MAN Industries (I) Q2 FY27 earnings call

Fri 13 Nov 202616:00 ISTMANINDS

In brief

Q2 FY27 revenue rose 49% YoY to ₹1,216 crore; management reported EBITDA of ₹190 crore as West Asia disruption deferred about ₹300 crore of revenue.

Management's tone
Optimistic
What was said
Leaned positive
Guidance
First guidance issued
Analyst pushback
Medium
Stock, next session
−7.90% (Nifty 50 +0.58%)
  • Q2 FY27 consolidated revenue rose 49% YoY to ₹1,216 crore; EBITDA was ₹190 crore, up 86.6% YoY and the highest ever for a quarter.
  • West Asia disruption and Strait of Hormuz congestion deferred about ₹300 crore of standalone revenue beyond Q2 FY27; management said contracts were intact.
  • NPC's first full quarter contributed revenue of ₹486 crore, EBITDA of ₹88 crore and PAT of ₹77 crore, with an 18% EBITDA margin.
  • A board-approved US pipe plant was planned at 350,000 metric ton and around $110 million capex, targeting commissioning in December 2027 or January 2028.
  • The consolidated order book was about ₹3,500 crore and the bid book ₹18,000-19,500 crore; most bids were scheduled over the next 6-9 months.

An AI read of our transcription of the recording · the filing

The numbers

The quarter, Q2 FY27

This quarterA year agoLast quarterMargin
Revenue₹1,210 cr+45.1%+14.9%
EBITDA (excl. other income)₹209 cr+72.3%+45.5%17.2% (14.5% a year ago)
Net profit₹82 cr+121.8%+33.5%6.8% (4.4% a year ago)
EPS (₹)₹10.93+126.3%+33.5%

From the company's filed results for the quarter ended 30 Sept 2026 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

Where management's figures differ from the filing

  • EBITDA: said ₹190 crore; +86.6% YoY; 15.6% margin; underlying business EBITDA ₹215 crore; filed ₹208.69 crore excluding other income; +72.3% YoY; 17.2% margin. Management separately presented a business-related customer transaction, including a ₹25 crore forfeited advance; the filed measure excludes other income, so the bases differ.

What moved the numbers, as management explained it

  • NPC's first full quarter added ₹486 crore of revenue, ₹88 crore of EBITDA and ₹77 crore of PAT, with management highlighting its 18% EBITDA margin.
  • Hormuz-related port congestion and dispatch delays deferred about ₹300 crore of standalone revenue beyond Q2 FY27; management described it as timing, not lost business.
  • A reversed customer transaction of around ₹38 crore and a ₹25 crore forfeited advance were shown separately; management said there was no economic profit or loss and cited underlying EBITDA of ₹215 crore. (accounting)
  • Q2 finance cost was about ₹50 crore; management said this was likely to remain the full finance cost after the debt taken for NPC.
  • Management said combined purchasing was nearly double India's prior level and had already saved 30-40% on some consumables, fluxes and wires.

The numbers management led with

  • Deferred revenue due to logistics disruption: Approximately ₹300 crore of revenue deferred beyond Q2 FY27 because of West Asia and port disruption.
  • Consolidated order book: Approximately ₹3,500 crore across India and Saudi Arabia.
  • Bid book: Approximately ₹19,000 crore, with most orders scheduled for execution over the next six to nine months.
  • U.S. plant capex: Approximately $110 million for the complete project.

Guidance

Guidance on this call

WhatForWhat management said
Consolidated revenueFY27FY27 consolidated revenue was targeted at ₹5,000 crore.
Consolidated revenue growthFY28FY28 consolidated revenue growth was targeted at 20-25%.
Consolidated EBITDA marginFY28FY28 consolidated EBITDA margin was expected to remain north of 15%.
NPC revenue (NPC Saudi Arabia)Q3 FY27-Q4 FY27NPC revenue for each of the next two quarters was expected north of approximately ₹500 crore.
NPC revenue (NPC Saudi Arabia)FY28Management separately stated FY28 NPC revenue at around ₹2,250 crore.
NPC revenue including coating (NPC Saudi Arabia)FY28Management also stated FY28 NPC revenue, including coating, at $200-250 million.
US plant top line (US pipe manufacturing plant)FY29At 75% capacity utilization, US plant top line was estimated at ₹4,500-5,000 crore from FY29.
US PAT margin (US pipe manufacturing plant)FY29US plant PAT margin was tentatively targeted at 10-15%.
Order book (India and Saudi Arabia)FY27FY27 year-end order book was put at ₹6,000-6,500 crore across India and Saudi Arabia.
Peak gross debt and net debtFY27FY27 peak gross debt was expected at ₹1,700 crore; net debt was around ₹200-250 crore, excluding US.
H2 capex (Saudi coating and Jammu projects)H2 FY27H2 FY27 capex was put at approximately ₹450 crore for Saudi coating and Jammu.
US plant CapEx (US pipe manufacturing plant)FY28US plant CapEx: around $110 million for approximately 350,000 metric ton capacity; closure targeted for February, commissioning for Dec 2027-Jan 2028.
Jammu peak contribution (Jammu stainless steel pipe and plant)—Jammu plant peak revenue contribution was put at ₹1,000-1,200 crore.
Stainless steel EBITDA margin (Jammu stainless steel pipe and plant)FY28FY28 stainless steel EBITDA margin was targeted at 18-22%.
Sai One World cash flow (Marine Shelters)next 5-6 yearsMarine Shelters was expected to generate ₹800-900 crore of cash flow over five to six years.

The business

By business

Consolidated operations

Q2 FY27 consolidated revenue rose 49% YoY to ₹1,216 crore and EBITDA rose 86.6% to ₹190 crore, with PAT up 102% to ₹82 crore.

Revenue: ₹1,216 crore · Revenue growth: 49% YoY · Revenue growth: 14% QoQ · EBITDA: ₹190 crore · EBITDA growth: 86.6% YoY · EBITDA margin: 15.6% · PAT: ₹82 crore · PAT growth: 102% YoY · PAT margin: 6.7%

Outlook: H2 FY27 consolidated performance was expected to be approximately similar to H1; FY28 revenue growth was targeted at 20-25%, with EBITDA margin above 15%.

Man Industries India standalone

Standalone Q2 was affected by Hormuz-related delays in raw-material inflows and finished-goods dispatches; about ₹300 crore of revenue was deferred beyond the quarter.

Revenue deferred beyond Q2 FY27: approximately ₹300 crore

Outlook: Most of the deferred dispatches were expected in Q3 FY27; management said the contracts and customer relationships remained unchanged.

NPC Saudi Arabia

NPC's first full quarter added revenue of ₹486 crore, EBITDA of ₹88 crore and PAT of ₹77 crore; operations, systems and reporting were fully integrated.

Acquisition completed: May 21, 2026 · Q2 revenue: SAR 191 million · Q2 revenue: approximately ₹486 crore · Q2 EBITDA: SAR 34 million · Q2 EBITDA: approximately ₹88 crore · Q2 PAT: SAR 30 million · Q2 PAT: approximately ₹77 crore · Q2 EBITDA margin: around 18% · Q2 PAT margin: 15.8%

Outlook: Revenue was expected north of ₹500 crore in each of the next two quarters; FY27 was around ₹1,500 crore, while FY28 was stated at around ₹2,250 crore and $200-250 million including coating.

Saudi coating and double-jointing facility

The Saudi coating business was described as busy and lucrative; a new coating and double-jointing facility was targeted to commence operations in April 2027.

Coating facility margins: north of around 15%

Outlook: The new Saudi facility was targeted for April 2027; FY28 NPC revenue including coating was expected at $200-250 million.

Jammu stainless steel pipe and plant

The stainless steel pipe and plant project was progressing toward April 2027 production and was positioned as an import-substitution opportunity.

Peak contribution: ₹1,000-1,200 crore · First-year contribution: 25-30% · Stainless steel EBITDA margin: 18-22%

Outlook: Peak contribution was put at ₹1,000-1,200 crore; the first year was targeted at 25-30%, with stainless steel EBITDA margins of 18-22%.

Marine Shelters

Sai One World by Paradise Group was launched on October 26 with full IOD, CC and RERA approvals under the Marine Shelters joint development.

Launch date: October 26 · Cash flow over the next five to six years: ₹800-900 crore

Outlook: Cash flows were expected from Q3 FY27 onwards, with total cash flow of ₹800-900 crore over the next five to six years.

US pipe manufacturing plant

The board approved a wholly owned US pipe manufacturing plant with capacity of approximately 350,000 metric ton and around $110 million CapEx.

Capacity: approximately 350,000 metric ton · Plant CapEx: approximately $110 million · Targeted timeline: 12-14 months · FY29 top line at 75% capacity utilization: approximately ₹4,500-5,000 crore · PAT margin: tentatively 10-15% · New US debt interest rate: 5.5-6.5%

Outlook: Financial closure was targeted for February 2027 and commissioning for December 2027-January 2028; revenue was expected from FY29 at 75% utilization.

Balance sheet, capex and funding

  • FY27 peak gross debt was expected at around ₹1,700 crore, with net debt around ₹200-250 crore; the net figure excluded the US project.
  • The US project was to be funded partly with debt and partly through pref or QIP funding; targeted leverage was not disclosed.
  • US plant project cost was around $110 million, covering machinery, land and infrastructure, with financial closure targeted for February.
  • H2 FY27 capex was put at approximately ₹450 crore, including the Saudi coating and Jammu projects.
  • NPC had no borrowing; net worth was about SAR 618 million, translated to approximately ₹1,576 crore at September 30, 2026.
  • The working-capital cycle was elongated by delayed dispatches and DDP orders; management expected normalization in Q4 FY27.

The industry, as management sees it

Management expects U.S. gas and power pipeline demand to remain strong for at least five years, arguing that AI companies are funding their own gas and power infrastructure and the grid remains underbuilt. It sees the U.S. market as large enough for a new local entrant despite established producers and policy barriers.

Risks management named

  • West Asia and Strait of Hormuz disruption, port congestion and dispatch delays that deferred about ₹300 crore of revenue
  • Working-capital elongation from delayed shipments and higher DDP execution needs
  • US expansion funding needs, including prospective equity dilution via preference capital or a QIP
  • Possible US mid-term and policy effects, despite management's expectation of no major demand slowdown
  • Higher finance cost following acquisition-related borrowing

Q&A

The U.S. expansion dominated the discussion, with repeated scrutiny of commissioning timing, funding, leverage, margins, cycle risk and Man Industries' right to win. Management was direct on project economics and the India-Saudi order book, but withheld standalone guidance, U.S. asset-turn economics and the final U.S. leverage and funding mix. Deferred dispatches and working-capital normalization formed the second major area of focus.

Not answered directly

  • Standalone H2 FY27 and FY28 revenue and margin guidance
  • Incremental U.S.-project leverage and final debt-equity funding mix
  • U.S. plant asset-turn economics
  • Exact U.S. and Saudi bid-pipeline conversion visibility

Asked for a number, answered without one

  • Standalone revenue and margin guidance: Management said it could not give standalone guidance; it only indicated H2 FY27 consolidated performance would be approximately similar to H1 and FY28 consolidated growth of 20-25%.
  • US plant asset turns: Management discussed a 12-14 month timeline and around $110 million project cost but did not provide asset-turn figures.
  • Separate US and Saudi bid pipelines: Management quantified only the combined India-Saudi bid book at ₹18,000-19,500 crore and gave no separate pipeline figures.
  • US project funding mix: Funding was described as partly debt and partly pref/QIP equity; management said it was still exploring the mix and could not commit a US debt figure.
  • Target leverage: Management said it could not yet disclose leverage and would update after the financing was closed.
  • Total NPC synergies: Management said benefits were ongoing and cited 30-40% savings on some consumables, fluxes and wires, but gave no aggregate synergy figure.

Every question, with its answer

  1. 1. Capacity ramp and margins

    Disha, Sapphire Capital

    Question. Saudi plant utilization and revenue contribution for the next two quarters; Jammu plant peak revenue, first-year contribution and margins; and expected consolidated margin after the coating and Jammu facilities start.

    Answer, Nikhil Mansukhani, Managing Director. Saudi utilization is 40–45%, with NPC revenue north of approximately ₹500 crore for each of the next two quarters. Jammu can contribute ₹1,000–1,200 crore at peak; first-year utilization is targeted at 25–30%, with 18–22% EBITDA margins. Consolidated EBITDA margin should remain above 15% during the first ramp year.

    Follow-up. What caused the ₹24 crore exceptional gain, when will the US plant come online, what asset turns are expected, what is the rationale for local U.S. manufacturing, and what bid-book conversion, FY27 revenue and FY28 growth are targeted?

    Answer. The CFO said the ₹24 crore presentation arose from reversing a ₹38 crore customer transaction and forfeiting a ₹25 crore advance; the company incurred no economic profit or loss, and reported EBITDA would otherwise have been ₹215 crore. The US plant is targeted for completion in 12–14 months, with a further update next quarter; management cited U.S. energy demand and closed-market duties as the rationale but did not quantify asset turns. Bid-book conversion has been 25–30%, implying ₹6,000–6,500 crore; FY27 consolidated revenue is ₹5,000 crore, and FY28 growth is expected at 20–25%.

    Partly answered.

  2. 2. U.S. partnership and Saudi capacity

    Nikhil Nati, Investec

    Question. Will Man Industries partner with a local company for the U.S. plant, what visibility exists on U.S. and Saudi bid pipelines, and what capacity was being ramped in Saudi before the NPC acquisition?

    Answer, Nikhil Mansukhani, Managing Director. Management said there is no local U.S. partner for now. The U.S. project will combine new and upgraded in-house machines. In Saudi, land had been acquired for a greenfield manufacturing facility, but the company proceeded with the coating plant instead after acquiring NPC, so it did not build the earlier manufacturing facility. No specific incremental bid-pipeline figure was provided.

    Partly answered.

  3. 3. Deferred shipments

    Shalak Jain, Chhattisgarh Investment Limited

    Question. Will the nearly ₹320 crore of deferred dispatches normalize going forward, and by when should investors expect the deferral to reduce?

    Answer, Nikhil Mansukhani, Managing Director. Management said the deferral would reduce over time as shipments were redirected to alternate ports. The customer granted a discount to facilitate dispatch, and management expects most of the deferred amount to be shipped during the current quarter.

  4. 4. U.S. funding and Saudi coating

    Dikshi Jain, Incred Equities

    Question. When will the U.S. facility be completed and funded, when will capacity become live, will marine shelters contribute this year, and what utilization, margins and FY28 revenue are expected from the Dammam coating facility?

    Answer, Nikhil Mansukhani, Managing Director. U.S. financial closure is expected by February; operations are targeted for December 2027-January 2028, with the API license to follow. Capex will be funded mainly with debt plus preference capital or a QIP. Some marine-shelter income will begin now, but it will be small because only about five months remain. The Saudi coating facility is expected to be busy, with margins north of 15%, as other Saudi plants are full and Aramco orders are currently sent out for coating. FY28 NPC revenue including coating is expected at $200–250 million.

  5. 5. Cash flow, synergies and debt

    Viraj Mahadevia, Moneygro Asset Private Limited

    Question. What is the likely finance cost after NPC debt, why did operating cash flow not rise despite higher profit, when will working capital normalize, what is the consolidated bid book and win rate, is bidding more aggressive in Saudi, what procurement synergies are visible, and what are FY27 peak gross and net debt?

    Answer, Nikhil Mansukhani and Sandeep Kumar Garg, Managing Director and Chief Financial Officer. Finance cost of around ₹50 crore is expected to persist following acquisition-related borrowing. Delayed dispatches elongated the working-capital cycle; management expects normalization in Q4 FY27. The consolidated bid book is ₹18,000–19,500 crore, with win rates generally 25–35%, and the company is bidding more aggressively in Saudi. NPC was upgraded to serve water-order sizes it previously could not handle. Procurement synergies are emerging, including 30–40% savings on consumables, fluxes and wires. FY27 peak gross debt is expected around ₹1,700 crore and net debt around ₹200–250 crore; management would not commit to additional U.S.-project leverage.

  6. 6. Standalone outlook and capex

    Raj Seth, Abans BMS

    Question. What caused the subdued standalone performance, what revenue and margin guidance applies to standalone business in H2 FY27 and FY28, and what capex is planned for H2 and FY28?

    Answer, Nikhil Mansukhani, Managing Director. The main cause of standalone weakness was Hormuz-related disruption, including delays in inbound raw materials and outbound finished goods. Management declined to provide standalone H2 FY27 or FY28 guidance and instead indicated that consolidated H2 FY27 should be similar to H1, with 20–25% consolidated growth in FY28. FY28's major capex is the U.S. plant at about $110 million. H2 capex is approximately ₹450 crore, including about $30 million for Saudi coating and ₹150 crore for Jammu.

    Not answered directly.

  7. 7. U.S. demand and competitive entry

    Pratik Singh, IIFL Capital Services

    Question. Does the operating-cash-flow presentation reflect deterioration or a period mismatch, can U.S. pipeline demand slow after the midterms, and what is Man Industries' right to win as a new U.S. entrant against established Indian and Turkish players?

    Answer, Nikhil Mansukhani, Managing Director. The FY26-versus-H1 FY27 cash-flow comparison is a period mismatch rather than like-for-like deterioration. Management sees no major U.S. slowdown because AI companies are funding their own gas and power lines, grid build-out remains under-supplied and demand should last at least five years. It views the market as large enough for a new entrant, with local manufacturing essential because established U.S. producers capture orders. NPC is expected to contribute about ₹1,500 crore this year and roughly ₹2,200–2,500 crore next year.

    Partly answered.

  8. 8. U.S. funding and leverage

    Ganesh Rao, Punarvi Capital

    Question. Is the FY27 peak gross debt of about ₹1,700 crore and net debt of about ₹250 crore correct and excluding the U.S. project, how will the U.S. investment be funded, and what leverage target is management adopting?

    Answer, Sandeep Kumar Garg, Chief Financial Officer. Management confirmed that the FY27 peak debt and net-debt figures exclude the U.S. project. U.S. funding will combine debt with some equity dilution through preference capital or a QIP. The targeted leverage was not disclosed and management deferred giving a figure until project financing and closings are completed.

    Not answered directly.

  9. 9. U.S. economics and funding cost

    Vishal Jain, Divita Investments

    Question. When will the U.S. facility commission, what top-line contribution and PAT margin are expected, and what interest rate will apply to the new debt?

    Answer, Nikhil Mansukhani, Managing Director. Management corrected the expected commissioning window to late 2027 or early 2028, with revenue beginning in FY29. At 75% capacity utilization, the plant could generate approximately ₹4,500–5,000 crore of top-line revenue. The tentative PAT-margin range is 10–15%, and the U.S.-dollar borrowing rate is expected at 5.5–6.5%.

  10. 10. U.S. capital intensity

    Nikhil Mhati, Investec

    Question. Why is the U.S. project's capex per kilogram of capacity below competitors' brownfield expansions despite Man Industries undertaking a greenfield project?

    Answer, Nikhil Mansukhani, Managing Director. Management attributed the lower capex intensity to project cost control and the use of some existing in-house equipment alongside new equipment, rather than relying entirely on a fully new plant and machinery set.

  11. 11. U.S. cycle, sourcing and tariffs

    Nirvana Laha, Badrinath Holdings

    Question. Is the U.S. pipeline build-out already mid- or late-cycle, what confidence is there after Man Industries abandoned a U.S. plant plan in 2007-08, how will steel be sourced, and could Section 232 duties be reversed?

    Answer, Nikhil Mansukhani, Managing Director. Management said current conditions differ from 2007-08, when it abandoned a U.S. plan after the cycle turned; it sees the next two to three years as prime and says local presence is essential because established U.S. producers capture orders. Sourcing risk is manageable: U.S. mills can supply, imports from Japan or Korea are possible if needed, and management's existing Nippon Steel relationship supports HRC procurement. Management does not expect Section 232 or dumping duties against India to disappear and views their persistence as an equal barrier for all local producers.

  12. 12. Geographic expansion

    Akhilash Rawat, Brijanta Vision Private Limited

    Question. Does Man Industries plan to establish manufacturing facilities in any additional geographies beyond India, Saudi Arabia and the United States?

    Answer, Nikhil Mansukhani, Managing Director. Management said there are no plans for manufacturing expansion into any other geography at present.

What was said

Topic by topic, in the order it was spoken

Q2 Performance and Logistics Disruption · Nikhil Mansukhani (MD)

  • Q2 FY27 consolidated EBITDA was ₹190 crore, a record for a quarter, while revenue grew 49% YoY and 14% QoQ.
  • Management attributed the strong quarter partly to NPC's first full-quarter contribution, a broader manufacturing footprint and improved product and geographic mix.
  • West Asia disruption, the Strait of Hormuz, port congestion and dispatch delays deferred approximately ₹300 crore of revenue beyond Q2 FY27, affecting standalone results.
  • Management described the deferral as logistical rather than lost business; contracts remained intact, alternate ports had been nominated and shipments were being executed.

NPC Integration and Saudi Platform · Nikhil Mansukhani (MD)

  • NPC was acquired on 21 May 2026, and integration was complete across operations, systems and reporting by Q2 FY27.
  • The quarter was NPC's first full period of contribution, and management said it performed ahead of the previously indicated range.
  • The acquisition converted Man from an exporter into Saudi into an in-kingdom manufacturer with closer customer access and more integrated project capabilities.

Saudi, Jammu and Marine Expansion · Nikhil Mansukhani (MD)

  • A Saudi coating and double-jointing facility was targeted to begin operations by April 2027, adding value-added processing and integrated pipeline solutions.
  • The Jammu stainless-steel pipe and plant project was progressing toward production in April 2027, marking entry into a higher-value import-substitution segment.
  • Paradise Group's Sai One World marine-shelter project was launched on 26 October with approvals; cash flows were expected from Q3 and ₹800-900 crore over five to six years.

New U.S. Manufacturing Platform · Nikhil Mansukhani (MD)

  • The board approved a U.S. pipe plant one day before the call, to be held through a wholly owned subsidiary.
  • The proposed facility would have approximately 350,000 metric tons of capacity and total project capex of around $110 million.
  • Management cited strong U.S. energy demand, the market's protectionist barriers and the advantage of manufacturing close to customers.
  • The stated focus was disciplined execution and commissioning in line with the project plan.

Order Book and Execution Outlook · Nikhil Mansukhani (MD)

  • The consolidated order book was approximately ₹3,500 crore across India and Saudi Arabia, while the bid book was approximately ₹19,000 crore.
  • Management said most orders were scheduled for execution over the next six to nine months.
  • NPC momentum was expected to continue in H2; India's West Asia logistics remained a headwind, but deferred shipments and the order book provided visibility.

Q2 Consolidated Financial Performance · Sandeep Kumar Garg (CFO)

  • Q2 FY27 revenue from operations was ₹1,216 crore, up 49% YoY; EBITDA was ₹190 crore, up 86.6% YoY and 20% QoQ.
  • EBITDA margin increased to 15.6% from 12.5% YoY and 14.6% in the prior quarter.
  • PAT was ₹82 crore, up 102% YoY, while PAT margin improved to 6.7% from 4.5% sequentially.

NPC Financial Contribution · Sandeep Kumar Garg (CFO)

  • From 21 May to 30 September, NPC generated SAR 208 million of revenue, SAR 37 million of EBITDA and SAR 31 million of PAT, equivalent to ₹532 crore, ₹94 crore and ₹79 crore.
  • For Q2 FY27, NPC generated SAR 191 million of revenue, SAR 34 million of EBITDA and SAR 30 million of PAT, equivalent to ₹486 crore, ₹88 crore and ₹77 crore.
  • NPC's Q2 EBITDA margin was about 18% and PAT margin 15.8%.
  • NPC had no borrowing, and its net worth was about SAR 618 million, equivalent to approximately ₹1,576 crore at 30 September 2026.

H1 Performance and Capital Priorities · Sandeep Kumar Garg (CFO)

  • H1 FY27 revenue grew 43.6%, EBITDA grew 89.2% and PAT grew 122.1% YoY.
  • H1 EBITDA margin expanded by 136 basis points to 15.1%, while PAT margin expanded by 220 basis points to 6.3%.
  • Management's stated priorities were disciplined capital deployment, timely project execution and efficient conversion of the order book into revenue and cash flow.

In their words

It was a timing and logistic disruption, not a loss of business. The contracts are intact, and the customer relationship is unchanged.
Nikhil Mansukhani (Managing Director, Man Industries)
The U.S. is a closed economy. I think we all are seeing that if you are there, you are getting the orders. If you are not there, you are not getting the orders.
Nikhil Mansukhani (Managing Director, Man Industries)
There is no profit or loss to the company, but because of accounting purpose, we have to show it separately.
Sandeep Kumar Garg (Chief Financial Officer, Man Industries)

To check next time

What management committed to on this call, or the dates they gave.

  • Check whether most of the approximately ₹300 crore of deferred shipments were dispatched in Q3 FY27.
  • Track NPC revenue against management's expectation of north of approximately ₹500 crore in Q3 FY27.
  • Verify whether Marine Shelters starts generating cash flow from Q3 FY27.
  • Check for the further update management promised on the US plant's 12-14 month timeline.
  • Track progress toward February FY28 financial closure for the US plant.
  • Check whether Q4 FY27 brings normalization in the elongated working-capital cycle.

Transcript

Read along with the recording

The whole call, 232 lines from 14 speakers over 51:47. Click any line to hear it, jump to the Q&A, or find a word. Free with an account.

Sign up freeLog in

The stock after the call

After the callCloseStockNifty 50