Torrent Power: 300 MW wind PPA with SECI terminated, Rs 39.78 cr damages payable
TORNTPOWER · price
▲ positive · ▼ negative · ● neutral filings · teal = economic event · numbered = multiple that day (click to pick). Times IST.
On the reaction day the stock moved 0.2 pts more than Nifty Midcap 150 and 0.5 pts more than its Power peers, over the same two closes: a difference in percentage points, not a measure of what the filing did.
Minute windows have no benchmark: there is no intraday index history to compare against.
Torrent Power's wholly owned subsidiary Torrent Saurya Urja 2 Private Limited has terminated its 300 MW wind power PPA with SECI, signed on May 4, 2023 after a July 2022 Letter of Award. The project was hit by force majeure events and delays in transmission connectivity and GNA operationalisation, pushing the scheduled commercial operation date beyond a reasonable timeframe. Liquidated damages of Rs 39.78 crore are payable under the contract.
Removes 300 MW of planned wind capacity from the pipeline. The Rs 39.78 cr damages payout is small, but it highlights execution risks in the green energy business.