NHPC Limited has informed the Exchange regarding 'Update on commissioning of 300 MW Grid Connected Solar PV Project in Bikaner, Rajasthan'.
NHPC · price
▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.
On the reaction day the stock moved 1.6 pts more than Nifty Midcap 150 and 2.0 pts more than its Power Generation peers, over the same two closes: a difference in percentage points, not a measure of what the filing did.
Minute windows have no benchmark: there is no intraday index history to compare against.
NHPC has provided an update on its 300 MW Karnisar Solar Power Project in Bikaner, Rajasthan. Out of the total 300 MW capacity, 214.28 MW has already been commissioned and is operational. The remaining balance capacity (~85.72 MW) was originally expected to be commissioned by August 31, 2025, but the timeline has now been pushed back by about a month, with the new target being September 30, 2025. This is a follow-up to NHPC's earlier communication dated June 30, 2025, filed under SEBI disclosure rules.
Minor delay of around one month in fully commissioning the solar project, but since nearly 71% of capacity is already generating revenue, the impact on earnings is limited. The short delay slightly defers income from the balance capacity but does not materially affect the project's long-term economics.