Power Grid won a TBCB bid to set up a 765kV GIS Pune West substation in Maharashtra on BOOT basis, with quoted annual transmission charges of Rs 199.55 crore. The LoI was received on 16 Oct 2026. This is POWERGRID's 10th TBCB transmission project secured in FY27, with cumulative annual transmission charges of Rs 7,863.63 crore till date.
Adds to POWERGRID's recurring revenue pipeline under the BOOT model, highlighting strong order momentum with 10 TBCB wins in FY27.