K.P. Energy commissions 50.4 MW wind power project for NTPC in Gujarat
KPEL · price
▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.
K.P. Energy has commissioned the first 50.4 MW capacity of a wind power project at Vanki site in Kutch, Gujarat, achieving Commercial Operation Date effective July 8, 2026. The project includes 16 Suzlon wind turbines of 3.15 MW each and was developed as an EPC contract for NTPC Renewable Energy. The company positions this as a key milestone reinforcing its standing as a leading wind energy EPC and operations and maintenance provider supporting India renewable energy growth.
Positive - COD achieved on EPC contract for NTPC Renewable Energy, boosting KPEL execution track record and likely supporting order book momentum.