POWERGRID commissions Khavda Phase IV Part E4 transmission project

Greenfield CommissionedCapex & Operations View source PDF

POWERGRID · price

Loading chart…

▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.

Price reaction · full curve 14 horizons · vs prior close
-1.5%1-day move
₹285.30
prior close
₹285.90
base price
After-mkt
timing
5m10m15m30m1D2D3D4D5D7D15D1M2M3M
-0.4-0.3-0.4-0.6-1.5-0.8+1.4+0.4+1.2+1.2
Up moveDown movePending
AI summary

Power Grid Corporation has commissioned its transmission project for evacuation of power from the renewable energy zone in Khavda, Gujarat under Phase IV (7 GW) Part E4. The project was commissioned effective 21st June 2026, with the date of commercial operation recorded as 13th July 2026. This transmission system supports evacuation of power from renewable energy projects in the Khavda area.

Likely market impact

Positive for shareholders as the new transmission asset begins earning tariff revenue, supporting incremental earnings growth.