ACME Solar commissions Phase-II of 300 MW BESS project in Rajasthan
ACMESOLAR · price
▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.
On the reaction day the stock moved 5.0 pts more than Nifty Smallcap 250 and 5.9 pts more than its Power Generation peers, over the same two closes: a difference in percentage points, not a measure of what the filing did.
Minute windows have no benchmark: there is no intraday index history to compare against.
ACME Solar's wholly owned subsidiary ACME Greentech Seventh commissioned Phase-II of its BESS project in Bikaner, Rajasthan on September 17, 2026, adding 52.32 MW/209.28 MWh. Total commissioned capacity now stands at 105.95 MW/423.80 MWh out of the full 300 MW/1200 MWh. COD set for September 19, 2026. PPA signed with SJVN, project financed by REC. Full commissioning expected by Q3 of current fiscal.
Positive: phased BESS commissioning on track, expanding storage capacity and adding revenue visibility from FY26 onwards.