GAILNSEGAIL (India) Limited· GasHighNegative
Announced Mon, 23 Jun, 2025 · 13:44 IST

GAIL (India) Limited has informed the Exchange regarding 'REVISION IN COMPLETION SCHEDULE AND ADDITIONAL COST FOR MUMBAI-NAGPUR-JHARSUGUDA PIPELINE (MNJPL) PROJECT'.

Capex DelayedCapex & Operations View source PDFExplain this filing

GAIL · price

Loading chart…

▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.

Price reactionminutes from the announcement price · days from the prior close
+1.6%Reaction day
₹181.69
prior close
₹183.98
announcement price
In-mkt
timing
Nifty 100market · index membership as recorded later (tracked since Jun 2026)-0.5%+2.1% vs market
Gas peers, median of 8sector · industry level+0.4%+1.2% vs sector

On the reaction day the stock moved 2.1 pts more than Nifty 100 and 1.2 pts more than its Gas peers, over the same two closes: a difference in percentage points, not a measure of what the filing did.

Minutes after the announcementfrom the announcement price · no benchmark
Stock
5m
+0.0
10m
+0.2
15m
+0.2
30m
+0.3
Sessions after the filingfrom the prior close
StockMarketvs marketSectorvs sector
Reaction day
+1.6-0.5+2.1+0.4+1.2
Next day
+1.9-0.1+2.0+1.6+0.3
2d
+1.2+0.7+0.5+1.8-0.6
3d
+2.9+1.8+1.1+3.2-0.2
4d
+5.1+2.2+2.9+4.5+0.6
5d
+5.0+1.9+3.0+5.8-0.8
1w
+4.8+1.6+3.2+7.0-2.2
15d
+1.0+0.3+0.7+3.8-2.8
1m
+2.6+0.8+1.8+4.1-1.4
2m
-3.3-0.2-3.1-4.5+1.2
3m
-1.8+0.9-2.7-1.9+0.1
UpDownMarket · Nifty 100Sector · Gas peers, median of 8Pending

Minute windows have no benchmark: there is no intraday index history to compare against.

AI summary

GAIL has pushed back the completion deadline for its 1,702 km Mumbai-Nagpur-Jharsuguda pipeline project by three months, from June 30, 2025 to September 30, 2025. The project cost has also risen by Rs. 411.12 crore, taking the revised total to Rs. 8,255.37 crore — a 5.24% increase over the originally approved Rs. 7,844.25 crore. The delay is due to right-of-way issues, pending forest and wildlife clearances, MoRTH permission delays, and local resistance. Despite the delay, physical progress is nearly complete: Part-A (Mumbai-Nagpur) is mechanically done except for 1 km, Part-B (Nagpur-Jharsuguda) is ~98% complete, and Part-C (Nagpur-Jabalpur) is ~97% complete. The revision was approved by GAIL's Board on June 23, 2025.

Likely market impact

The 5.24% cost overrun and three-month delay are modest and unlikely to materially impact shareholders, especially since the pipeline is nearly fully laid. Minor short-term pressure on project margins is possible, but the asset is close to revenue generation.