Commercial production moved to April 2027 after further project delays
ITALIANE · price
▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.
On the reaction day the stock moved 1.1 pts less than Nifty Microcap 250, over the same two closes: a difference in percentage points, not a measure of what the filing did.
Minute windows have no benchmark: there is no intraday index history to compare against.
Land was bought in March 2024 and construction began on March 15, 2025. Building work is now expected to finish in February 2027, with machinery purchase and installation due by March 2027. Commercial production is expected in April 2027. Delays reflect steel price swings, supply disruptions, late steel-structure deliveries, labour shortages, weather, regulatory clearances and mining suspension.
Project revenue will start later, while continued cost and execution uncertainty may weigh on the stock.