Acme Solar Holdings Limited has informed the Exchange about commissioning of sixth phase of 38 MW / 80.252 MWh capacity of BESS Project in Rajasthan
ACMESOLAR · price
▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.
On the reaction day the stock moved 1.6 pts less than Nifty Smallcap 250 and 2.2 pts less than its Power Generation peers, over the same two closes: a difference in percentage points, not a measure of what the filing did.
Minute windows have no benchmark: there is no intraday index history to compare against.
Acme Solar Holdings, through its wholly owned subsidiary ACME Suryodaya Private Limited, has commissioned the sixth phase of a 38 MW / 80.252 MWh Battery Energy Storage System (BESS) project in Jaisalmer, Rajasthan, on April 13, 2026. The commercial operation date (COD) for this phase is set for April 15, 2026. With this phase, the subsidiary's total commissioned capacity has reached 285 MW / 601.904 MWh. This is a continuation of multiple phase-wise commissionings reported over recent months.
Positive for shareholders — steady phase-wise execution of the BESS project demonstrates operational progress and adds revenue-generating capacity. Growing the commissioned energy storage portfolio strengthens Acme Solar's positioning in the renewable energy storage segment.