NTPC commissions final 41.6 MW of Ramagundam Solar PV project, total 176 MW
NTPC · price
▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.
On the reaction day the stock moved 1.2 pts more than Nifty 100 and 0.9 pts more than its Power Generation peers, over the same two closes: a difference in percentage points, not a measure of what the filing did.
Minute windows have no benchmark: there is no intraday index history to compare against.
NTPC has declared commercial operation of the third and last part capacity of 41.6 MW at its 176 MW Solar PV Project at Ramagundam, Telangana, effective 30th June 2026. Earlier parts of 100 MW and 34.4 MW were commissioned on 2nd May and 29th May 2026. With this, NTPC groups total installed capacity rises to 90,899 MW and commercial capacity to 89,819 MW.
Boost to NTPCs renewable capacity base; supports revenue and earnings growth from the solar segment going forward.