Announced Fri, 6 Jun · 15:40 IST

Disclosure attached

Greenfield CommissionedCapex & Operations View source PDF
Price reaction · full curve

Awaiting price reaction for this filing.

AI summary

NTPC announced that the first 250 MW unit of the 4x250 MW Tehri Pumped Storage Plant (PSP), operated by its subsidiary THDC India Limited, has been declared on Commercial Operation effective 00:00 Hrs on 07.06.2025. With this addition, NTPC Group's total installed and commercial capacity rises to 80,515 MW. The Tehri PSP is a pumped storage hydro project, and this marks the commissioning of its first of four units. The remaining three units are expected to follow.