Solex Energy Q2 FY26 earnings call

Mon 10 Nov 2025SOLEX

In brief

Solex H1 FY26 revenue ₹415.7 cr (+51.8% YoY), PAT margin 7.3%; FY26 revenue guided at ₹2,000-2,200 cr despite monsoon-hit Q2.

Management's tone
Confident
What was said
Leaned positive
Guidance
Guidance held
Analyst pushback
Low
Stock, next session
−4.38% (Nifty 50 +0.32%)
  • H1 FY26 revenue ₹415.7 cr (+51.8% YoY); EBITDA margin expanded to 14.7% from 9.6% in H1 FY25; PAT ₹30.5 cr with margin 7.3%.
  • Q2 muted by an extended 6-month monsoon that delayed IPP site readiness; finished goods inventory rose to ₹153 cr (Sept 30) from ₹25 cr (March 31), pushing working capital to 102 days.
  • Lines 3 and 4 commissioned taking total module capacity to 4 GW from end-October 2025; company on NSE main board from Oct 8, 2025.
  • Order book at ₹4,000+ cr (incl. ₹100 cr EPC) as on Sept 30, 2025; 100% Solex own-brand mix now driving gross margins to ~29%.
  • Cell line: 2.2 GW N-Type TOPCon Plus target commissioning March 2027; total capex ₹1,500 cr funded via ₹1,000 cr debt and ₹500 cr equity through QIP.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q2 FY26

This quarterA year agoLast quarterMargin
Revenue₹155 cr——
EBITDA (excl. other income)₹18.6 cr——12%
Net profit₹5.8 cr——3.7%
EPS (₹)₹27.20——

From the company's filed results for the quarter ended 30 Sept 2025 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

What moved the numbers, as management explained it

  • Shift to 100% Solex own-brand from earlier OEM-heavy mix lifted gross margins to ~29% on richer pricing and better cost recovery.
  • Economies of scale as capacity utilisation built from 1.5 GW (H1) toward 4 GW (H2) supported EBITDA margin expansion to 14.7% (H1 FY26) from 9.6% (H1 FY25).
  • Extended monsoon (6 months vs normal 4) delayed IPP site readiness, building finished goods inventory to ₹153 cr (Sept 30) and muting Q2 deliveries; expected to reverse in Q3. (one-off)
  • GST rate cut on modules from 12% to 5% effective Sept 21, 2025 caused pending billing/dispatches for roughly a week, weighing on Q2 invoicing. (one-off)
  • Working capital rose to 102 days (H1 FY26) from 61 days (FY25) on finished goods inventory plus raw material stocking for Lines 3-4 ramp-up; not a P&L driver but a balance sheet distortion.

The numbers management led with

  • Order book: Rs 4,000+ crore as of 30 September 2025 (including Rs 100 cr EPC)
  • Module manufacturing capacity: 4 GW operational from October 2025 (Lines 1-4), with 2.5 GW incremental planned by Q1 FY27
  • Cell manufacturing capacity: 2.2 GW N-Type TOPCon Plus targeted by March 2027, with 10 GW total roadmap
  • Cell capex: Rs 1,500 cr total (Rs 1,100 cr cell line + Rs 200 cr module + Rs 100 cr WC); funded Rs 1,000 cr debt + Rs 500 cr equity

Guidance

Guidance on this call

WhatForWhat management said
FY26 revenue guidanceFY26FY26 revenue guidance ₹2,000-2,200 cr
PAT margin—Will stick to 6% to 7% PAT margin, with potential to improve on efficiency
Working capital daysFY26Working capital to reduce to approximately 80 to 85 days by end of FY26
Cell line capacity commissioning (Cell manufacturing)FY272.2 GW N-Type TOPCon Plus cell line target commissioning March 2027
Next-phase module capacity commissioning (Module manufacturing)FY27Incremental 2.5 GW module capacity targeted by end of H1 of next year (April to June)

What changed since the Tue 27 May 2025 call

WhatOn the Tue 27 May 2025 callOn this call
FY26 revenue guidance (cut)FY26 revenue guidance retained at INR2,200-2,400 cr (earlier INR2,400 cr)FY26 revenue guidance ₹2,000-2,200 cr
Mainboard migration (achieved)ESM/SME status delays mainboard migrationMigrated to NSE main board on Oct 8, 2025
Module capacity 4 GW (achieved)Capacity ramping from 1.5 GW to 4 GW by Oct'25Lines 3 and 4 commissioned, total 4 GW operational from end-October 2025
Order book (raised)Order book INR1,450 cr (CRISIL) with ~INR1,300 cr from a single clientOrder book ₹4,000+ cr (incl. ₹100 cr EPC); served by diverse national and international IPPs
Cell line QIP timing (delayed)Raise INR500 cr equity within 2-3 monthsQIP engagement with banker to close later this week (mid-November 2025)
Next-phase 2.5 GW module capacity (new)Not detailed in previous callTargeted by end of H1 of next year (April to June)
PAT margin guidance (held)Maintain PAT margin 6-7%Will stick to 6% to 7% PAT margin, with potential to improve on efficiency

The business

By business

Module manufacturing

H1 FY26 revenue ₹415.7 cr (+51.8% YoY); Lines 1-2 ran at 1.5 GW through H1, Lines 3-4 commissioned from end-October taking capacity to 4 GW. 100% Solex own-brand mix lifted gross margin to ~29%.

H1 FY26 revenue ₹415.7 cr · +51.8% YoY · EBITDA margin 14.7% · PAT margin 7.3% · Capacity 4 GW

Outlook: Q3 FY26 to capture dispatch of ₹153 cr finished goods and ramp-up of Lines 3-4; aligned with FY26 revenue guidance of ₹2,000-2,200 cr; margin expected to improve on scale and own-brand mix.

Cell manufacturing

2.2 GW N-Type TOPCon Plus cell line under planning with ISC Konstanz R&D collaboration; land identified, awaiting funding closure.

Target capacity 2.2 GW · Capex ₹1,100 cr

Outlook: Commissioning targeted March 2027; further 3 GW and 5 GW phased per technology roadmap with ISC Konstanz.

EPC

Around ₹100 cr of EPC orders included within the ₹4,000+ cr order book as on Sept 30, 2025; not broken out separately in financials.

₹100 cr EPC orders

Balance sheet, capex and funding

  • Working capital at 102 days in H1 FY26 vs 61 days at FY25 end; targeted reduction to 80-85 days by end-FY26 as dispatches normalise.
  • Total capex plan of ₹1,500 cr: ₹1,100 cr for cell line, ₹200 cr for proposed module, ₹100 cr for working capital.
  • Funding plan: ₹1,000 cr bank debt plus ₹500 cr equity via QIP; engagement with banker to be closed later this week.
  • Debt-to-equity slightly elevated due to project drawdowns; expected to improve as operating cash flows strengthen in H2 FY26.
  • Finished goods inventory ₹153 cr (Sept 30, 2025) vs ₹25 cr (March 31, 2025); ready for dispatch from Q3 FY26.

The industry, as management sees it

Management sees robust, sustained demand for solar in India - annual capacity addition has grown from 8-10 GW pre-2019 to 30-40 GW today, with BESS adoption expected to double this to 60-70 GW. Repowering of legacy 200-250 Wp plants with 625-650 Wp modules is an additional demand driver. Chetan Shah explicitly dismissed the module oversupply narrative, arguing the real capacity that will dictate the future is cell capacity (not module), and that smaller Mono-PERC-only players will either exit or replace capacity.

Risks management named

  • Working capital at 102 days, expected to normalise to 80-85 days by FY26 end
  • Extended monsoon delayed IPP site readiness, resulting in Rs 153 cr of finished goods inventory
  • Cell line project depends on confirmed availability of 2 MLD (5 MLD at 5 GW scale) water and dedicated power for 5 GW
  • Debt-to-equity ratio currently elevated due to project-related drawdowns

Q&A

Q&A was friendly and exploratory with low pushback intensity. Discussion centred on (1) the H1 revenue dip and FY26 guidance achievability, (2) the 2.2 GW cell line project status, funding and site readiness, and (3) industry demand and oversupply. Management gave a confident and detailed response on each, reaffirming FY26 revenue guidance and providing more visibility on the cell capex structure (Rs 1,000 cr debt + Rs 500 cr QIP). The only partially-answered question was on H2 EBITDA margin range, where management gave directionality rather than a specific number.

Not answered directly

  • FY27 capacity-driven revenue upside
  • H2 FY26 specific EBITDA margin range

Asked for a number, answered without one

  • H2 FY26 EBITDA margin band: CFO said the company feels it would surpass what was achieved in H1 but did not quantify an H2 band
  • Order book revenue split FY26 vs FY27: Said ₹1,300 cr WIP orders are to be delivered before March 31, 2026; did not give a quantitative FY27 split
  • FY27 revenue target with next-phase capacity: Said the FY27 number is based on current 4 GW; further 2.5 GW numbers to be shared later

Every question, with its answer

  1. 1. Q2 revenue dip and monsoon impact

    Raghav Maheshwari, Individual Investor

    Question. Q2 dip in sales attributed to monsoon, but other solar module manufacturers were not affected. Is it that delivery is pending or the complete production is delayed because of the monsoon?

    Answer, Chetan Shah, Chairman and Managing Director. Most orders are from IPPs and their site readiness has been the big challenge, leading to inventory piling up. There is no material impact on production; it has run as scheduled and deliveries have now started. Q3 should reflect improvement. Gujarat monsoon started on 15 May this year versus the usual 15 June, contributing to the situation.

  2. 2. FY26 revenue guidance

    Raghav Maheshwari, Individual Investor

    Question. In the last concall you indicated a Rs 2,200 cr target for FY26. With H1 only at ~Rs 415 cr, is this still viable or are you downsizing?

    Answer, Chetan Shah, Chairman and Managing Director. RE business has a typical annual cycle where H1 is always low and H2 comes in multiples. Solex is aligned with the earlier guidance, supported by a strong order book to be executed before 31 March. Management is confident of achieving the numbers guided for H2, with annual revenue reflecting the same. Hemal Kachiwala and Vipul Shah added that Line-3 and Line-4 are operational from October, full 4 GW is available for H2, and the ramp-up supports the earlier estimated sales.

  3. 3. Gross margin expansion drivers

    Manan Shah, Moneybee Investment Advisors

    Question. Gross margins expanded to almost 29% this quarter. What drove this and is there potential for further expansion and sustainability?

    Answer, Vipul Shah, Director. Two factors: first, the previous year had a mix of OEM and own brand whereas this year almost the entire sales are Solex own brand, adding to margin; second, economies of scale benefits. On sustainability, Vipul Shah said Solex achieved the margin targeted in the previous call and is confident margins will improve further from current levels with new lines, order book, and operational efficiency.

    Follow-up. What is the OEM vs own-brand mix in the Rs 4,000+ cr order book?

    Answer. Vipul Shah: Everything is Solex (own brand).

  4. 4. ISC Konstanz MoU significance

    Manan Shah, Moneybee Investment Advisors

    Question. On the recently signed MoU with ISC Konstanz - what is its importance and how will it help achieve the cell ambition?

    Answer, Chetan Shah, Chairman and Managing Director. ISC Konstanz is a German R&D institute, the inventor of back-contact technology (passed on to AIKO and LONGi). Long-term goal is to develop an Indianised rear contact cell technology with Solex for global markets. They will also help operationally on the 2.2 GW TOPCon Plus cell line, monitoring output and quality to enable faster ramp-up. They will also support strategic planning as the company migrates from TOPCon Plus to rear-contact technology, aligning the 10 GW cell roadmap (2 GW + 3 GW + 5 GW) with the technology curve.

  5. 5. Industry demand and oversupply

    Manan Shah, Moneybee Investment Advisors

    Question. Some projects are not securing PPAs and being shelved. Is there an impact on module demand side? Any risk of oversupply in the industry?

    Answer, Chetan Shah, Chairman and Managing Director. PPA delays are temporary and tied to transmission infrastructure development (Adani 735 kV, Reliance and government grid build-out). Demand visibility remains strong: India did 8-10 GW p.a. pre-2019 (95% imports), 30 GW last year, likely 40 GW this year, all 100% from Indian factories. BESS is a major incremental driver (current 30-40 GW will move to 60-70 GW), plus repowering of legacy 200-250 Wp installations with 625-650 Wp modules in India and Europe. Chetan Shah does not see a demand or oversupply challenge for the next couple of years; the real capacity constraint is cell capacity, not module capacity. Smaller players with Mono-PERC lines will either close or replace; module overcapacity is not a concern.

  6. 6. Export market opportunity

    Manan Shah, Moneybee Investment Advisors

    Question. On the export front, recently there was a large order from Zelestra group. Are there more such opportunities? How do Indian manufacturers compete with China in exports?

    Answer, Chetan Shah, Chairman and Managing Director. Clarified that the Zelestra order is for their Indian project, not export. On exports generally: India exported only 500 MW in 2019 vs 5-7 GW p.a. now, with 30 GW p.a. opportunity. Geopolitical situation needs to settle; US and Europe reservations/quota for Indian modules are expected in coming months. Solex has a smaller export presence currently and expects a sizable number once ready to export.

    Follow-up. For the incremental 2.5 GW capacity planned for next year, should it come online in H1 or H2?

    Answer. Chetan Shah: Targeting by end of H1, i.e., between April and June.

  7. 7. FY27 capacity expansion outlook

    Manan Shah, Moneybee Investment Advisors

    Question. The FY27 target is currently based on 4 GW capacity. With ~6 months of incremental 2.5 GW availability, is there potential upside?

    Answer, Chetan Shah, Chairman and Managing Director. Next year number is based only on 4 GW of current capacity. Once the new addition rolls out, the company will update guidance. Vipul Shah added that the location decision (Gujarat or elsewhere) is underway and more clarity will be shared when finalised.

    Not answered directly.

  8. 8. Cell line project status

    Devvrat Himatsingka, Augmenta Asset Manager

    Question. What is the status of the cell line? Have you procured land? When can we expect it to come in?

    Answer, Chetan Shah, Chairman and Managing Director. Target: commission 2.2 GW N-Type TOPCon Plus cell line by March 2027. Experienced team in place; technology equipment discussions nearly closed (China and Germany suppliers). Two sites identified; key challenges are electricity availability for 5 GW and water (2 MLD initially, 5 MLD at 5 GW scale). Considering both canal and groundwater to avoid future constraints. ISC Konstanz and other experienced manufacturers supporting on technology. Funding for land, equipment, and civil work at advanced stage with financial institutions. Execution time will be shorter than peers since planning is on paper.

  9. 9. Cell capex funding structure

    Naveen Bansal, Paradise Moon Investment

    Question. For the cell manufacturing, what will be the debt/equity structure for the Rs 1,100-1,200 cr raise?

    Answer, Chetan Shah, Chairman and Managing Director. Total capex Rs 1,500 cr: Rs 1,100 cr for cell line, Rs 200 cr for proposed module, Rs 100 cr for working capital. Mix: Rs 1,000 cr bank debt + Rs 500 cr equity. Vipul Shah confirmed the equity raise is via QIP and the banker engagement will close later this week.

    Follow-up. Will market cap increase by Rs 500 cr after the QIP round?

    Answer. Vipul Shah: Yes.

  10. 10. FY26 revenue achievability

    Naveen Bansal, Paradise Moon Investment

    Question. Last call you said top line would be Rs 2,000-2,200 cr but H1 is only Rs 415 cr. Are you hopeful of achieving the balance in H2?

    Answer, Chetan Shah, Chairman and Managing Director. Guidance was Rs 2,000-2,200 cr based on commissioning of Line-3 and Line-4 (high-speed 2.5 GW lines). H1 had only two lines (1.5 GW) plus the extended monsoon. By 20 November, all sites should be ready, delivery will begin and revenue will be booked. Vipul Shah added that GST reduction on modules from 12% to 5% effective 21 September 2025 also caused billing and dispatch delays during that week.

    Follow-up. Will margins remain at these elevated levels going forward?

    Answer. Chetan Shah: With extended capacity, production and deliveries should improve margins, but company will stick to its stated 6-7% PAT margin. With efficiency, improvement is expected.

  11. 11. Order book execution timeline

    Mihir Deasai, Desai Investments

    Question. On the Rs 4,000+ cr order book including EPC - what is the execution timeline and revenue conversion over the next two years?

    Answer, Hemal Kachiwala, Chief Financial Officer. The Rs 4,000+ cr order book is to be executed in FY26 and FY27. The order book has three parts: first, confirmed POs already disclosed; second, MSAs signed with POs awaited; third, MSAs in finalisation. Chetan Shah added that WIP orders amount to ~Rs 1,300 cr to be delivered before 31 March, plus existing Rs 153 cr inventory takes the total to ~Rs 1,450 cr for near-term delivery.

    Follow-up. What portion of the order is currently in WIP, with revenues visible in coming quarters?

    Answer. Hemal Kachiwala: Rs 153 cr finished goods as of 30 September is immediately available for Q3 sale. WIP portion is minimal in this industry - it is either raw material or finished product. WIP orders to be delivered by March total ~Rs 1,300 cr.

  12. 12. Customer preference N-Type vs PERC

    Mihir Deasai, Desai Investments

    Question. Is there a shift in customer preference from N-Type to PERC modules? How will this influence selling prices and gross margins?

    Answer, Chetan Shah, Chairman and Managing Director. N-Type modules are now more stable and in demand; P-Type demand is decreasing. Solex was the first in India to launch G12R modules in October last year, which has been the most successful product. Mono-PERC remains relevant in the DCR/residential rooftop segment. No major difference in margin between Mono-PERC and N-Type. After existing Mono-PERC orders are complete, Line-1 (Mono-PERC) will be migrated to TOPCon to meet additional TOPCon demand.

    Follow-up. How should investors look at Solex five years down the line? What is the aspiration and vision?

    Answer. Chetan Shah: Differentiated journey - went from heavy OEM (manufacturing for ~28 Indian and 2 multinational customers) to 100% own brand, which has built credibility. Solex philosophy: belief in technology, early adoption, professional manufacturing. USPs are 30-year product warranty discipline, focus on quality, process, predictability, and working with global leaders - these will differentiate Solex over 5-10 years.

  13. 13. Inventory dispatch timeline

    Manan Shah, Moneybee Investment Advisors

    Question. Has the Rs 150 cr of rolled-over inventory already been dispatched or is it getting dispatched currently?

    Answer, Chetan Shah, Chairman and Managing Director. Dispatch is underway as sites are drying. By end-November or first week of December, most inventory should be dispatched. Most sites are in Rajasthan and Gujarat where rainfall was heavy. Solex is working closely with IPPs to align delivery and future production plans with their COD and project deadlines.

    Follow-up. Do the identified cell line sites have the necessary water and power availability, or are you still negotiating with authorities?

    Answer. Chetan Shah: For 2.2 GW, both are primarily available; at one site, water is available for even 10 GW. Discussions are on for the additional 3 GW at the same location (need internal cross-department confirmation). Company does not want to proceed on verbal confirmation alone.

  14. 14. Cell line land acquisition timing

    Manan Shah, Moneybee Investment Advisors

    Question. Should we expect the cell line land deal to conclude before calendar year-end or in January-February?

    Answer, Chetan Shah, Chairman and Managing Director. Land deal will be concluded before end of calendar year 2025.

    Follow-up. Will the incremental 2.5 GW module capacity come on the new cell line land parcel or existing area?

    Answer. Chetan Shah: Three options under evaluation - (1) acquire more space adjoining existing factory; (2) co-locate 2.5 GW with the new cell line; (3) set up in southern India to serve growing south demand and reduce logistics cost/time. Line design is finalised; awaiting location decision.

  15. 15. H2 FY26 EBITDA margin potential

    Manan Shah, Moneybee Investment Advisors

    Question. Is there potential to achieve 16-18% EBITDA margins in H2 FY26 with better absorption of fixed costs as revenue scales?

    Answer, Hemal Kachiwala, Chief Financial Officer. With scale of operations increasing to the turnover levels targeted, the company feels it will surpass the H1 EBITDA margin. No specific number was committed to, but direction is upward.

    Partly answered.

What was said

Topic by topic, in the order it was spoken

Company Milestone and Strategic Position · Chetan Shah (CMD)

  • Migrated from NSE Emerge to NSE main board on 8 October 2025
  • Inception in 1995 as EPC services provider, evolved to solar PV module manufacturer
  • Currently operates 4 GW fully automated module manufacturing facility in Surat
  • Transitioned to becoming a credible name in India solar manufacturing ecosystem over 30 years

Capacity Expansion Update · Chetan Shah (CMD)

  • Line-1 and Line-2 operated at 1.5 GW effective nameplate capacity in H1 FY26
  • Line-3 and Line-4 commissioned with combined 2.5 GW; 4 GW total operational from October end
  • Ramp-up of new lines progressing as planned
  • All four module lines now fully operational, ready for H2 dispatch

H1 FY26 Operational Performance · Chetan Shah (CMD)

  • Monsoon extended to six months versus normal four, starting in Gujarat from 15 May 2025
  • IPP site readiness delayed across multiple project locations
  • Rs 153 cr of finished goods inventory at 30 September 2025 (vs Rs 25 cr at 31 March 2025)
  • Inventory expected to convert to revenue in H2 FY26 as site installations stabilise

Order Book and Revenue Pipeline · Chetan Shah (CMD)

  • Total order book of Rs 4,000+ cr as of 30 September 2025, including Rs 100 cr of EPC
  • Serving marquee national and international IPPs
  • Multiple master service agreements in finalisation phase, expected to convert to POs
  • Mgmt aligned with earlier communicated growth outlook for FY26

Cell Manufacturing Roadmap · Chetan Shah (CMD)

  • Setting up 2 GW N-Type TOPCon Plus cell manufacturing facility
  • R&D collaboration with Germany ISC Konstanz, inventors of back-contact technology
  • Target: become fully integrated module-to-cell manufacturer
  • 10 GW cell roadmap: 2 GW immediate, 3 GW additional, 5 GW further phased based on technology curve
  • Land identified, work on power infrastructure, water, and vendor engagement in advanced stage

Financial Performance H1 FY26 · Hemal Kachiwala (CFO)

  • Total revenue Rs 4,157 million, +51.8% YoY
  • EBITDA margin improved to 14.7% versus 9.6% in H1 FY25
  • PAT of Rs 305 million, PAT margin at 7.3%
  • Strong volume growth with meaningful profitability improvement

Working Capital and Leverage · Hemal Kachiwala (CFO)

  • Working capital rose from 61 days in FY25 to 102 days in H1 FY26 due to monsoon
  • Higher finished goods and raw material stocking for Lines 3-4 cited
  • Target: reduce working capital to 80-85 days by FY26 end
  • Debt-to-equity slightly elevated due to project drawdowns, expected to improve with H2 operating cash flow

H2 Outlook · Hemal Kachiwala (CFO)

  • H2 FY26 expected to reflect higher capacity utilisation and stronger cash conversion
  • Domestic policy tailwinds and accelerating solar capacity addition supportive
  • Increasing preference for high-efficiency modules favours Solex product mix
  • Cell project capital planning at advanced stage, aligned to long-term value creation

In their words

I do not see any challenge in terms of demand or I do not see any challenge for couple of years in terms of oversupply. I keep getting questions for oversupply because of the kind of capacity, which is built up in India for the manufacturing. But that is only module. The real capacity that will decide the future is the cell capacity.
Chetan Shah (CMD, Solex Energy)
What is that differentiate Solex compared to others? That is a very highly focused and investment into the technology into the quality process into predictability, working with the global leaders to adapt a new method of manufacturing with more reliability, getting certifications internationally for the reliability of products. These are the USPs of Solex and that will differentiate Solex in coming 5 years to 10 years compared to others.
Chetan Shah (CMD, Solex Energy)
Now finished goods stock on 31st March 25, we had a stock of Rs. 25 crores, whereas on 30th September night, the finished good stock is Rs. 153 crores. So, this is ready and ready for dispatch and I think the dispatches have started. So, I think whatever was lacking in the 2nd Quarter, we will be covering up in the 3rd Quarter.
Hemal Kachiwala (CFO, Solex Energy)

To check next time

What management committed to on this call, or the dates they gave.

  • Q3 FY26 revenue delivery from ₹153 cr finished goods inventory and Lines 3-4 ramp-up
  • Working capital reduction towards the 80-85 days target by FY26 end
  • Closure of the ₹500 cr QIP and debt funding for the cell line
  • Land deal conclusion for the 2.2 GW cell line (targeted before end of CY25)
  • Decision on next-phase 2.5 GW module location (existing factory, cell-line site, or southern India)
  • Site readiness and dispatch progress at IPP customers across Rajasthan and Gujarat

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Mon 10 Nov 2025₹1,615.50−4.38%+0.32%
5 sessions Fri 14 Nov 2025₹1,710.10+1.22%+1.64%
20 sessions Fri 5 Dec 2025₹1,516.40−10.25%+2.72%

From the close of Fri 7 Nov 2025, ₹1,689.50: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

Solex Energy's other calls

  • Q1 FY27Tue 22 Sept 2026Tone: Optimistic
  • Q1 FY27Mon 17 Aug 2026Tone: Cautious
  • Q4 FY26Mon 18 May 2026Tone: Confident
  • Q3 FY26Thu 12 Feb 2026Not read
  • Q4 FY25Tue 27 May 2025Tone: Confident