SJVN's wholly owned subsidiary, SJVN Green Energy Limited (SGEL), has commenced commercial operation of an additional 128.88 MW capacity at the 1,000 MW Bikaner Solar Power Project as of September 30, 2025. With this addition, the project's total cumulative commissioned capacity has reached 629.90 MW out of the planned 1,000 MW. The remaining capacity is expected to be commissioned soon. This is part of SJVN's renewable energy expansion through its green energy arm.

Likely market impact

Positive for shareholders as steady progress toward full commissioning of the 1,000 MW solar project will gradually boost SJVN's renewable energy generation revenue. Investors should watch for the final commissioning of the remaining ~370 MW capacity and the project's contribution to earnings.