JNPRBSEJUNIPER GREEN ENERGY LTDHighPositive
Announced Fri, 11 Sept · 20:24 IST

Juniper Green commissions additional 40 MW wind capacity

Greenfield CommissionedCapex & Operations View source PDFExplain this filing

JNPR · price

Loading chart…

▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.

Price reaction · full curve

Awaiting price reaction for this filing.

AI summary

Wholly owned subsidiary Juniper Green Spark Four has commissioned the full 40 MW wind component of its 120 MW Wind Solar Hybrid Power Project in Gujarat. Capacity at this project now stands at 82.01 MWp out of 152 MWp planned. Total operational capacity of Juniper Green Energy and its subsidiaries is now about 2,679 MWp and 500 MWh BESS. Certification by Gujarat Energy Development Agency is awaited.

Likely market impact

Boosts operational capacity to 2,679 MWp; supports revenue growth as remaining capacity at this project nears completion.