Investment approval for about Rs 857 Cr transmission line reconductoring
POWERGRID · price
▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.
On the reaction day the stock moved 4.0 pts less than Nifty 100 and 3.7 pts less than its Power peers, over the same two closes: a difference in percentage points, not a measure of what the filing did.
Minute windows have no benchmark: there is no intraday index history to compare against.
Power Grid's Committee of Directors on Investment on Projects has approved an estimated Rs 856.94 Crore investment for reconductoring the Tirunelveli-Udumalpet and Pugalur-Madurai 400kV double circuit lines with HTLS conductors. The work is booked as additional capital expenditure and is scheduled for commissioning within 24 months from allocation, by February 11, 2028.
Positive for order pipeline; strengthens southern India transmission capacity and supports revenue growth over the medium term.