NHPCNSENHPC Limited· PowerHighPositive
Announced Tue, 5 May · 12:33 IST

NHPC Limited has informed the Exchange about Update on commissioning of Subansiri Lower HE Project (2000 MW) of NHPC Limited

Greenfield CommissionedCapex DelayedCapex & Operations View source PDF

NHPC · price

Loading chart…

▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.

Price reaction · full curve 14 horizons · vs prior close
+0.3%1-day move
₹83.34
prior close
₹82.47
base price
In-mkt
timing
5m10m15m30m1D2D3D4D5D7D15D1M2M3M
+0.3+0.5+0.6+0.9+0.3-2.0-3.2-5.0-7.8-5.8-6.0-10.1-4.1
Up moveDown movePending
AI summary

NHPC Limited has declared the Commercial Operation Date (CoD) of Unit# 4 (250 MW) of the Subansiri Lower Hydroelectric Project, effective 08.05.2026. With this, four out of eight generating units (1,000 MW total) are now operational. The project, located in Assam/Arunachal Pradesh, has an installed capacity of 2,000 MW (8x250 MW). The company indicated that CoD for the remaining units will be communicated in due course. This follows multiple prior updates going back to October 2023, suggesting a staged commissioning process for this large greenfield hydro project.

Likely market impact

Partial commissioning of a major greenfield hydro project is a positive operational milestone for NHPC, adding 250 MW of generation capacity. Once fully operational, the project will significantly boost NHPC's power generation and revenue base.