Denta Water N Infra Sol Q1 FY26 earnings call

Mon 18 Aug 2025DENTA

In brief

Q1 FY26 revenue ₹67.28 cr (+35.9% YoY), EBITDA ₹25 cr at 37.15% margin; targets ₹1,000 cr FY26 order inflow and 30% FY27 growth.

Management's tone
Confident
What was said
Leaned positive
Guidance
Guidance held
Analyst pushback
Medium
Stock, next session
+1.76% (Nifty 50 +1.00%)
  • Q1 FY26 revenue ₹67.28 cr, up 35.92% YoY and 24.24% QoQ, driven by water project execution and Q4 FY25 deferred billings.
  • EBITDA ₹25 cr with 37.15% margin, beating prior ~36% guidance, helped by operating leverage and lower finance costs.
  • Order book ₹593.68 cr; ₹180 cr new orders won between June 30 and August 14, 2025.
  • FY26 order inflow target ~₹1,000 cr; FY27 revenue growth guidance of 30% over FY26's ₹300 cr.
  • Zero-debt model, working capital cycle 40-50 days; 80% of Q1 sales realised in cash.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q1 FY26

This quarterA year agoLast quarterMargin
Revenue₹67.3 cr—+24.2%
EBITDA (excl. other income)₹22.5 cr—+36.0%33.4%
Net profit₹18.6 cr—+35.2%27.6%
EPS (₹)₹6.95—+3.7%

From the company's filed results for the quarter ended 30 Jun 2025 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

Where management's figures differ from the filing

  • EBITDA / EBITDA margin: said EBITDA ₹25 cr, margin 37.15%; filed EBITDA ex other income ₹22.46 cr, margin 33.4%. Management's stated EBITDA appears to include other income (₹2.54 cr); filed figure is EBITDA excluding other income.

What moved the numbers, as management explained it

  • Accelerated execution in water management projects and completion of milestone-linked deliverables lifted Q1 revenue 35.92% YoY.
  • Portion of Q4 FY25 deferred billing (₹55-60 cr flagged in prior call) recognised this quarter; balance expected in coming quarters — a one-off timing tailwind. (one-off)
  • Operating leverage on higher execution volumes and a favourable project mix lifted EBITDA margin to 37.15% from 34.22% in Q4 FY25.
  • Lower finance costs and a zero-debt model supported PAT of ₹18.55 cr.

The numbers management led with

  • Order book outstanding: Rs 593.68 crore as of June 30, 2025
  • FY26 order inflow target: ~Rs 1,000 crore
  • FY27 revenue growth guidance: 30% increase over FY26

Guidance

Guidance on this call

WhatForWhat management saidFiled
FY26 revenue (modest level)FY26Revenue around Rs. 300 crore for FY26 as a modest level; expect to achieve much more₹250 cr, below the figure guided
FY26 order inflowFY26We are anticipating around Rs. 1,000 Cr of order inflow in FY26—
FY27 revenue growth over FY26FY2730% increase in revenue over FY26—
Q2 FY26 revenue growth over Q2 FY25Q2 FY2620% increase in Q2 FY26 revenue vs Q2 FY25—
EBITDA margin sustainedFY26Try to maintain the same type of margin (Q1 actual 37.15%)29.7%, below the figure guided
Order book execution splitFY26-FY2740% of outstanding order book in FY26 and 60% in FY27—
Working capital cycle—Working capital cycle 40-50 days—

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

What changed since the Tue 3 Jun 2025 call

WhatOn the Tue 3 Jun 2025 callOn this call
Order book execution split (held)Order book of Rs.614 cr to be executed 40% in FY26 and 60% in FY27outstanding order book stands at Rs. 593.68 crore...40% of the outstanding order book will be completed within this year. 60%...we will realize in next year, '26-'27
FY26 revenue target (held)Chairman guides Rs.300 cr revenue in FY26we have anticipated a revenue of around Rs. 300 crore...That is the modest level which I am anticipating
EBITDA margin (achieved)Management committed to sustaining ~36% marginEBITDA for the quarter was Rs. 25 crore, with margins improving to 37.15%
Bidding pipeline Q1-Q2 FY26 (held)Bidding pipeline of Rs.1,200-1,500 cr in Q1-Q2 FY26 with 70-75% historical win ratioRs. 750 crore to Rs. 800 crore...one more tender valued at Rs. 120 crore...balance Rs. 100 crore of tenders under draft tender processing stage
FY27 revenue growth (new)Not specified30% increase over '25-'26
FY26 order inflow target (new)Not stated as a single numberWe are anticipating around Rs. 1,000 Cr
Working capital / receivables (restated)Receivables rose to ~Rs.80 cr; expected to normalise from Q1 FY26working capital is Rs.180 crores...Our working capital cycle is 40 to 50 days

Guided on earlier calls, and what was filed

WhatForGuidedFiled
Q1 FY26 revenue (deferred billing)Q1 FY26₹55–60 cr (on the Q4 FY25 call)₹67 cr, above the range
FY26 revenue (conservative, incl. new orders)FY26₹300 cr (on the Q4 FY25 call)₹250 cr, below the figure guided
FY26 revenue (alt estimate)FY26₹260–275 cr (on the Q4 FY25 call)₹250 cr, below the range

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

The business

Balance sheet, capex and funding

  • Zero-debt balance sheet; debt used only for non-fund-based bank guarantees.
  • Working capital cycle 40-50 days; total working capital ~₹180-184 cr.
  • IPO proceeds: ₹88 cr utilised by March 2025, balance ~₹132 cr to be deployed in FY26 primarily for working capital.
  • 80% of Q1 sales realised in cash.
  • ~₹25 cr invested in 95-acre Madikeri coffee plantation and UVA Sands resort in Kundapura, held as collateral for BG limits.

The industry, as management sees it

Management views the water infrastructure sector demand environment as very encouraging, supported by the government's sustained focus on water reuse, recycling, and water infrastructure development under schemes like Jal Jeevan Mission, AMRUT, and Atal Jal. No slowdown observed in central funding flow; state-level fund matching is being delivered as promised.

Risks management named

  • Working capital intensity elevated post-IPO fund deployment; Rs 184 crore tied up in inventory and receivables
  • Execution of new projects depends on multi-month DPR and competent authority approvals
  • Competitive bidding in Karnataka could pressure bid pricing in 3-4 player contests

Q&A

Discussion was dominated by order book and pipeline visibility (Rs 1,000 crore FY26 inflow target, Sandur and Karnataka water supply projects), with several analysts probing sustainability of 30-35% EBITDA margins and working capital intensity post-IPO. The strongest pushback came from Sapphire Capital's Rahil S who flagged a clear inconsistency between the Q2 FY26 revenue guide (20% over Q2 FY25) and the Q1 FY26 run-rate — management acknowledged the figures were likely mixed up and deferred the corrected number. The O&M margin and JJM order book break-up were also deferred.

Not answered directly

  • Q2 FY26 revenue growth number (acknowledged as inconsistent, promised correction)
  • O&M segment margin profile (CEO said he would come back with the figure)
  • JJM share of current order book (CEO said break-up not available)
  • Specific O&M margin for the business

Asked for a number, answered without one

  • FY27 margin profile: We try to strive ourselves to maintain the same type of margin and definitely we will achieve good economy in our execution.
  • O&M margin profile: Exact margin I don't have and I will come back to you.
  • JJM share of order book: I don't have breakup of those figures.
  • Q2 FY26 absolute revenue: Probably Q1, Q2, some figures have got mixed up. I will come back to you with the exact expected revenue only.

Every question, with its answer

  1. 1. Order inflow pipeline

    Sanket Sadh, AARTH AIF

    Question. Update on the Rs 1,200-1,500 crore bidding target for H1 FY26.

    Answer, C. Mruthyunjaya Swamy, Chairman & Executive Director. On track with the prior guidance. Post June 30 till August 14, Rs 180 crore of orders won. Currently bidding for a water supply and sewerage project worth Rs 750-800 crore in Karnataka; lowest bidder in another Rs 120 crore tender in final approval stage. Total under pursuit ~Rs 1,100 crore; balance Rs 100 crore in draft tender processing.

    Follow-up. Update on the Rs 850 crore Sandur town project for Karnataka Mineral Rehabilitation Exploration Fund.

    Answer. Project has 4 components. Two have been cleared by the highest technical body and are going for draft tender procurement. The other two estimates are with the competent authority and expected to clear in 10-20 days. Bidding expected to close by Q2 FY26 or within 15 days thereof.

  2. 2. Government scheme execution

    Sanket Sadh, AARTH AIF

    Question. Any improvement from the government on AMRUT and Jal Jeevan Mission execution compared to last year when there was some slowdown?

    Answer, C. Mruthyunjaya Swamy, Chairman & Executive Director. Both schemes are funded by Central and State governments. Central government is delivering on committed funds; no dip seen in revenue realization from either scheme. Major Q1 FY26 revenue was earned through Jal Jeevan Mission and AMRUT.

  3. 3. FY27 guidance

    Maitri Shah, Sapphire Capital

    Question. Guidance for FY27 order inflow — is Rs 600-700 crore a fair assumption? Also, what percentage growth over FY26 Rs 300 crore can be expected?

    Answer, C. Mruthyunjaya Swamy, Chairman & Executive Director. Confirmed 30% increase over FY26. Margins on newer projects to be maintained at current levels (25-26% PAT) given debt-light model and procurement efficiency. Also clarified that the Rs 750-800 crore water supply order is separate from the Rs 850 crore Sandur project.

    Follow-up. Order inflow guidance for full year FY26?

    Answer. Anticipating around Rs 1,000 crore for FY26.

    Partly answered.

  4. 4. Quarterly guidance

    Aniket Madhwani, Steptrade Capital

    Question. Management guidance for September quarter and FY26.

    Answer, C. Mruthyunjaya Swamy, Chairman & Executive Director. Q2 FY26 expected to deliver 20% revenue increase over Q2 FY25. Did not provide specific FY26 revenue guidance in this exchange. Working capital days reported at 40-50 days.

    Follow-up. Current working capital days?

    Answer. 40-50 days.

  5. 5. FY26 revenue target

    Mukund Agarwal, BMC Advisors

    Question. Is the Rs 300 crore revenue target for FY26 being revised upward given new orders, or is Rs 300 crore the conservative floor?

    Answer, C. Mruthyunjaya Swamy, Chairman & Executive Director. For ongoing projects, ~40% revenue expected this year; new projects require DPR preparation and competent authority approval which takes months. Modest level of Rs 300 crore anticipated, striving to achieve much more. Confirmed each of the next three quarters should deliver better topline than Q1 Rs 67 crore. Margins to remain at Q1 levels.

    Partly answered.

  6. 6. Competitive intensity and margins

    Madhur Rathi, Counter Cyclical Investments

    Question. How is competitive intensity given the company reports much higher margins than other water EPC players? Can margins be sustained at 30-35% EBITDA in large tenders like Sandur and the Rs 750 crore project?

    Answer, C. Mruthyunjaya Swamy, Chairman & Executive Director. Few listed competitors in Karnataka water/groundwater recharging; many unlisted players. Technical efficiency and on-time delivery are competitive moats. Tenders under Karnataka Transparency Act attract 3-4 bidders. Rates calculated meticulously for raw material and execution. O&M costs are 7-8% of project cost with similar margin profile (specific margin to be confirmed later).

    Follow-up. Why is working capital intensity rising — FY22 had ~Rs 16 crore vs FY25 with ~Rs 150 crore stuck in inventory and receivables on similar revenue? What percentage of revenue should be modeled going forward?

    Answer. IPO funds accessed Feb 1, 2025. Rs 50 crore deployed in FY25 and Rs 100 crore to be deployed in FY26 for working capital per offer document. Material procurement (MS, DI, HDPE pipes, steel, cement) placed with Jindal and Tata with 20-25 day manufacturing lead time plus coating/painting treatment. Installation began in Q1 FY26. Working capital converts in 40-50 days.

  7. 7. Order book execution schedule

    Sanjay Nandi, VT Capital

    Question. Timeframe for execution of the Rs 594 crore outstanding order book, setting aside Rs 180 crore of new orders.

    Answer, C. Mruthyunjaya Swamy, Chairman & Executive Director. 40% of the outstanding order book will be completed in FY26; 60% (of Rs 583 crore base) will be realized in FY27. Fresh orders beyond the existing book will also contribute to revenue.

  8. 8. Order book age and cash realization

    Om Dhavane, Individual Investor

    Question. Can the current outstanding order book be bifurcated into orders received in current vs prior financial year? What percentage of Q1 sales were realized in cash?

    Answer, C. Mruthyunjaya Swamy, Chairman & Executive Director. All existing outstanding order book was received in the prior year. Fresh orders of Rs 180 crore won between June 30 and August 14 will roll into Q2 FY26 order book. 80% of Q1 sales were realized in cash.

  9. 9. FY27 execution and margin sustainability

    Deepak Poddar, Sapphire Capital

    Question. How much of the Rs 1,000 crore FY26 order inflow target can be executed in FY27, and what is the JJM share of the current order book? Is there risk the Rs 1,000 crore target falls short? Is 30-35% EBITDA margin sustainable?

    Answer, C. Mruthyunjaya Swamy, Chairman & Executive Director. About 40% of the Rs 1,000 crore target can be executed in FY27, implying higher growth than the 30% FY27 guide. Confident of capturing the work based on technical capability. Executing 3 JJM projects currently; mix of AMRUT and JJM in the pipeline. JJM order book break-up not available now. Margins compared favorably with EMS and rainwater companies; trying to sustain at current levels. No risk to Rs 1,000 crore target flagged.

    Not answered directly.

  10. 10. Non-core investments

    Avantika Jawahar, Individual Investor

    Question. Are there investments in Madikeri land and a resort homestay? How do these integrate with the core business and what is their value?

    Answer, C. Mruthyunjaya Swamy, Chairman & Executive Director. 95-acre coffee plantation in Madikeri and UVA Sands resort in Kundapura held as collateral for non-fund-based BG requirements per bank stipulation. Both running well. Total investment value around Rs 25 crore. Not core business.

  11. 11. Working capital structure

    Madhur Rathi, Counter Cyclical Investments

    Question. Can working capital cycle of 184 days come down to 90 days or lower? Is the Rs 184 crore figure days or rupees?

    Answer, C. Mruthyunjaya Swamy, Chairman & Executive Director. Clarified that Rs 184 crore is the working capital amount in rupees, not days. Working capital cycle is 40-50 days.

  12. 12. Q2 growth clarification

    Maitri Shah, Sapphire Capital

    Question. Clarification on Q2 FY26 growth — is it 20% or 30% YoY? Does the 20% figure imply a sequential decline from Q1 FY26?

    Answer, C. Mruthyunjaya Swamy, Chairman & Executive Director. Confirmed 20% growth when compared to Q2 FY25. Did not directly address the sequential comparison concern, but indicated Q2 FY25 was itself a healthy revenue quarter.

    Partly answered.

  13. 13. Q2 revenue inconsistency

    Rahil S, Sapphire Capital

    Question. Earlier Q2 revenue guide of 20% over Q2 FY25 implies a sequential decline versus Q1 FY26 Rs 67 crore run-rate — why the inconsistency?

    Answer, C. Mruthyunjaya Swamy, Chairman & Executive Director. Acknowledged figures may have got mixed up; said it will not come down and promised to come back with the correct expected revenue figure.

    Not answered directly.

What was said

Topic by topic, in the order it was spoken

Q1 FY26 Financial Performance · C. Mruthyunjaya Swamy (Chairman & Executive Director)

  • Revenue from operations for Q1 FY26 was Rs 67.28 crore, up 24.24% QoQ and 35.92% YoY
  • EBITDA for the quarter was Rs 25 crore with margins of 37.15% vs 34.22% in Q4 FY25
  • PAT was Rs 18.55 crore translating to a PAT margin of 26.57%
  • Improvement driven by operating leverage, favorable project mix, and lower finance costs
  • Portion of deferred billings from Q4 FY25 materialized this quarter with balance expected in coming quarters

Order Book and Pipeline · C. Mruthyunjaya Swamy (Chairman & Executive Director)

  • Outstanding order book as of June 30, 2025 stood at Rs 593.68 crore
  • Water management remains the core focus, with roads, railways and irrigation adding diversification
  • New orders worth Rs 180 crore won between June 30 and August 14, 2025
  • Bidding pipeline includes Rs 750-800 crore Karnataka water supply project and Rs 850 crore Sandur project
  • FY26 order inflow target set at ~Rs 1,000 crore

Geographic Expansion Strategy · C. Mruthyunjaya Swamy (Chairman & Executive Director)

  • Expanding beyond Karnataka into water-deficit states: Gujarat, Madhya Pradesh, Maharashtra, Uttar Pradesh, Haryana
  • These states identified under Government of India's Atal Jal scheme
  • Focus on groundwater recharging, sustainability, and improved availability
  • Continuing selective opportunities in roadways and railways
  • Plan to bid for new projects in Karnataka that are in final DPR or bidding stage

Operations and Execution Capabilities · C. Mruthyunjaya Swamy (Chairman & Executive Director)

  • Steady progress on large-scale water supply and groundwater recharging projects
  • Strengthened project management and engineering capabilities for efficiency and timely delivery
  • Material procurement covers mild steel pipes, ductile iron pipes, HDPE pipes, steel and cement
  • Procurement from reputed manufacturers like Jindal and Tata
  • MS pipes require external uniting, inner epoxy coating, and outer painting before site installation

Sector Outlook and Demand Environment · C. Mruthyunjaya Swamy (Chairman & Executive Director)

  • Demand environment described as very encouraging
  • Government sustained focus on water reuse, recycling and water infrastructure development
  • No dip observed in revenue realization from Jal Jeevan Mission or AMRUT scheme
  • Major Q1 revenue earned through Jal Jeevan Mission and AMRUT scheme
  • Current scheme focus: groundwater recharging, sustainability, and improved water availability

Social Impact and Recognition · C. Mruthyunjaya Swamy (Chairman & Executive Director)

  • Projects have improved health conditions, drinking water access, fish culture and livestock in target areas
  • Project adopted under MP area development scheme by Finance Minister
  • G20 Summit leaders and UN General Assembly President have visited project site
  • Methodology uses treated sewage water from BWSSB for groundwater recharge via tank water bodies
  • Improved year-round groundwater availability cited as key outcome

Balance Sheet and Financial Strength · C. Mruthyunjaya Swamy (Chairman & Executive Director)

  • Characterized as debt-light with healthy margins
  • Debt utilized only for non-fund-based obligations like bank guarantees
  • IPO funds of Rs 50 crore deployed in FY25 and Rs 100 crore to be deployed in FY26 for working capital
  • Madikeri 95-acre coffee plantation held as collateral for non-fund-based requirements
  • UVA Sands resort in Kundapura also held for similar collateral purposes

In their words

30% increase over '25-'26.
C. Mruthyunjaya Swamy (Chairman & Executive Director, Denta Water and Infra Solutions)
We are anticipating around Rs. 1,000 Cr.
C. Mruthyunjaya Swamy (Chairman & Executive Director, Denta Water and Infra Solutions)
Probably Q1, Q2, some figures have got mixed up. I will come back to you with the exact expected revenue only. It will not come down.
C. Mruthyunjaya Swamy (Chairman & Executive Director, Denta Water and Infra Solutions)

To check next time

What management committed to on this call, or the dates they gave.

  • Sandur project tender closure (expected by Q2 2025 calendar, ±15 days)
  • Q2 FY26 revenue outcome vs the 20%-over-Q2-FY25 guide and reconciliation vs Q1 ₹67.28 cr
  • Approval of remaining 2 Sandur project components (10-20 days from call)
  • LOI announcement on ₹750-800 cr Karnataka water supply and ₹120 cr tenders
  • Order inflow progress toward ₹1,000 cr FY26 target
  • Deployment update of remaining ₹132 cr IPO proceeds for working capital

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Mon 18 Aug 2025₹343.90+1.76%+1.00%
5 sessions Fri 22 Aug 2025₹423.40+25.28%+0.97%
20 sessions Mon 15 Sept 2025₹417.70+23.60%+1.78%

From the close of Thu 14 Aug 2025, ₹337.95: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.