DEE Development Eng Q4 FY26 earnings call

Fri 22 May 2026DEEDEV

In brief

DEE Development Engineers posts FY26 PAT up 76.9% YoY at ₹77.2 Cr; guides FY27 revenue ₹1,500 Cr with >19% consol EBITDA margin.

Management's tone
Confident
What was said
Leaned positive
Guidance
First guidance issued
Analyst pushback
Medium
Stock, next session
+4.99% (Nifty 50 +0.27%)
  • FY26 PAT up 76.9% YoY at ₹77.2 Cr; FY26 revenue ₹1,142 Cr up 38% YoY on strong oil & gas and power execution.
  • Core business EBITDA (Inc. Other Income) up 64.2% YoY at ₹210.5 Cr for FY26, driven by operating leverage.
  • Order book of ₹2,040 Cr (CMD) / ₹1,940 Cr (CFO), giving multi-year revenue visibility weighted to piping and heavy fabrication.
  • Management commits to FY27 revenue of ₹1,500 Cr and consol EBITDA margin above 19%.
  • FY27 CAPEX guided at ₹20-30 Cr; ₹2,500 Cr revenue target set for FY30 from current facilities.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q4 FY26

This quarterA year agoLast quarterMargin
Revenue₹362 cr+26.3%+26.1%
EBITDA (excl. other income)₹65.9 cr+3.8%+51.8%18.2% (22.2% a year ago)
Net profit₹28 cr−11.1%+53.2%7.7% (11% a year ago)
EPS (₹)₹4.00−12.3%+49.3%

From the company's filed results for the quarter ended 31 Mar 2026 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

Where management's figures differ from the filing

  • Q4 FY26 net profit (PAT vs Net profit to owners): said PAT for Q4 FY26 stood at Rs. 27.7 Cr; filed Net profit to owners ₹28.01 cr. Gap of ~₹0.31 Cr likely reflects minority interest treatment; consolidated PAT vs profit attributable to owners of parent.

What moved the numbers, as management explained it

  • Higher execution momentum in piping segment, with strong supply to oil & gas and power sectors driving FY26 revenue up 38% YoY to ₹1,142 Cr.
  • Operating leverage in core business lifted FY26 EBITDA margin to 16.7% from 15.0% in FY25, with core EBITDA (Inc. Other Income) up 64.2% YoY.
  • Q4 FY25 was an unusually high base as it absorbed revenue and profit spillover from Q3 FY25, making Q4 FY26 PAT growth optically muted on a YoY basis. (one-off)
  • Malwa Power tariff revision to ₹5.22/kWh from ₹3.5/kWh with retrospective recovery of ~₹5.52 Cr in Q4 boosted non-core performance. (one-off)
  • Small portion of trading activities in Q4 FY26 with high material value (~95-100%) contributed to gross margin dip year-on-year.

The numbers management led with

  • Core Business EBITDA (FY26): Rs. 210.5 Cr, up 64.2% YoY
  • Revenue from Operations (FY26): Rs. 1,142 Cr, up 38% YoY
  • Operating EBITDA (FY26): Rs. 189.3 Cr, up 52.9% YoY; EBITDA margin 16.7% vs 15.0% in FY25
  • PAT (FY26): Rs. 77.2 Cr, up 76.9% YoY
  • Order Book: Rs. 2,040 Cr (stated by CMD); Rs. 1,940 Cr (stated by CFO) — slight discrepancy in transcript

Guidance

Guidance on this call

WhatForWhat management said
FY27 revenue targetFY27FY27 revenue ₹1,500 Cr committed (conservative).
Consol EBITDA margin FY27FY27Consol EBITDA margin above 19% in FY27.
FY27 order inflowFY27Order inflow of more than ₹2,000 Cr expected in FY27.
FY27 CAPEXFY27FY27 CAPEX of ₹20-30 Cr.
FY30 revenue targetFY30Revenue target ₹2,500 Cr by FY30 from existing facilities.
FY27 working capital cycleFY27Working capital cycle target of 180 days in FY27 (CMD); CFO mentioned ~200 days.
FY27 payable days targetFY27Payable days target 70-75 in FY27, from current 42 days.
FY27 inventory days reductionFY27Inventory days to reduce by further 15-20 days in FY27.
FY27 power + biomass pellet revenue (Non-core (Malwa Power + Biomass pellets))FY27Combined revenue from power and biomass pellet expected at ~₹47.71 Cr in FY27.

Guided on earlier calls, and what was filed

WhatForGuidedFiled
Q4 FY25 revenueQ4 FY25₹260–270 cr (on the Q3 FY25 call)₹286 cr, above the range
Full-year average EBITDA marginFY2515–16% (on the Q3 FY25 call)15%, within the range
EBITDA margin from this quarter onwardsQ4 FY2519–20% (on the Q3 FY25 call)22.2%, above the range
Top lineFY26₹1,100 cr (on the Q3 FY25 call)₹1,142 cr, above the figure guided
EBITDA marginFY2619–20% (on the Q3 FY25 call)16.6%, below the range
Execution from current order bookFY26₹1,150 cr (on the Q3 FY25 call)₹1,142 cr, below the figure guided
FY26 revenueFY26at least ₹1,300 cr (on the Q4 FY25 call)₹1,142 cr, below the range
FY26 EBITDA marginFY2619–20% (on the Q4 FY25 call)16.6%, below the range
FY26 revenueFY26at least ₹1,300 cr (on the Q1 FY26 call)₹1,142 cr, below the range
FY26 EBITDA margin (base case)FY2619–20% (on the Q1 FY26 call)16.6%, below the range
FY26 EBITDA margin (PSERC downside)FY2616–18% (on the Q1 FY26 call)16.6%, within the range
Revenue growth over FY25 baseFY2640–45% (on the Q2 FY26 call)38%, below the range
Operating EBITDA marginFY2616–18% (on the Q2 FY26 call)16.6%, within the range
EBITDA margin if biomass tariff revisedFY2618–20% (on the Q2 FY26 call)16.6%, below the range

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

The business

By business

Core business (piping, heavy fabrication, others)

Core business drove FY26 with EBITDA up 64.2% YoY at ₹210.5 Cr; Anjar and seamless plant commissioned; Thailand ~₹150 Cr annual revenue, 60% capacity reserved for Nooter Eriksen HRSG orders.

Core EBITDA FY26 ₹210.5 Cr (+64.2% YoY) · FY26 revenue ₹1,142 Cr (+38% YoY) · FY26 EBITDA ₹189.3 Cr (+52.9% YoY) · FY26 EBITDA margin 16.7% vs 15.0% in FY25 · Order book ₹2,040 Cr (CMD) / ₹1,940 Cr (CFO)

Outlook: FY27 ₹1,500 Cr revenue committed; consol EBITDA margin >19%; Anjar to reach optimal utilization, seamless plant 60-70% in FY27

Non-core (Malwa Power + Biomass pellets)

Pivoting from pure power to biomass pellets; Malwa Power tariff revised to ₹5.22/kWh with ₹5.52 Cr retrospective recovery in Q4 FY26; biomass pellet plant commissioned.

Malwa tariff revised to ₹5.22/kWh from ₹3.5/kWh · Retrospective tariff recovery ₹5.52 Cr · FY27 combined power+biomass pellet revenue ~₹47.71 Cr

Outlook: Biomass pellet facility expected to offset cash burn and stabilize segment profitability; Appellate pursued for further tariff optimization

Balance sheet, capex and funding

  • Order book ₹2,040 Cr (CMD) / ₹1,940 Cr (CFO) provides multi-year revenue visibility weighted to piping and heavy fabrication.
  • CAPEX cycle now majorly complete with Anjar and seamless plant commissioned; gradual reduction in debt levels expected.
  • FY27 CAPEX guided at ₹20-30 Cr; additional capacity for nuclear under evaluation.
  • Working capital cycle target 180 days in FY27 (CMD), with CFO earlier stating ~200 days; debtor days 95-100; payable days target 70-75 from 42.
  • Inventory days to reduce by further 15-20 days in FY27 driven by faster power-sector execution.
  • Equity raise remains on drawing board; no immediate decision on funding or further capacity expansion.

The industry, as management sees it

India's broader CAPEX cycle is gaining traction as corporates in infrastructure, energy, and industrial sectors scale up plant and equipment investments. Overseas markets show clear pick in energy, process industries, and infrastructure. Domestic thermal project execution is accelerating (L&T faster than BHEL), with piping erection expected to peak in FY27-28. US data center-driven gas turbine demand is creating a multi-year HRSG order backlog with GE, Siemens, and Mitsubishi. Middle East reconstruction opportunity exists but remains fluid.

Risks management named

  • BHEL order releases slower than expected; L&T thermal execution pace partially offsets
  • Appellate ruling on Malwa Power tariff revision — outcome uncertain
  • Potential equity raise under consideration; timing and quantum undecided
  • Commodity inflation and product mix shifts causing gross margin variability

Q&A

Q&A was active with 15 analysts covering 19 exchanges, dominated by questions on the HRSG piping opportunity tied to US data center gas turbine demand, capacity utilization at the Anjar and seamless pipe facilities, working capital management, and the Malwa Power impairment. Strongest pushback came on gross margin variability (attributed to trading activity in Q4) and the working capital days increase (defended as a deliberate trade-off for better purchase discounts). Analysts probed the Rs. 2,000 Cr order inflow target, the BHEL ordering delay risk, and the timing of a potential equity raise — all of which received cautious but forward-looking responses. Management was confident and direct throughout, with minimal deflection except on Middle East opportunity (too fluid to comment) and exact alloy mix data (not immediately available).

Not answered directly

  • Middle East reconstruction opportunity — too fluid, no concrete enquiries yet
  • Exact alloy mix and job work vs material mix breakdown — data not immediately available

Asked for a number, answered without one

  • Segment EBITDA margins for piping vs heavy fabrication: Declined to break out segment margins; consol EBITDA >19% committed; heavy fabrication will be similar; with-material jobs may dilute % margin but expand in value.
  • Alloy mix and job-work vs with-material in order book: Pankaj Agarwal said not handy; CMD gave approximate numbers - job work ~30% of orders, alloy steel 55-60% in power/oil & gas mix.
  • Current capacity utilization at Anjar and seamless plant: Not quantified; only forward-looking targets: Anjar to reach optimal in FY27, seamless 60-70% in FY27.
  • Equity raise decision: Management declined, indicating strategy is on the drawing board; will revert when plans are clear.

Every question, with its answer

  1. 1. HRSG Order Opportunity & Thailand Capacity

    Pranay Chatterjee, Burman Capital Management

    Question. Are the HRSG orders (including the Thailand order) related to the multi-year gas turbine backlog driven by US data center electricity demand? And is the Rs. 150 Cr Thailand revenue figure the job-work value (gross profit) only, with actual total revenue being higher? Does DEE have sufficient capacity or need CAPEX to execute?

    Answer, Krishan Lalit Bansal, CMD. Yes, most orders are related to HRSG market from overseas. The Rs. 150 Cr is the job-work value (free-flow material supplied by customer); in some cases DEE also supplies material adding further value to turnover. Thailand operates purely on job-work basis — no significant incremental revenue uplift beyond Rs. 150 Cr. No CAPEX required for this order; only nominal/insignificant CAPEX if needed. The 60% capacity reservation is on the 14,500-ton Thailand facility.

    Follow-up. So Rs. 150 Cr is the job work value — revenue number should be much higher, right? And EBITDA margin on this revenue will be much higher than 20%?

    Answer. Thailand operates purely on job-work basis so there will not be very high incremental increase. EBITDA margin on the Rs. 150 Cr will be much higher than 20% — confirmed.

  2. 2. Gross Margin Decline

    Vaibhav Shah, Equirus Securities

    Question. Gross margin has declined on Q4 and full-year basis — how much is attributable to commodity inflation vs product mix change? Also, within product mix, what is the alloy mix and product supply vs job work contribution that has changed from FY24 to FY26?

    Answer, Krishan Lalit Bansal, CMD. Project-based company — difficult to explain quarter-on-quarter margin changes. One reason for Q4 dip: some small portion of trading activities happened in Q4 where material value is ~100% or 95%, which compresses margins. Request to compare on year-on-year basis only.

    Follow-up. Can you share the current alloy mix and product supply vs job work mix within the outstanding order book?

    Answer. Pankaj Agarwal responded that exact data is not immediately available but will be shared later. Krishan Bansal then estimated: job work orders will be ~30% and material orders ~70%; alloy mix: ~55-60% alloy steel (for power and HRSG thermal jobs) and remaining carbon/non-alloy steel; power sector share ~70% and oil & gas ~30% of revenue.

    Partly answered.

  3. 3. Capacity Utilization & Margin Guidance

    Vaibhav Shah, Equirus Securities

    Question. What is the current capacity utilization at the new Anjar plant and seamless pipeline? When can we expect optimum utilization? And what are the sustainable EBITDA margins for heavy fabrication vs piping?

    Answer, Krishan Lalit Bansal, CMD. In FY27, Anjar fabrication facility should reach optimal/full level. Seamless plant may ramp up to 60-70% utilization in FY27. Consolidated EBITDA will be above 19% — heavy fabrication margins will be similar to consolidated level as more jobs with material are done (percentage may drop but value increases).

  4. 4. FY27 Order Inflow Guidance

    Riken Gopani, Capri Global

    Question. What order inflow do you expect in FY27? Which segments will be major contributors? And what is the domestic vs export order mix?

    Answer, Pankaj Agarwal, COO. Expecting >Rs. 2,000 Cr orders in FY27. Major contributor will be power sector (~60%) and rest from oil & gas. Domestic vs export mix: ~60-65% domestic, ~35-40% export orders.

    Follow-up. What would be the bulk of it — domestic vs export?

    Answer. 60-65% domestic, 35-40% export orders confirmed.

  5. 5. Fertilizer Sector Opportunity

    Riken Gopani, Capri Global

    Question. Are you seeing any developments on the fertilizer sector given the government is setting up new plants? Any orders expected?

    Answer, Pankaj Agarwal / Krishan Bansal, COO / CMD. Pankaj: Expecting one job from the Namrup fertilizer plant but not sure if it will mature in FY27. Krishan Bansal added: actively discussing an export order for a fertilizer unit with a customer — fertilizer could become a considerable part of the business in the coming future.

  6. 6. Working Capital Guidance

    Riken Gopani, Capri Global

    Question. How do you see working capital shaping up in FY27?

    Answer, Brham Yadav / Krishan Bansal, CFO / CMD. Brham Yadav: Working capital cycle on improving trend. Targeting inventory days reduction of 15-20 days in FY27; debtor days fixed at 95-100; payable days improving from 42 days to 70-75 through supplier negotiations; total working capital cycle ~200 days in FY27. Krishan Bansal clarified: inventory days will reduce mainly because ~70% of jobs are in power sector where cash conversion and inventory holding time is much lower than oil & gas.

  7. 7. GE Vernova HRSG Order Status

    Vinit, Toro Wealth Management

    Question. What is the current execution status of the GE Vernova HRSG order received last year? Are you expecting similar orders from GE again given the surge in US gas turbine orders?

    Answer, Pankaj Agarwal / Krishan Bansal, COO / CMD. Pankaj: Good order book from GE — not expecting much new order book in FY27 as focus is on executing existing orders. GT piping orders will come from GE. Krishan Bansal: Apart from GE, Nooter Eriksen has reserved 60% of Thailand capacity for HRSG piping. Also in discussions with Siemens — expecting similar agreements; confident of receiving many more orders for HRSG segment.

  8. 8. Middle East Reconstruction Opportunity

    Vinit, Toro Wealth Management

    Question. Are you seeing any enquiries from the Middle East given the reconstruction and rebuilding work happening after recent disruptions?

    Answer, Krishan Lalit Bansal, CMD. Not at present — situation still not normal, everyone is assessing the loss. It is a big opportunity which will come DEE's way, possibly requiring some CAPEX or something out of the way to grab it. Very fluid; cannot comment on specifics right now.

    Not answered directly.

  9. 9. FY27 Revenue Target & Capacity

    Dhwanil Desai, Total Capital Partners

    Question. You have given a roadmap to FY30 but order book has increased 50% while you project 20-25% growth. Is this because delivery timelines will extend? Or will you exceed the Rs. 1,500 Cr revenue target?

    Answer, Krishan Lalit Bansal, CMD. Rs. 1,500 Cr is a very conservative estimate. May have to do more work and possibly expand some capacity. The math is absolutely right — may not be able to restrict to just Rs. 1,500 Cr in FY27. This is the commitment for the coming year but likely to increase.

    Follow-up. Why did inventory remain flat this year despite order book increasing significantly?

    Answer. Mainly because of power sector — power sector raw material deliveries are comparatively larger and started flowing late after placing orders. Since execution is equally fast, it helped keep inventory flat. Previous year's reduction was also due to placing orders immediately after receipt, with longer delivery cycles keeping material off the books.

  10. 10. Power Sector Revenue Mix & Capacity

    Ankit Soni, Mirae Asset

    Question. What is the current power sector order contribution in the order book? And what will be power sector revenue contribution in FY27? Also, what is the CAPEX guidance for FY27 and what revenue can be done from existing facilities?

    Answer, Krishan Lalit Bansal, CMD. Expecting 65-70% of FY27 revenue from power sector. Current power sector order book is >Rs. 1,000 Cr (around Rs. 1,200 Cr exact). Mix: thermal from India and HRSG orders from abroad. With existing CAPEX spent, revenue potential is ~Rs. 2,500 Cr — FY30 is the target but may happen earlier given increased order flow. May need some expansion for nuclear sector — still on drawing board.

  11. 11. Nooter Eriksen Capacity Reservation & Competitive Landscape

    Chandresh Malpani, Nivesha Investment Advisory

    Question. Was the Nooter Eriksen 60% capacity reservation a negotiation outcome, or did DEE choose to keep 40% for other OEMs? And what percentage of total HRSG piping market from top 3 OEMs is DEE targeting?

    Answer, Krishan Lalit Bansal, CMD. True — DEE preferred to keep some capacity for other customers rather than tying up with one customer. Nooter Eriksen is one of the most valued customers so 60% was given. Many customers are now talking about capacity reservations — this is the first such agreement. Discussions and exploration ongoing with other OEMs. India has practically no competition except one or two players with significantly lesser capacity; main competition is Korean and Turkish players.

    Follow-up. Are you also looking at data center rigid piping opportunities?

    Answer. Working on data center rigid piping — have a few active inquiries but not yet matured into orders. Anything related to metallic piping is being pursued.

  12. 12. Alloy Steel (P-91/P-92) Supply Chain

    Ankit Gupta, Bamboo Capital Partners

    Question. How is the availability of alloy steel, particularly P-91 and P-92? Are you importing from China? What is the raw material booking situation?

    Answer, Krishan Lalit Bansal, CMD. Previously imported everything from China or Europe. After commissioning own seamless pipe plant, supply chain majorly established from India. Will not be majorly dependent on imports. Already received some approvals and more coming shortly — once those come through, ~100% availability for domestic power sector jobs. Also successfully qualified with some foreign players who may source P-91 pipes from DEE's manufacturing unit.

    Follow-up. What margins do you expect from the seamless pipe plant at higher utilization (70-80%) in FY28?

    Answer. For in-house backward integration use, the EBITDA margin benefit is the purchase margin avoided. For independent sales, since it's a commodity, margin may not be very high but still around 20%.

  13. 13. EBITDA Margin Guidance & Order Execution Timeline

    Nishita, Sapphire Capital Partners

    Question. You mentioned EBITDA above 19% — is that on a specific segment or consolidated basis? And from the Rs. 1,940 Cr order book, what is the execution timeline and how much revenue can be booked in FY27?

    Answer, Krishan Lalit Bansal, CMD. Consolidated basis — above 19% EBITDA margin. Orders run between 6-18 months, average ~12 months for execution. FY27 revenue target of Rs. 1,500 Cr is very conservative; may exceed that target but Rs. 1,500 Cr is the committed number.

    Follow-up. What is the CAPEX guidance for FY27?

    Answer. Substantial CAPEX is done. CAPEX for FY27 may be Rs. 20-30 Cr — only balance from previous year. May need to rethink for nuclear sector and other new sectors; working on that and will announce soon.

  14. 14. Domestic Thermal Ordering Outlook

    Tanay Chatterjee, Burman Capital Management

    Question. Based on live thermal project timelines, piping erection should peak in FY27-28. Should we expect a massive step-up in domestic thermal ordering over the next 4-6 quarters? Or do you foresee delays given BHEL is slower?

    Answer, Krishan Lalit Bansal, CMD. Analysis is absolutely right. BHEL is going slower than expected — may have done different calculations. L&T is moving quite fast. DEE already has a few orders with L&T and discussing more. The Rs. 2,000 Cr order inflow target is contingent on BHEL orders materializing.

  15. 15. Malwa Power Impairment & Audit Qualification

    Pratik Srivastava, Nivesh Wisdom

    Question. This is the second year of qualified audit opinion due to Malwa Power impairment. What are you doing to address this? If the Appellate rules against the revised tariff, do you have contingency plans? When can we see a clean audit opinion?

    Answer, Krishan Lalit Bansal / Brham Yadav, CMD / CFO. Biomass pallet plant has been commissioned to mitigate impairment entirely. Tariff revision already provides some positive impact. Based on current tariff levels, both plants should be slightly positive — no question of impairment or financial contingency. Brham Yadav confirmed: clean audit opinion (not qualified) expected by Q3.

  16. 16. Tariff Recovery & Equity Raise

    Kamlesh, Lotus Asset Managers

    Question. Is the Rs. 5.52 Cr retrospective tariff recovery included in Q4? And are you considering an equity raise given the stock has performed well, to reduce debt?

    Answer, Krishan Lalit Bansal, CMD. Yes, Rs. 5.52 Cr retrospective recovery is included in Q4. On equity raise: strategy decisions are on the drawing board — nothing immediately decided. Will communicate when clear on plans.

    Follow-up. How are you balancing capacity between delayed BHEL orders and other HRSG orders from GE/Nooter Eriksen so you don't miss other orders?

    Answer. No active balancing needed — whenever BHEL gives an order, delivery starts from that date (12-18 months lead time). Capacity is not being kept idle for BHEL specifically; execution is managed based on order receipt dates.

  17. 17. Working Capital Days Guidance

    Kamlesh, Lotus Asset Managers

    Question. During the plant visit, working capital was guided at ~150 days. Now you are saying ~200 days. Why has this increased?

    Answer, Krishan Lalit Bansal, CMD. Projection is 180 days for FY27 (not 200 days), then ultimately 150 days. Inventory days have considerably come down vs last year. Payable cycles reduced because of a very good discount on purchases (reflected in material cost). Even if inventory days were 30 days higher, getting 1% more EBITDA is more beneficial. Going forward, plan is to use more sales bill discounting and milestone payments from export customers to reduce inventory days.

  18. 18. Heavy Fabrication Business Scaling

    Ankit Gupta, Bamboo Capital Partners

    Question. Heavy fabrication business has been scaling up well with a big Rs. 170 Cr order. How is the capacity ramp-up and model shift from job work to material supply?

    Answer, Krishan Lalit Bansal, CMD. Capacity is ramping up. Previously all jobs were on job work basis; over the last year the model is shifting to jobs with material supply. This is the main reason for increasing turnover from heavy fabrication — capacity is also being ramped up.

  19. 19. HRSG Capacity Expansion CAPEX

    Chandresh Malpani, Nivesha Investment Advisory

    Question. HR demand from GE and Siemens is very strong. Why is DEE holding back on more CAPEX for capacity expansion? It is a chicken-and-egg story — more capacity will attract more orders.

    Answer, Krishan Lalit Bansal, CMD. Not holding back at all — on the drawing board to decide how to go about it. Whatever capacity built must be sustainable for 10-15 years, so careful assessment is needed. Risk appetite and sustainability considerations are being evaluated. Very close to finalizing the blueprint and will come back with an announcement soon. Agrees there is a huge opportunity that must be encashed.

What was said

Topic by topic, in the order it was spoken

FY26 Annual Performance Overview · Krishan Lalit Bansal (CMD)

  • FY26 core business EBITDA (Inc. Other Income) at Rs. 210.5 Cr, up 64.2% YoY, driven by better execution, improved utilization, and operating leverage.
  • Non-core power segment losses reflected at consolidated level only; core business performance is strong.
  • Policy and investment backdrop supported by sustained Union Budget CAPEX allocation across infrastructure, transport, energy, and industrial corridors.

Non-Core Segment Strategy · Krishan Lalit Bansal (CMD)

  • Strategic pivot to biomass pallet manufacturing to enhance capital efficiency and minimize incremental capital commitment in power segment.
  • Malwa Power tariff revised to Rs. 5.22/KwH from Rs. 3.5/KwH with retrospective recovery of ~Rs. 5.52 Cr.
  • Combined revenue from power and biomass pallet expected at ~Rs. 47.71 Cr in FY27; Appellate appeal for further tariff optimization ongoing.
  • Biomass pallet facility commissioned to offset cash burn, stabilize segment profitability, and support margin improvement.

Seamless Pipe Plant & Backward Integration · Krishan Lalit Bansal (CMD)

  • Seamless pipe plant commissioned in FY26; strengthens capabilities in high-spec applications, improves supply security, and reduces lead times.
  • Backward integration reduces dependence on imports for P-91/P-92 alloy steel; supply chain majorly established from India.
  • Once final approvals come through, ~100% availability for domestic power sector jobs; also qualified with some foreign players for pipe sourcing.

Order Book & Demand Outlook · Krishan Lalit Bansal (CMD)

  • Order book stands at Rs. 2,040 Cr providing strong multi-year revenue visibility across key segments.
  • Demand visibility across core end markets — power, oil & gas, process industries in India and overseas — remains healthy.
  • Strong order pipeline gives confidence in delivering profitable growth and long-term stakeholder value.

Q4 & FY26 Financial Results · Brham Yadav (CFO)

  • Q4 FY26 revenue from operations: Rs. 361.6 Cr (+26.3% YoY); FY26 full year: Rs. 1,142 Cr (+38% YoY).
  • Operating EBITDA Q4: Rs. 65.9 Cr; FY26 full year: Rs. 189.3 Cr (+52.9% YoY); FY26 EBITDA margin: 16.7% vs 15.0% in FY25.
  • FY26 PAT: Rs. 77.2 Cr (+76.9% YoY); Q4 PAT: Rs. 27.7 Cr in line with guidance on a high Q4 FY25 base.
  • Performance driven by higher execution momentum and improved capacity utilization across both facilities.

Revenue Visibility & Order Inflow Guidance · Brham Yadav (CFO) / Pankaj Agarwal (COO)

  • Order book of Rs. 1,940 Cr provides multi-year revenue visibility with execution weighted toward piping, fittings, and heavy fabrication.
  • FY27 order inflow target: >Rs. 2,000 Cr; major contributor: power sector (~60%), rest from oil & gas.
  • Domestic vs export mix for FY27: ~60-65% domestic, ~35-40% export.

In their words

Our competition is broadly with Korean people and some Turkish players only. In India, practically no competition except with one or two players who also have significantly much lesser capacity.
Krishan Lalit Bansal (CMD, DEE Development Engineers)
We are expecting more than Rs. 2,000 Cr orders in this financial year. Out of that, the major contributor will be the power sector only. We are expecting around 60% jobs from power and rest from oil and gas.
Krishan Lalit Bansal (CMD, DEE Development Engineers)
You have rightly said, your math is absolutely right that we may not be able to restrict to just Rs. 1,500 Cr in the coming year, which we have said. So, that's likely to increase.
Krishan Lalit Bansal (CMD, DEE Development Engineers)

To check next time

What management committed to on this call, or the dates they gave.

  • FY27 order inflow progress toward >₹2,000 Cr commitment (60% power, 35-40% export per guidance).
  • Anjar fabrication and seamless plant utilization ramp toward optimal / 60-70% levels.
  • Working capital cycle achievement of 180 days target (CMD) vs 200 days (CFO).
  • Decision on further CAPEX / capacity expansion to capture HRSG and nuclear opportunities.
  • Biomass pellet plant ramp-up at Malwa and outcome of Appellate on tariff revision.
  • Resolution of Malwa power impairment; auditor expected to give clean opinion by Q3 FY27.

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Fri 22 May 2026₹523.80+4.99%+0.27%
5 sessions Fri 29 May 2026₹593.40+18.94%−0.45%
20 sessions Fri 19 Jun 2026₹703.05+40.92%+1.52%

From the close of Thu 21 May 2026, ₹498.90: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

DEE Development Eng's other calls