Power Grid wins TBCB bid for Krishnagiri REZ Phase-I transmission project
POWERGRID · price
▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.
On the reaction day the stock moved 0.7 pts more than Nifty 100 and 1.2 pts more than its Power peers, over the same two closes: a difference in percentage points, not a measure of what the filing did.
Minute windows have no benchmark: there is no intraday index history to compare against.
Power Grid has been declared successful bidder under Tariff Based Competitive Bidding for the Transmission System for integration of Krishnagiri REZ Phase-I on BOOT basis. Letter of Intent received on 10 July 2026. The project involves 2 new 765/400kV substations in Andhra Pradesh and 765kV and 400kV transmission lines crossing Andhra Pradesh, Telangana, and Karnataka, aimed at renewable energy evacuation.
Positive order win strengthens Power Grid's order book and reinforces its dominant position in India's interstate transmission business.