to 13.2% in Q2 from operating leverage as revenue normalized (₹104 cr, +73% QoQ); H1 FY26 EBITDA at ₹163 cr.
- Strong private customer execution (~60% of contribution) offsetting delay in Indian Railway tenders; private volumes in containers and auto-car wagons showed strong traction.
- Diversification into higher-margin segments (BESS, JEM, containers, Stone India) progressing per stated plan; these segments remain small relative to wagons.
- Wheelset disruption in Q1 and early Q2 (July) drove management to abandon ₹5,000 cr FY26 top-line target explicitly on this call. (one-off)
The numbers management led with
- Q2 FY26 consolidated revenue from operations: INR 786 crore (up 71% QoQ)
- Total order book: INR 5,538 crore
- Wagon order book: ~11,000-12,000 wagons, valued at ~INR 4,000 crore
- Odisha forged wheel/axle capex: INR 2,500 crore investment, 100,000 wheelsets/year capacity
Guidance
Guidance on this call
| What | For | What management said | Filed |
|---|---|---|---|
| FY26 EBITDA margin | FY26 | we are still very hopeful that we will be able to achieve the margin guidance | 11.8%, below the range |
| JEM revenue (Jupiter Electric Mobility) | FY26 | this year, our JEM, Electric Mobility revenues, we will be very close to our INR 100 crore target | — |
| JEM revenue growth (Jupiter Electric Mobility) | FY27 | next year, we are looking to double the revenues in FY27 | — |
| Wagon share of revenue (Wagons) | FY28 | by FY28, wagon revenues would constitute close to about 50% of the overall revenues | — |
| Orissa wheel/axle capacity (Wheelsets) | FY28 | An INR 2,500 crore investment that will, upon commissioning in 2027, to produce 100,000 wheelsets annually | — |
| JEM EBITDA positive (Jupiter Electric Mobility) | FY27 | in FY27, we expect it to be EBITDA positive | — |
| Stone India commissioning | Q4 FY26 | by the last quarter of FY26, Stone India, we expect the commissioning to happen | — |
| Stone India PAT positive | FY27 | Next year, definitely, Stone India is also going to become even PAT positive | — |
| Dako JV positive contribution | FY27 | Dako is the only business, and that also, next year, we expect that to also turn positive | — |
| BESS capacity | — | we can easily do about close to 40 to 50 Megawatts of BESS systems on a monthly basis | — |
| JEM additional dealerships (Jupiter Electric Mobility) | FY26 | we plan to open another four to five before the end of this financial year | — |
Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.
What changed since the Wed 13 Aug 2025 call
| What | On the Wed 13 Aug 2025 call | On this call |
|---|---|---|
| FY26 top-line growth guidance (not repeated) | MD firmly maintains FY26 guidance of 10–15% top-line growth | ₹5,000 crore is something, unfortunately, I don't think we will be able to reach those numbers |
| FY26 EBITDA margin guidance (held) | 14–15% EBITDA margins | we are still very hopeful that we will be able to achieve the margin guidance |
| Order book (cut) | Order book stands at ₹5,972 cr covering 11,500 wagons | Our order book of INR 5,538 crore |
| JEM FY26 revenue target (new) | not quantified for FY26 | this year, our JEM, Electric Mobility revenues, we will be very close to our INR 100 crore target |
| Orissa commissioning timing (restated) | Orissa integrated wheel-and-axle plant (₹2,500 cr capex) on track | Calendar Year 2026 the axle line will start, and Calendar Year 2027 wheel-line will start |
| Stone India commissioning (new) | not specifically discussed | by the last quarter of FY26, Stone India, we expect the commissioning to happen |
| JEM dealerships (achieved) | plans 6 showrooms by Sept 2025 | we have close to about 10 dealerships across the country, and we plan to open another four to five |
| Wagon share of revenue FY28 (restated) | combined EV + battery + brake + wheelset targeting ₹8,000–10,000 cr FY28 top line | by FY28, wagon revenues would constitute close to about 50% of the overall revenues |
Guided on earlier calls, and what was filed
| What | For | Guided | Filed |
|---|---|---|---|
| Sustainable consolidated EBITDA margin | FY25 | 15% (on the Q1 FY25 call) | 14.6%, below the figure guided |
| Top line growth | FY26 | 10–15% (on the Q1 FY26 call) | -26.4%, below the range |
| EBITDA margin | FY26 | 14–15% (on the Q1 FY26 call) | 11.8%, below the range |
Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.
The business
By business
Wagons
Main wagon business; Q2 revenue recovery driven by normalized wheelset supplies; FY26 ₹5,000 cr top-line target dropped, 14-15% margin guidance maintained.
Revenue ₹786 cr · EBITDA ₹104 cr · EBITDA margin 13.2% · PAT ₹45 cr · PAT margin 5.8% · H1 FY26 revenue ₹1,245 cr · Order book ₹5,538 cr · Wagon order book ~12,000 wagons / ₹4,000 cr
Outlook: H2 expected on similar trajectory; margins to improve in last 2 quarters; significant expansion in FY27 once Railway order book kicks in.
Wheelsets (Jupiter Tatravagonka Railwheel Factory)
Q2 wins include ₹113 cr LHB axles (9,000) and ₹215 cr Vande Bharat wheelsets (5,376); supply normalized from late July; Aurangabad plant in production.
₹113 cr LHB axles order · ₹215 cr Vande Bharat wheelsets order · 9,000 LHB Axles · 5,376 wheelsets
Outlook: No supply issue expected in next 6-12 months; Orissa integrated facility with axle line CY2026, wheel line CY2027 at 100,000 wheelsets/year.
BESS / Containerized Energy Storage
Launched 10-foot and 20-foot containerized BESS (241 kW to 3 MW); first 10-foot unit delivered to Greenlit via GMMCO; first 20-foot system being prepared for export.
Capacity 40-50 MW/month · 10-foot and 20-foot containers · 241 kW to 3 MW modular air-cooled
Outlook: Volumes to improve significantly in next 6-8 months; C&I focus initially, grid scale later; scaling expected over next 2-3 years.
Jupiter Electric Mobility (eLCVs)
Sales volumes growing 20-30% monthly; expanded to ~10 dealerships across India (Bengaluru + 6 new); partnerships with Porter, Pickkup, others.
~10 dealerships · 20-30% monthly volume growth · FY26 revenue target ~₹100 cr
Outlook: Break even by end FY26, EBITDA positive FY27 with margins similar to other businesses; doubling FY27 revenues; launching 1-tonne and 2-tonne variants.
Containers
Volume more than doubled YoY in Q2 FY26; traction with BESS and data center clients including GE, TMEIC, Tata Solar, Reliance, Delta; capacity being expanded.
Volume >2x YoY
Outlook: Significant growth expected in foreseeable future from India and global demand.
Brake disc
Encouraging traction in volumes during the quarter alongside container, wheelset, CMS Crossing and CV Body lines.
Stone India (brake systems)
Acquired brake systems business; final trials and Indian Railways certification underway; commissioning targeted Q4 FY26.
Outlook: Commissioning by Q4 FY26; significant revenues expected from FY27; PAT positive FY27.
Balance sheet, capex and funding
- Orissa forged wheel/axle plant: ₹2,500 cr phased capex; axle line to commission in CY2026, wheel line in CY2027 with 100,000 wheelsets/year capacity.
- BESS integrated capacities: 40-50 MW/month currently operational within shared facilities; specific BESS capex not separately quantified by management.
The industry, as management sees it
Management is bullish on the broader rail and logistics sector, citing the National Rail Plan, INR 70,000-80,000 cr of Railways capex this year, infrastructure build-up in steel/cement/thermal power, and a $5T+ economy target by 2030. Logistics is expected to play a critical role and the opportunity is 'huge' with no structural challenge, though short 6-12 month hiccups are possible. On BESS, the segment is in early stage in India with significant domestic opportunity as the country transitions from import dependence, similar to the solar inflection.
Risks management named
- FY26 revenue target of INR 5,000 crore no longer achievable due to Q1 wheelset disruption
- Indian Railways main wagon tender delayed; Railways waiting on existing order book to exhaust
- Competitive intensity in wheelsets with Titagarh setting up capacity
- BESS is an early-stage business — explicit margin guidance deferred by 3-6 months
- C&I acceptance risk vs diesel generators (acknowledged but played down)
Q&A
Q&A was dominated by three themes: (1) the FY26 revenue guidance walk-back, where Lohia formally withdrew the INR 5,000 cr target after persistent follow-up from Sahil Patani and clearly stated only margin guidance is being maintained; (2) the BESS vertical, where Sarang Joglekar pushed on capacity, investment quantum and per-MW realization, with management being forthcoming on capacity (40-50 MW/month) but deferring margin and investment specifics; and (3) competitive positioning on wheelsets, where Lohia pushed back on competitor comparisons and emphasized JWL's export and integration advantages. Pushback intensity was moderate — there were no aggressive confrontations, but a few follow-ups on the same topic, particularly on revenue guidance and BESS economics.
Not answered directly
- BESS per-megawatt realization and margin specifics
- BESS investment quantum (since capacity is shared)
- FY26 wagon volume guidance
- Product-wise value and margin breakup (offered to share via email)
- Order book breakup by private vs railway in value terms
- Titagarh-specific competitive comparison
Asked for a number, answered without one
- BESS capex / investment: Very difficult for me to pinpoint any kind of investment numbers for that, because it is part of the complete integrated capacities which we have.
- BESS margins and realization per MW: We would not like to comment specifically on the margins...maybe in the next three to six months, we will be able to give you a clear view on the margins.
- FY26 wagon volumes: Very difficult for me to give...maybe by end of next quarter, I will be in a better position to give you in terms of the guidance for the entire year.
- Product-wise revenue and margin breakup: Offhand to give you data would be very difficult...wagons constitute close to 60% to 70% of the order book; wheel, container and crossing would have the maximum margins.
Every question, with its answer
1. Railway tender timing
Balasubramanian A., Arihant Capital
Question. Could you quantify the expected Indian Railways tender size, the wagon types involved, and explain why the tender has been delayed for so long?
Answer, Vivek Lohia, Managing Director. Tender timing is entirely an Indian Railways decision and not within JWL's control. Railways has stated it requires close to 50,000 wagons to achieve its revenue forecast, so the company expects the tender to come out anytime. One reason cited for delay is the existing outstanding order book being substantial; Railways wants existing orders to be reduced before issuing new tenders.
Follow-up. On the BESS side, beyond in-house assembly, what is the strategy for localizing key components like battery management systems and power conversion systems to reduce reliance on Chinese imports and create a durable cost advantage?
Answer. BMS and EMS are localized; Jupiter is already doing EMS in-house and should be ready with its own EMS very shortly. From China, the main import dependence is on battery cells; everything else — design, BESS and system integration — is in-house. Management positioned JWL as one of the few Indian companies that has successfully delivered and commissioned BESS systems, with a strong and growing order book.
2. Wheelset supply & EV break-even
Balasubramanian A., Arihant Capital
Question. How has wheelset lead time improved from Indian Railways, what volume and margin threshold does the EV division need to break even, and what is the value proposition given the competitive landscape?
Answer, Vivek Lohia, Managing Director. Wheelset supply disruption is no longer a constraint — wheelsets are now available. On the EV side, JWL has close to 10 dealerships and plans to add 4-5 more by end-FY26. Vehicle sale numbers are growing 20-30% per month and non-BESS battery business volumes are also growing significantly. Management expects the e-mobility business to break even by end-FY26 and become EBITDA positive in FY27, with margins similar to other existing businesses.
3. Container business
Sahil Patani, Strokes Capital
Question. Container volumes more than doubled over Q2 of last year — what propelled this growth?
Answer, Vivek Lohia, Managing Director. Container demand in India is growing significantly, and Jupiter focuses on specialized segments — BESS containers and containers for data centres. The company works with marquee clients such as General Electric, TMEIC (Toshiba-Mitsubishi), Tata Solar, Reliance and Delta, giving it both a strong Indian and global presence. Capacity is being expanded significantly because global demand is also rising; significant growth is expected in the foreseeable future.
Follow-up. How is the Porter partnership progressing and is JWL on track to achieve the earlier INR 100 cr revenue guidance for the eLCV segment?
Answer. JWL is on track and JEM revenues will be very close to the INR 100 cr target this year, with the aim to double revenues in FY27. Partnerships — including Porter and other significant players like Pickkup — are doing very well. A lighter 1-tonne truck and a 2-tonne payload truck are planned for next year. Segment growth is around 100% month-on-month, and management is very bullish on volume expansion.
4. H2 FY26 outlook
Rajesh Bhandari, Nakoda Engineers
Question. Q1 FY25 results were very good — can we expect H2 FY26 to be on similar or better lines?
Answer, Vivek Lohia, Managing Director. Management expects H2 to be on similar trajectories, with both revenue and margin improvement. Currently execution is heavy on private order books and complex wagons like auto-car carriers, where margins are better — so margin improvement should be visible in the last two quarters. Volume numbers may not be that high until the railway order book kicks in from FY27, when significant expansion in overall numbers is expected.
Follow-up. Are there any wheelset issues currently? And are both LHB wheelset factories in production?
Answer. No wheelset issue currently; expectation is that the next 6-12 months will also be problem-free. The Aurangabad plant is in production with limited capacity and is used for LHB wheelsets and the company's private order books. LHB refers to passenger coaches for Indian Railways; JWL supplies for both LHB and Vande Bharat.
5. Wheelset pricing & competition
Rajesh Bhandari, Nakoda Engineers
Question. What is the cost of a Vande Bharat wheelset vs an LHB wheelset? And since Titagarh is also setting up wheel manufacturing, won't competition intensify?
Answer, Vivek Lohia, Managing Director. Lohia pushed back on the INR 1.2 lakh per wheelset figure — clarifying that this number pertains to the standalone axle order (INR 113 cr), not a complete wheelset. On competition, he declined to comment on competitors specifically but highlighted JWL's differentiators: (1) fully integrated facility producing both wheels and axles with in-house machining, and (2) significant export demand from European partners, lowering domestic dependence vs competitors.
Follow-up. When will the Odisha factory be operational — financial or calendar year 2027?
Answer. Confirmed: Calendar Year 2026 the axle line will start, and Calendar Year 2027 the wheel line will be fully commissioned.
Partly answered.
6. Product mix & margins
Ashit Kothi, Individual Investor
Question. Can the operating highlights be provided in value terms and margins, and which of the nine products carry the highest EBITDA margins?
Answer, Vivek Lohia, Managing Director. Lohia said value/revenue data by product was difficult to provide offhand and offered to share it over email. On margins, he confirmed that wagons constitute 60-70% of the order book, while the highest margins come from the wheel, container and crossing businesses.
Follow-up. Should JWL reduce dependence on wagons over time given 5% net margin profile?
Answer. Management confirmed margin expansion is a key focus and explained the diversification rationale. Stated target is that by FY28, wagon revenues will constitute only ~50% of overall revenues, with other businesses growing significantly. In wagons itself, forward and backward integration should continue to improve margins.
Partly answered.
7. Aluminum wagons & Vande Bharat foray
Ashit Kothi, Individual Investor
Question. Are we into aluminum wagons? And are we exploring Vande Bharat entry? Is Vande Bharat a better margin business than wagons?
Answer, Vivek Lohia, Managing Director. JWL is already in aluminum wagons but the market is very small, so focus is on specialized wagons requiring design/investment intensity. Vande Bharat: JWL is in talks with global players and may announce passenger-side foray by FY27. Lohia said Vande Bharat is not necessarily better margin but expands the product base; existing products (brake systems, wheelsets, brake discs) are already supplied for Vande Bharat, Metro and other businesses.
Follow-up. What is the contribution of railways vs private customers in overall sales?
Answer. Private customers contribute ~60% and railways ~40% to current order book/sales. Lohia pushed back on the analyst's view that margins are low, arguing that compared to competition JWL's margin profile is significantly better. Margin recovery was constrained by wheelset availability in the first two quarters; as revenues normalize, margins will improve.
8. BESS capacity, cost & competitiveness
Sarang Joglekar, Vimana Capital
Question. What is JWL's BESS capacity and how much has been invested in it? What is the per-megawatt realization vs China, and is JWL competitive?
Answer, Vivek Lohia, Managing Director. Capacity: 40-50 MW of BESS systems per month; capacity is not a constraint. Investment number not separable since BESS uses shared integrated capacity. JWL is competitive vs China — significant export order books are being executed, and as BMS/EMS are brought in-house over the next 3-6 months, competitiveness will further improve. Per-megawatt margin disclosure was deferred.
Follow-up. Is the focus on utility-scale storage or C&I (DG replacement)? Is BESS acceptance vs diesel generators a challenge? Are ancillaries (PCS, inverter, HVAC) sourced from Indian suppliers?
Answer. Focus is on both C&I and utility scale, but initial focus is C&I because the market opportunity is huge; grid scale will come later when technology and size mature. On acceptance: Lohia said adaptability is very strong and BESS is not the only solution being pursued — there are other significant opportunities. On ancillaries: only cells are imported from China; everything else is largely indigenous, with much in-house.
Not answered directly.
9. FY26 revenue guidance withdrawal
Sahil Patani, Strokes Capital
Question. In Q3 FY25, JWL guided for INR 5,000 cr top line by FY26 — will that be met? What is the wagon number guidance for FY26? And what is the order book pipeline?
Answer, Vivek Lohia, Managing Director. Lohia formally withdrew the INR 5,000 cr FY26 revenue target: Q1 was hit hard by wheelset issues and the first month of Q2 also faced challenges. Margins guidance is maintained, but the INR 5,000 cr number will not be reached. On wagon numbers and full-year guidance, Lohia declined and said a clearer view would be possible by end of next quarter. On pipeline: Railways has floated tenders for ~5,000-6,000 wagons this year, and the large tender is expected any time once outstanding industry order books get executed (likely by early next year).
Partly answered.
10. Segment growth priorities
Ashit Kothi, Individual Investor
Question. Which is the most exciting business segment, and could Jupiter Electric Mobility potentially surpass other divisions in growth?
Answer, Vivek Lohia, Managing Director. Lohia called all businesses 'his babies' and said all are showing significant growth momentum. Wagons and commercial vehicles are more mature, while wheelsets and containers have substantial revenue opportunities backed by capacity build-up. On electric mobility and batteries, he cited entry of Reliance, Adani and Tata as evidence of the sector scaling, said JWL has a strong head start with significant resources and talent, and predicted a 2,000-3,000% growth in these businesses in India over the next 2-3 years.
11. Wagon order book size
Sandeep Mukherjee, SKP Securities Limited
Question. What is the wagon order book backlog — wagons to be executed currently and for Q2 FY26?
Answer, Vivek Lohia, Managing Director. Wagon order book stands at close to 11,000-12,000 wagons, valued at approximately INR 4,000 cr. Exact number of wagons could not be provided.
12. Industry outlook & export optionality
Athif, Individual Investor
Question. How is the industry pulse, will the infrastructure push taper off before the wheelset plant comes online, and does JWL have optionality to export wagons? Also, are we doing anything on the metro side?
Answer, Vivek Lohia, Managing Director. Management sees sustained opportunity driven by the National Rail Plan, National Growth Plan, infrastructure push (steel, cement, now thermal power) and a $5T+ economy target by 2030. Railways has announced INR 70,000-80,000 cr of investments this year in new lines and modernization. There could be small 6-12 month hiccups but no structural challenge. On exports: complete wagon exports are not viable due to volume/size, so the company is focusing on component exports (brake systems, wheelsets). On metros: focus is on this segment and announcements may come before end-FY26.
13. Private orders, Stone India, JVs
Sudeep Anand, Systematix Institutional Equities
Question. While we wait for the big Railways order, how is the private ordering trend this quarter? Also, what is the current status of Stone India and when will it commission? And when will JVs turn positive at PAT level?
Answer, Vivek Lohia, Managing Director. On private orders: no slowdown — private execution is strong and JWL keeps adding private order books; outlook remains positive. Stone India: commissioning expected by last quarter of FY26; final trials ongoing and Indian Railways certification in process; significant revenues expected next year and Stone India will become PAT positive in FY26 (next year). On JVs: only Dako is currently a negative contributor — rest are positive. Electric mobility to be EBITDA positive and possibly PAT positive next year; Stone India similar; wheel business already profitable; Dako expected to turn positive next year. From FY27, subsidiaries will start showing good traction.
What was said
Topic by topic, in the order it was spoken
Q2 FY26 Performance Recovery from Wheelset Disruption · Vivek Lohia (MD)
- Q1 FY26 was hit by supply-side disruptions in wheelsets, extending into July 2025
- Supply conditions improved meaningfully from late July onwards, enabling a sharp sequential recovery
- Q2 FY26 consolidated revenue from operations stood at INR 786 cr, up 71% QoQ
- EBITDA rose 73% QoQ to INR 104 cr, with EBITDA margin of 13.2%
- Profit after tax reached INR 45 cr in Q2, reflecting a PAT margin of 5.8%
- H1 FY26 consolidated revenue was INR 1,245 cr, EBITDA INR 163 cr, PAT INR 76 cr
Order Book, Diversification and Business Verticals · Vivek Lohia (MD)
- Total order book stands at INR 5,538 cr, providing strong multi-quarter revenue visibility
- Encouraging volume traction in brake discs, containers and wheelsets; CMS Crossing and CV bodies remained resilient
- Goal is to first restore wagon business to past performance benchmarks and then build on them via diversification
- Management framed vertical performance (containers, BESS, e-mobility) as continuing to scale even during the wagon disruption
Key Order Wins — LHB and Vande Bharat · Vivek Lohia (MD)
- Subsidiary Jupiter Tatravagonka Railwheel Factory secured an INR 113 cr order for 9,000 LHB Axles from Ministry of Railways
- Secured INR 215 cr order for 5,376 wheelsets for the Vande Bharat high-speed train project
- Orders strengthen backward integration into wheelset manufacturing
Jupiter Electric Mobility — BESS Product Launches and Dealership Expansion · Vivek Lohia (MD)
- Launched 10-ft and 20-ft containerized battery energy storage systems with modular air-cooled architecture ranging from 241 kW to 3 MW
- Suitable for DG replacement and solar energy storage applications
- Delivered first 10-ft BESS unit to Greenlit in partnership with GMMCO; first 20-ft system being prepared for export
- Development progressing on liquid-cooled grid-scale BESS to reinforce energy storage leadership
- Following Bengaluru showroom success, expanded to six new dealerships in Hyderabad, Delhi, Ghaziabad, Pune, Ahmedabad and Trivandrum
Capex — Odisha Forged Wheel and Axle Facility · Vivek Lohia (MD)
- Odisha forged wheel and axle facility involves an INR 2,500 cr investment
- Upon commissioning in 2027, the plant will produce 100,000 wheelsets annually
- The plant is central to backward integration and reducing dependence on third-party wheelset supplies
ESG, Leadership and Closing Outlook · Vivek Lohia (MD)
- Jupiter Wagons has been independently assigned an ESG rating of 45 by ESG Risk Assessments and Insights based on FY25 data
- Mr. Vinod Kumar Agrawal has been appointed as Chief Financial Officer and key managerial personnel
- H2 FY26 priorities articulated as scale responsibly, innovate continuously, create enduring value
- Management sees strong momentum, capacity headroom and progress in expansion plans as foundation for sustained growth
In their words
I don't think we will be able to do it [INR 5,000 cr revenue] because in Q1, we faced significant headwinds because of the wheelset issue... unfortunately, I don't think we will be able to reach those numbers. Overall we are looking to maintain the margin guidance which we have given.
I think in the next two to three years, especially in India itself, you will see about a 2,000%, 3,000% growth in those [battery/EV] businesses... and we have a very, very strong head start in that business.
Our facility is fully integrated, enabling us to produce both wheels and axles, with all machining done in-house — something competitors may not offer... a sizable part of our capacity is already earmarked for exports.
To check next time
What management committed to on this call, or the dates they gave.
- FY26 revenue achievement (₹5,000 cr target already dropped on this call)
- Indian Railways big tender timing (MD expects anytime)
- JEM revenue tracking to ~₹100 cr FY26 target
- Stone India commissioning progress (target Q4 FY26 on this call)
- Orissa axle line progress (target CY2026 on this call)
- Dako JV contribution turning positive (target FY27 on this call)
Transcript
We have not transcribed this call's recording. Read the company's transcript (PDF).
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Wed 12 Nov 2025 | ₹310.30 | −0.34% | +0.70% |
| 5 sessions Tue 18 Nov 2025 | ₹304.70 | −2.14% | +0.84% |
| 20 sessions Tue 9 Dec 2025 | ₹260.85 | −16.22% | +0.56% |
From the close of Tue 11 Nov 2025, ₹311.35: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.
Jupiter Wagons's other calls
- Q2 FY27Mon 16 Nov 2026Tone: Confident
- Q1 FY27Tue 18 Aug 2026Tone: Confident
- Q4 FY26Mon 1 Jun 2026Tone: Mixed
- Q3 FY26Fri 13 Feb 2026Not read
- Q1 FY26Wed 13 Aug 2025Tone: Confident
- Q4 FY25Mon 19 May 2025Tone: Confident
- Q3 FY25Thu 30 Jan 2025Tone: Confident
- Q2 FY25Mon 11 Nov 2024Tone: Mixed
- Q1 FY25Fri 26 Jul 2024Tone: Confident
- Q4 FY24Wed 8 May 2024Tone: Confident