9.9 MW hybrid power project commissioning further delayed
BORANA · price
▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.
On the reaction day the stock moved 4.8 pts more than Nifty Microcap 250 and 5.8 pts more than its Other Textile Products peers, over the same two closes: a difference in percentage points, not a measure of what the filing did.
Minute windows have no benchmark: there is no intraday index history to compare against.
Borana Weaves said the 9.9 MW hybrid power project at Kalikanagar, Gujarat, will be commissioned in stages: the first wind turbine location and 7.65 MW solar component by November 30, 2026, the second wind turbine location by December 31, 2026, and the third by March 31, 2027. Delays resulted from high winds, monsoon-related road work and delayed power-line shutdowns.
The delay postpones expected project revenue and returns and may weigh on the share price until commissioning progresses.