Powerica Q4 FY26 earnings call

Fri 29 May 2026POWERICA

In brief

First post-listing call: FY26 revenue ₹3,012 cr (+13.5%); targets double-digit FY27 top-line, 11-12% DG organic growth.

Management's tone
Confident
What was said
Leaned positive
Guidance
First guidance issued
Analyst pushback
Low
Stock, next session
−3.51% (Nifty 50 −1.50%)
  • FY26 revenue crossed ₹3,012 cr (+13.5% YoY) for the first time; EBITDA ₹386 cr at 12.8% margin, PAT ₹277 cr at 9.2% margin.
  • Q4 FY26 revenue ₹801 cr (+10.9% YoY), EBITDA ₹86 cr at 10.8% margin, PAT ₹45 cr at 5.6% margin; margins trailed H1 on geopolitics.
  • Wind revenue ₹512 cr (+28.6% YoY) at 31.3% EBITDA margin; IPP 40% / EPC-O&M 60% mix; 330.85 MW operational plus 52.7 MW under construction.
  • Post-IPO, repaid ₹525 cr debt in Q1 FY27; cash plus investments ~₹450 cr; finance cost set to drop materially from Q1 FY27.
  • Targets double-digit FY27 top-line growth with 11-12% DG organic growth; Platino to grow faster; 75/25 DG-to-wind mix in 4-5 years.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q4 FY26

This quarterA year agoLast quarterMargin
Revenue₹801 cr—+5.0%
EBITDA (excl. other income)₹84.1 cr—+7.8%10.5%
Net profit₹42.5 cr—−55.6%5.3%
EPS (₹)₹3.82—−56.7%

From the company's filed results for the quarter ended 31 Mar 2026 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

Where management's figures differ from the filing

  • Q4 FY26 PAT: said ₹45 cr at 5.6% margin (as stated on call); filed ₹42.51 cr at 5.3% margin. Stated figure is ~5.8% above filed; reason for the difference not stated on the call.

What moved the numbers, as management explained it

  • FY26 PAT ₹277 cr was lifted by an INR51 cr deferred tax credit tied to the post-budget tax regime change — not a run-rate item. (one-off)
  • Wind +28.6% YoY at 31.3% EBITDA margin drove mix benefit; structurally higher margin than DG at 9.1%.
  • Q4 FY26 EBITDA margin 10.8% trailed FY26 average of 12.8% due to geopolitical tensions and supply chain pressures in Q4.
  • MSLG revenue is milestone-driven with 12-48 month project cycles; quarter alone is not representative of the segment.
  • Post-IPO ₹525 cr debt repayment in Q1 FY27 and the lower finance cost materially supports PAT margin from Q1 FY27 onward — step-change.

The numbers management led with

  • FY26 Revenue from operations: INR3,012 crores (+13.5% Y-o-Y)
  • Post-IPO debt repayment: INR525 crores repaid in Q1 FY27
  • Cash and investments position: INR450 crores as on May 26, 2026
  • Wind installed capacity: 330.85 MW across 12 projects in Gujarat; 52.7 MW under construction; 100 MW GUVNL bid secured; 50 MW advanced planning

Guidance

Guidance on this call

WhatForWhat management said
Double-digit top line growthFY27We are targeting double-digit top line growth in FY27.
DG Sets organic growthFY27We target an organic growth of about 11%, 12% from our DG space.
50 MW capex capitalization (Wind Power)FY27We are going to capitalize another 50 megawatt during the year.
Wind IPP EBITDA margin (new projects, year 1) (Wind Power (IPP))—The new projects, the first year of the operation, it will be around 88% - 87% of the EBITDA.
Wind IPP EBITDA margin (stabilised) (Wind Power (IPP))—Gradually... it will stabilize at 82% - 83% of the EBITDA margin in the IPP.
Revenue mix DG / Wind (4-5 years)FY26-FY30In the next four or five years, it will be in the range of 75%, 25% only.
Wind EPC run-rate per MW (Wind Power (EPC))FY27Around INR1.6 crores, INR1.7 crores per megawatt almost INR400 crores of the BoP business.
Wind EPC volume per year (Wind Power (EPC))FY27That will be you can say 250, 300 megawatt or 250 megawatt every year.

The business

By business

DG Sets

83% of FY26 revenue with 10.9% YoY growth at 9.1% EBITDA margin. Cummins DG Sets ~66% of FY26 revenue, MSLG (Hyundai) ~5%; data centres ~12% of Cummins revenue; high horsepower >50% in value terms.

Revenue share 83% · YoY growth 10.9% · EBITDA margin 9.1% · Cummins share ~66% · MSLG share ~5% · Data centre share of Cummins 12% · High horsepower share >50%

Outlook: Targets 11-12% organic growth in FY27; data centre share to rise; expects to beat ~10.5% industry average.

Wind Power (IPP + EPC/O&M)

16.9% of FY26 revenue at ₹512 cr (+28.6% YoY), EBITDA margin 31.3%. IPP 40%, EPC-O&M 60% mix. IPP portfolio 330.85 MW operational + 52.7 MW under construction + 100 MW GUVNL bid + 50 MW advanced planning.

Revenue ₹512 cr · YoY growth 28.6% · EBITDA margin 31.3% · IPP share 40% · EPC-O&M share 60% · IPP operational 330.85 MW · IPP under construction 52.7 MW

Outlook: IPP portfolio to scale to wind and WSH by 2030 (RE park land pending); evaluating hybrid wind-solar-battery; 250-300 MW/year BoP EPC.

Allied Business

12.5% of FY26 revenue. Includes EMI shelters, containers, defence applications, acoustic enclosures, Schneider Electric Prisma Panels and project-related work.

Revenue share 12.5%

Platino (Associate)

Associate company with Platino RECD retrofit emission device (cuts DG emissions up to 92%, priced ₹3-30 lakh per installation). Q4 FY26 sales ₹22 cr, PBT ₹5.8 cr.

Q4 FY26 sales ₹22 cr · Q4 FY26 PBT ₹5.8 cr · Device price ₹3-30 lakh · Emission cut up to 92%

Outlook: Expected to grow faster than DG set business as state-level emission mandate enforcement accelerates.

Balance sheet, capex and funding

  • Debt repayment; Repaid ₹525 cr of existing debt in Q1 FY27 using IPO proceeds.
  • Cash position; Cash plus investments ~₹450 cr as on 26 May 2026.
  • Capex spent FY26; 51.3 MW of capex incurred during the year.
  • Capex planned FY27; Additional 50 MW expected to be capitalized in FY27.
  • Finance cost; Substantial reduction expected in Q1 FY27; directly to enhance PAT margin.
  • Working capital; Cycle improved during FY26 via disciplined inventory, AR and receivable management.

The industry, as management sees it

Management sees a structurally strong outlook for power infrastructure backed by data center investments, 500 GW renewable target, private C&I PPAs, FDRE/24x7 RTC products, and EV charging-driven backup demand. Near-term Q1 FY27 headwinds from geopolitics, energy prices and supply chain are flagged as transient.

Risks management named

  • Geopolitical tensions, rising energy prices and supply chain pressures weighing on near-term Q1 FY27 demand
  • Right-of-way issues in wind projects persisting due to competition for windy sites
  • Khavda 2 GW RE JV with GE Vernova gated on Gujarat government land allotment
  • Wind Q3-Q4 PLF seasonality compresses IPP revenue and margin in second half

Q&A

Q&A was cordial and largely friendly with no aggressive pushback. Discussion was dominated by wind (Khavda JV status, IPP margins and PLF, EPC pipeline of 585 MW, FY27 EPC vs IPP mix) and data centers (12% of Cummins revenue, high-horsepower 50%+, order book visibility, technology threat from fuel cells). Notable deflection: the Platino Q4 number was promised and only delivered late in the call, and a question on power backup as % of total data center capex was declined on grounds of difficulty to quantify. Wind PLF and IPP EBITDA margin disclosures were granular, suggesting management is comfortable being specific on its core renewable business. The Khavda land question received a candid 'not yet allotted' response, indicating limited near-term project visibility.

Not answered directly

  • Platino Q4 FY26 standalone P&L (initially deferred, later provided)
  • Power backup as a percentage of total data center capex (declined on grounds of difficulty to quantify)
  • Price vs volume split in FY27 DG Sets growth (only 11-12% growth cited, no split)

Asked for a number, answered without one

  • FY27 EBITDA margin guidance: Said Q4 hit by geopolitics and prior CPCB4 impact, views as temporary; said FY27 will be 'in the target' but will come back with a better number from Q2 onwards.
  • Power backup as % of hyperscaler data centre capex: Said difficult to quantify; genset quantity per data centre can range 10 to 50-60-90 units; installation can be 25-75% of order value.
  • FY27 capex and depreciation in ₹: Said ~50 MW more to capitalize in FY27 and higher depreciation; MSLG has no capex as it is service-based; no ₹ amounts given.

Every question, with its answer

  1. 1. Platino Q4 numbers; FY27 margin outlook

    Nidhi Shah, ICICI Securities

    Question. My first question is on the Platino business. In Q4, what was the revenue and PAT? Second, on margins — Q3 and Q4 EBITDA margins have been slightly subdued versus Q1 and Q2. Is the 10-10.5% margin range what we should expect for FY27 or are margins expected to improve?

    Answer, Ritesh Agrawal, Group CFO. On Platino, CFO said he will come back with the Q4 number in a queue. On margins, he said FY26 excluding Q4 was impacted by geopolitical tensions; the company believes this is temporary and FY27 margin will be in target, materially clearer from Q2 onwards. Pradeep Gupta added that wind generation in first two quarters of FY27 will be higher and that supports margin seasonality — Q1 and Q2 wind EBITDA margin will be higher, Q3 and Q4 lower on IPP side.

    Not answered directly.

  2. 2. Wind EPC pipeline

    Nidhi Shah, ICICI Securities

    Question. On the EPC and O&M side for wind, how are we seeing the inquiry pipeline buildup for FY27? Other companies have suggested slight delays because of land and connectivity issues — are we facing similar problems?

    Answer, Pradeep Gupta, Whole-Time Director. Pradeep Gupta said they have an order pipeline of almost 585 MW being executed till December '27. 175 MW in Gujarat is likely to be completed by December '26 and 410 MW for Torrent Power in Maharashtra is under execution. He said they have definitive contracts and orders in hand.

  3. 3. Khavda 2 GW RE project

    Divyam Sureka, Nuvama

    Question. On the wind generation side, with Power Grid saying ROW issues are easing, how is execution progressing for the 2 GW RE project and what is the expected completion timeline?

    Answer, Pradeep Gupta, Whole-Time Director. Pradeep Gupta said Khavda is a long-term project along with the JV with GE Vernova. Land acquisition from Gujarat government is in the final process but has not been acquired or allotted yet; only after that will the project take shape. He said ROW situation is not improving — competition and investment in RE is increasing, demand-supply gap exists in windy places, and challenges remain.

    Follow-up. What was the EBITDA margin and PLF specifically of the IPP business in FY26?

    Answer. Pradeep Gupta said new machines come with 36.5% PLF and older machines 23-24% PLF; average PLF in the 280 MW profile is around 26%. IPP EBITDA margin for the entire portfolio is 60-62%; new projects first-year at 87-88% and stabilising at 82-83% after O&M stabilises.

  4. 4. FY27 EPC vs IPP mix

    Divyam Sureka, Nuvama

    Question. What is the revenue split envisaged between EPC and IPP in FY27, given EPC was higher this year? Will the trend continue or shift towards IPP?

    Answer, Pradeep Gupta, Whole-Time Director. Pradeep Gupta said IPP portfolio will gradually increase — 330 MW today, 50 MW under construction to be added, 100 MW GUVNL bid next year, every year IPP will be added over the next 4-5 years. EPC will be steady at around 250-300 MW per year at ~INR1.6-1.7 cr/MW equating to ~INR400 cr BoP business annually. IPP top line will also expand.

  5. 5. FY27 growth drivers

    Devang, Modern Asset Management

    Question. For the coming financial year, what are some of the key growth drivers?

    Answer, Jai Ram Oberoi, Whole-Time Director. Jai Ram Oberoi said on DG side, macro-level capex investment in data centers is a huge driver; Powerica entered data center space in 2021 and has gained the trust of hyperscale and colo players. Manufacturing and realty remain key organic drivers. Low-horsepower opportunity in EV charging backup outside metros next year. Rental market is picking up significantly.

    Follow-up. How do you see the revenue split changing over the next few years between renewable power and DG Sets?

    Answer. Pradeep Gupta said currently 83% DG and 14-15% wind; over 4-5 years it will be in the 75-25 range because DG is also growing and allied business is growing. Ritesh Agrawal added that from a revenue standpoint, mix will range 75-80% genset and 20-25% wind, but on EBITDA side the shift will be more pronounced.

  6. 6. Data center contribution and competition

    Sampath Nayak, ZTO Capital

    Question. What is the current contribution from data centers to the top line? And what is the demand pipeline and right to win vis-a-vis competitors like other genset makers fighting for hyperscaler orders?

    Answer, Jai Ram Oberoi, Whole-Time Director. Jai Ram Oberoi said data centers contributed 12% to top line last year, with steady growth expected on strong order book with visibility up to next financial year. On competitors, he said he cannot speak to competition but Powerica has good reputation with data center colocation and hyperscaler players and has executed multiple projects successfully.

    Follow-up. Bloom Energy and fuel cells are emerging in the US — do you see them as a threat to your data center business? Also, what is the contribution of power backup as a percentage of total data center capex?

    Answer. Jai Ram Oberoi said as new technology comes to India, Powerica is part to market for these engines and will service the data centers. Ritesh Agrawal said any new technology is an insurance product and genset will remain; quantity might reduce but Powerica will be part of the new tech distribution. On power backup as % of total data center capex, both Oberoi and Agrawal said it is difficult to estimate — quantity can vary from 10 to 90 units depending on size, and EPC contribution can vary from 25% to 75% of the order.

    Not answered directly.

  7. 7. FY27 DG Sets growth guidance

    Vikram Datwani, Nuvama Group

    Question. What is the growth expected for the DG Sets business in FY27? And could you quantify how much is price-led versus volume-led?

    Answer, Jai Ram Oberoi, Whole-Time Director. Jai Ram Oberoi said they target organic growth of 11-12% in DG space. MSLG contribution is on milestone basis so some quarters/years may go higher. Key growth driver is data centers as orders get executed; Powerica expects to beat the industry average of about 10.5% given experience in high-horsepower and data centers over four decades. Price vs volume split was not quantified.

    Follow-up. Could you throw light on the visibility for the Platino automotive business? Will it grow faster than 10-12%?

    Answer. Jai Ram Oberoi said Platino has retrofit RECD devices that fit every pre-CPCB4+ DG set, with a large addressable market. This year was about building marketing infrastructure; they look to accelerate growth. He confirmed Platino is a small-scale high-growth business and would grow faster than 10-12% as state-level mandates for RECD installation enforce adoption.

  8. 8. MSLG Australia project and FY27 capex

    Hetvi Sanghvi, HS Investments

    Question. Can you give a quick update on the Australia project for MSLG? Also, what is the capex and depreciation expected for FY27?

    Answer, Jai Ram Oberoi, Whole-Time Director. Jai Ram Oberoi said the Australia project is 90-95% complete and they have secured a good service order for ongoing O&M post-completion. Ritesh Agrawal added that in FY27, depreciation will be higher as they capitalise the 50 MW wind capacity plus an additional ~50 MW during the year, implying additional 50 MW capex. On MSLG, no major capex is needed as it is a service business.

  9. 9. Data center pipeline; Platino Q4 numbers

    Nidhi Shah, ICICI Securities

    Question. On the inquiry pipeline for data centers — do we have current inquiries ongoing, and do we expect a meaningful increase in the data center DG Sets contribution in FY27 from the current 12%?

    Answer, Jai Ram Oberoi, Whole-Time Director. Jai Ram Oberoi said data center inquiries are consistently ongoing and they have 9 months to about a year of order book visibility. Ritesh Agrawal added that post-budget, there is a surge in inquiries and they see very robust order book. Ritesh Agrawal also came back on Platino: INR22 crores of sales with INR5.8 crores of PBT in Q4 FY26.

    Follow-up. Is the 12% data center contribution of the 66% Cummins business? And what is the weightage of high-horsepower DG Sets within Cummins business? Any other growth drivers in FY27?

    Answer. Jai Ram Oberoi confirmed 12% data center is of the 66% Cummins business. Ritesh Agrawal said high-horsepower contribution is over 50% in terms of value, with healthy 6-7 month order book. Jai Ram Oberoi added that manufacturing and realty remain key growth drivers across the product range; data center has not displaced them. Rental players are also picking up.

What was said

Topic by topic, in the order it was spoken

First earnings call post-IPO and company journey · Jai Ram Oberoi (Whole-Time Director)

  • Marks Powerica's first earnings call after listing; founders built the DG set category in India in early 1980s when delivery times were 8-10 weeks from unorganised vendors.
  • Cummins India OEM partnership since 1984; MSLG division added in 1996 and Hyundai association in 2014 covers 3,000-10,000 kVA range for cement, steel, nuclear and fertiliser.
  • Manufacturing in Bangalore, Silvassa and Khopoli with in-house acoustic enclosures, fuel/exhaust systems, control panels — engine and alternator are the only bought-out components.
  • Product range of 7.5 kVA to 10,000 kVA described as the broadest single-integrated-manufacturer portfolio in India.

DG Sets, data center and growth drivers · Jai Ram Oberoi (Whole-Time Director)

  • DG Sets outlook remains strong; data center application backed by DCA-approved engines and gensets is a key driver, particularly high-horsepower orders.
  • Customer base spans manufacturing, real estate, infrastructure, pharma, government, defence, IT/data centers and rental fleet operators — providing diversified resilience.
  • Wind IPP 330.85 MW across 12 Gujarat projects; associate Platino Automotive positioned for CPCB4+ retrofit opportunity with device cost INR3-30 lakh and up to 92% emissions reduction.
  • Q1 FY27 near-term demand soft on geopolitics, energy prices and supply chain; long-term supported by electrification, renewable integration, EV ecosystem and data center investments.

Wind portfolio strategy and EPC pipeline · Pradeep Gupta (Whole-Time Director)

  • Wind portfolio covers IPP, EPC and O&M for BoP; existing IPP backed by 25-year PPAs with GUVNL and SECI at fixed tariff; 52.7 MW under construction will take portfolio to 384 MW.
  • Secured additional 100 MW GUVNL bid at Botad (under development) and 50 MW under advanced planning; aim to scale IPP across wind and WSH by 2030 subject to RE Park land allotment.
  • BoP EPC projects: 175 MW at Khambaliya for Airpower Wind Farms and 250 MW at Beed for Torrent Surya Urja — incremental revenue without major equity deployment.
  • Strategic relationships with GE Vernova and Vestas; actively evaluating hybrid wind-solar-BESS opportunity within own IPP portfolio for dispatchable clean energy.

FY26 financial performance and balance sheet · Ritesh Agrawal (Group CFO)

  • Q4 FY26 revenue INR801 cr (+10.9% YoY), EBITDA INR86 cr at 10.8%, PAT INR45 cr at 5.6%; FY26 revenue INR3,012 cr (+13.5%), EBITDA INR386 cr at 12.8%, PAT INR277 cr at 9.2%.
  • Lower tax expense in FY26 reflects INR51 cr deferred tax credit on account of tax regime change post-budget; DG Sets 83% of revenue at 9.1% EBITDA margin, Wind 16.9% at 31.3% margin.
  • Cummins-powered DG sets ~66% of revenue, MSLG ~5%; Allied (EMI shelters, containers, defence, acoustic enclosures, Schneider Prisma panels) 12.5% of revenue.
  • Working capital improved; INR525 cr debt repaid in Q1 FY27 post-IPO leaving INR450 cr cash and investments as on May 26, 2026 — material finance-cost reduction expected in Q1 FY27.

In their words

Powerica is not a DG Set manufacturer, we are a power solutions provider. So we will always provide the best overall solution for the customer, and we'll always find a way to deliver it.
Mr. Jai Ram Oberoi (Whole-Time Director, Powerica Limited)
Any of the new technology, whichever will come, the generator set is a power backup, which is basically an insurance for any of the activities that we do. So whatever we'll do, the genset will be there.
Mr. Ritesh Agrawal (Group CFO, Powerica Limited)

To check next time

What management committed to on this call, or the dates they gave.

  • Q1 FY27 finance cost run-rate post ₹525 cr debt clearance (step-change in PAT).
  • Q2 FY27 wind margin lift from seasonal higher PLF and 52.7 MW capex capitalization.
  • Data centre DG set share of FY27 vs FY26 12% — meaningful increase signalled.
  • Platino revenue acceleration with state-level emission mandate enforcement.
  • Australia MSLG project completion (90-95% on call) and O&M service revenue.
  • GUVNL 100 MW bid at advanced development — trigger for IPP capacity addition.

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Fri 29 May 2026₹551.45−3.51%−1.50%
5 sessions Thu 4 Jun 2026₹514.95−9.90%−2.05%
20 sessions Thu 25 Jun 2026₹660.25+15.53%+0.62%

From the close of Wed 27 May 2026, ₹571.50: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

Powerica's other calls