No deviations in fund use; Factory 3.0 start shifts to December 2026
ATHERENERG · price
▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.
On the reaction day the stock moved 4.5 pts more than its 2/3 Wheelers peers, over the same two closes: a difference in percentage points, not a measure of what the filing did.
Minute windows have no benchmark: there is no intraday index history to compare against.
CARE Ratings reported no deviation in use of Rs 5,126 crore raised through the IPO, institutional placement and preferential issue. At September 30, 2026, Rs 1,364.25 crore of IPO proceeds had been used and Rs 1,261.75 crore remained. Factory 3.0 production is now expected in December 2026 after approval, labour and fuel delays; Phase 1 completion by March 2027 remains on track with no expected cost overrun.
Neutral on fund use, but delayed factory launch raises execution risk. The March 2027 target and no expected cost overrun limit the concern.