Clarion Wind Farm, a step-down subsidiary, has revised the timeline for completing the repowering of 7.8 MW wind energy generators to November 30, 2026 from the earlier date of September 30, 2026. The delay is subject to approval from statutory authorities. The Investment, Borrowing and Banking Committee of Clarion approved the revised timeline in a meeting held on September 30, 2026.
Two-month delay in repowering project completion, subject to regulatory approvals, may push back expected revenue benefits.