CEIG approval received for 100 MW solar project for MAHAGENCO in Maharashtra
KPIGREEN · price
▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.
On the reaction day the stock moved 0.5 pts more than Nifty Microcap 250 and 1.4 pts more than its Power Generation peers, over the same two closes: a difference in percentage points, not a measure of what the filing did.
Minute windows have no benchmark: there is no intraday index history to compare against.
KPI Green Energy has received charging permission from the Chief Electrical Inspector, Nagpur for its 100 MW (AC) or 128 MW (DC) grid-connected ground-mounted solar PV project, executed on a turnkey EPC basis for Maharashtra State Power Generation Company (MAHAGENCO) at Ramthi, Narkhed, Nagpur. This CEIG clearance is the final regulatory step that allows the project to be commissioned. The company says it establishes its presence in Maharashtra and adds a marquee state-utility project to its operating portfolio.
Project now cleared for commissioning, adding 100 MW to operating capacity and unlocking potential revenue from a state government utility counterparty.