REGAALBSEREGAAL RESOURCES LIMITEDHighNegative
Announced Thu, 1 Oct, 2026 · 15:47 IST

Turbine repair timeline extended by 5 days at Regaal Resources plant

Plant Fire AccidentGreenfield CommissionedCapex & Operations View source PDFExplain this filing

REGAAL · price

Loading chart…

▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.

Price reactionminutes from the announcement price · days from the prior close
-0.2%Reaction day
₹85.20
prior close
₹85.75
announcement price
After-mkt
timing
Nifty Microcap 250market · in no size index; the smallest one is used+0.0%-0.2% vs market

On the reaction day the stock moved 0.2 pts less than Nifty Microcap 250, over the same two closes: a difference in percentage points, not a measure of what the filing did.

Minutes after the announcementfrom the announcement price · no benchmark
Stock
5m
+1.0
10m
+0.9
15m
+0.8
30m
+1.2
Sessions after the filingfrom the prior close
StockMarketvs market
Reaction day
-0.2+0.0-0.2
Next day
+0.9+1.3-0.4
2d
+0.5+1.1-0.5
3d
-2.0-1.7-0.3
4d
-0.2-1.4+1.2
5d
+1.5-0.6+2.1
1w
+3.6+0.3+3.4
15d
+3.4-6.1+9.5
1m
———
2m
———
3m
———
UpDownMarket · Nifty Microcap 250Pending

Minute windows have no benchmark: there is no intraday index history to compare against.

AI summary

REGAAL Resources has extended the repair and recommissioning timeline of a damaged 10 MW turbine at its newly commissioned 825 TPD plant in Kishanganj, Bihar by about 5 days. The turbine had rotor and fan damage, first disclosed on September 10, 2026. Other manufacturing operations remain unaffected and continue normally.

Likely market impact