Finolex Cables Q2 FY25 earnings call

Thu 14 Nov 2024FINCABLES

In brief

Management's tone
Cautious
What was said
Mixed
Guidance
None given
Analyst pushback
Medium
Stock, next session
+0.05% (Nifty 50 −0.11%)
  • Q2 FY25 revenue rose 7% QoQ/10% YoY to INR1,312 crores, but EBIT margin slipped ~4pp YoY on copper-related price cuts and inventory liquidation — CFO says 'worst is behind us'.
  • Partner has been placed L1 in 3 of 16 BSNL BharatNet packages; ordering expected late Q3 FY25, supplies from Feb-March; 3-year execution + 7-year maintenance, with cable being ~10% of each package value.
  • E-beam facility commissioned and awaiting BIS clearance; preform plant (100 MT glass / ~4M km fiber) commissioning in next 2 weeks with production from Q4 FY25; full INR500 crore capex program nearly complete.
  • FMEG business at INR128 crores in H1 FY25 vs INR100 crores in H1 FY24, on track for ~INR300 crores in FY25 (~40% YoY growth); break-even threshold of INR250-260 crores expected to be cleared this year.
  • Wire volume growth was just ~2% — CFO attributed gap to peers reporting consolidated wires+cables while Finolex has only ~INR200 crore presence in the INR25,000 crore power-cables market; DSO of 14-15 days highlighted as discipline differentiator.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q2 FY25

This quarterA year agoLast quarterMargin
Revenue₹1,312 cr+10.5%+6.6%
EBITDA (excl. other income)₹111 cr−36.8%−60.6%8.5% (14.8% a year ago)
Net profit₹118 cr−23.5%−51.7%9% (13% a year ago)
EPS (₹)₹7.71−23.5%−51.7%

From the company's filed results for the quarter ended 30 Sept 2024 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

The numbers management led with

  • Q2 FY25 consolidated revenue: INR1,312 crores (+7% QoQ, +10% YoY)
  • Indian wire market size (estimate): INR25,000 crores
  • Finolex wire market share: ~18-20% of the INR25,000 crores wire market
  • Communication cable fiber draw capacity expansion: 4 million km → 6 million km (Phase 1) → 8 million km (Phase 2)
  • Capex programme total: ~INR500 crores; INR160 crores spent in FY24; bulk of balance in FY25, small overflow into FY26

Guidance

Guidance on this call

WhatForWhat management saidOn the Q1 FY25 call
Revenue (full-year FY25)FY25If copper remains steady, 'towards the INR6,000 crores number'; H1 already at INR2,600 crores—
EBIT marginQ3-Q4 FY25'Track back to normalcy' in coming quarters; consensus reference ~10-11% level—
CapexFY26INR100-200 crores possible in FY26, residual of the INR500 crore programme₹500 crore earmarked overall — E-beam facility, OFC preforms (live Q4 FY25), fibre drawing (4M→6M→8M km), Roorkee auto cables +50% capacity
Communication cable EBIT margin6-8 quartersHistorically 7-8%; should 'start climbing' once BSNL procurement resumes—
FMEG revenueFY25'Very close to the INR300 crores mark' in FY25 (vs INR228-230 crores FY24)—
Said on the Q1 FY25 call, not repeated on this one (3)
  • Revenue growth: 'Five digit growth' over the next 4–5 years (i.e. 10%+ per annum); FY24 base of ₹5,014 crore
  • New products revenue: Target of ₹500 crore over 2–3 years vs ₹225 crore achieved in FY24
  • Dividend per share: ₹8 per share recommended for FY24 (400% of face value of ₹2)

The business

The industry, as management sees it

Wire demand has been muted for 6-8 months owing to copper-led speculative destocking; management believes electrical cables should show recovery signs from Q3 onward. Power-cables demand described as 'strong' though tender-driven with collection risk. Communication cables viewed positively as government procurement resumes (BSNL followed by 7-8 state DPRs expected over next 3-6 months including Gujarat, Maharashtra, Karnataka, AP), and global fiber pricing is expected to normalise in 6-8 months as 5G/data-centre demand picks up.

Risks management named

  • Sustained copper price volatility could delay margin recovery to steady-state 11-12% range
  • Project-based mix shift in cables weighed on wire margins (~slight incremental pressure)
  • Fiber pricing remains soft due to global (China) overcapacity — visibility on recovery is 6-8 months out
  • Government contract pricing for BSNL-style tenders is firm for the execution period; protection relies on back-to-back supplier freezes

Q&A

The Q&A was dominated by copper-volatility and margin-recovery discussions from Jefferies (Sonali), with the CFO repeatedly walking through LME price paths, inventory dynamics and price-cut math. The single longest discussion was with Nuvama (Achal Lohade) covering capacity, market structure versus Polycab/KEI/Havells, communication-cable margin trajectory and capex phasing — the CFO deflected any comment on peer hedging practices and declined to quantify BSNL order values at this stage. Litigations on disputed Orbit shares were probed by an individual investor and acknowledged as still pending before NCLT. The most direct exchange was on revenue guidance, where the CFO committed only to an 'INR6,000 crores' directional figure contingent on copper stability. Topics deflected: precise BSNL order quantum (too early), peer hedging comparisons, industry capacity beyond IEEMA data, and identifiable market-share by subsegment.

Not answered directly

  • BSNL order quantum and partner identity (too early in process)
  • Peer hedging/sourcing strategy (declined to comment)
  • State-level BSNL package coverage (could not recall offhand)
  • Industry-level capacity publication (only IEEMA, post-2014 not mandated)

Every question, with its answer

  1. 1. BSNL / BharatNet tender

    Sonali, Jefferies India

    Question. Could you share any details on the BSNL/BharatNet tender — quantum of order, regions, contract terms, and who the partner is?

    Answer, Mahesh Viswanathan, Deputy CEO and CFO. The bids have been opened only in the last 2 days; we had an understanding with one of the bidders that they would use Finolex cables. They have won 3 of the bids they participated in. At this point, contract values are too early to disclose and I would not want to name the bidder until the process completes.

    Follow-up. Question on electrical wires — volume growth was muted at ~2% this quarter; can you help us understand current demand scenario?

    Answer. Demand has been muted for the last 6-8 months. Copper climbed from $8,500 to ~$11,000 in early calendar year, prompting prebuying, then corrected sharply from $11,000 to $8,200-$8,300 by mid-May, which stalled further trade buying through August. Speculative pre-buy has since been consumed; the peaks and valleys have been sharp with limited stability.

    Not answered directly.

  2. 2. Channel destocking

    Sonali, Jefferies India

    Question. Was there destocking in channels due to the copper correction from $11,000 to $8,000 through mid-August, and are channels now restocking?

    Answer, Mahesh Viswanathan, Deputy CEO and CFO. Spot copper dropped below $9,000 again around call date (~$8,800-$8,900); swings remain high with limited stability windows, so demand normalisation is hard to predict confidently.

    Follow-up. Can you quantify the inventory loss in Q2?

    Answer. Inventory is back to near-normal levels: INR570 crores in March vs INR604 crores in September; inventory days at 52 (same as March-end).

  3. 3. Price cuts

    Sonali, Jefferies India

    Question. Can you quantify the price cuts taken in Q2?

    Answer, Mahesh Viswanathan, Deputy CEO and CFO. There were 3 corrections totalling ~11% during the quarter; one +2% increase on September 30 (the first price increase after 4 months). LME has been dipping in the week before the call, so further moves depend on how that plays out.

    Follow-up. Structurally, do you see housing and capex cycles holding up?

    Answer. They are steady in absolute terms, but the copper volatility distorts the picture considerably.

  4. 4. Mix change

    Sonali, Jefferies India

    Question. Has competition/mix change contributed to the margin pressure beyond copper?

    Answer, Mahesh Viswanathan, Deputy CEO and CFO. There has been more project-based selling as opposed to pure retail — slightly negative for margins but not large. Same channel mix, but longer lengths (for contractor/building segment) have sold more than standard 90-metre retail boxes, and long-length pricing is finer.

    Follow-up. Project share (B2B) was ~25% last quarter — what is it now?

    Answer. Clarified that 'project-based' here refers to long-length sales through the same channel rather than a separate B2B split; project lengths have grown at the expense of standard box SKUs.

    Not answered directly.

  5. 5. Margin recovery

    Sonali, Jefferies India

    Question. Do you expect margins to revert to the 11-12% steady-state in the coming quarter, or will volatility/mix continue to weigh?

    Answer, Mahesh Viswanathan, Deputy CEO and CFO. If copper volatility continues, getting back to 12% might take a little longer — it will eventually get there but the journey may be longer.

    Follow-up. Within electrical cables, any material subsegment shift (auto, construction, etc.)?

    Answer. No material change other than seasonal — Q2 agricultural volumes lower due to monsoon; nothing structural in subsegment mix.

  6. 6. Market share & litigation

    Shriram R, Individual Investor

    Question. What is Finolex's market share in the wires segment, and any update on pending litigation?

    Answer, Mahesh Viswanathan, Deputy CEO and CFO. On an annual basis, Finolex wires revenue was INR4,200-4,300 crores against a wire market of ~INR25,000 crores — ~18-20% share. Other than public-domain disclosures, nothing to add on litigation; the NCLAT matter was disposed off and directed NCLT to decide the disputed shareholding in Orbit (and consequent control) expeditiously.

    Follow-up. Was market share steady over the last 2-3 years?

    Answer. More or less steady, with maybe 1% variation either way.

  7. 7. Capacity & utilisation

    Achal Lohade, Nuvama Institutional Equities

    Question. Could you share current electrical cables/wires capacity and the expansion plan over the next 2-3 years?

    Answer, Mahesh Viswanathan, Deputy CEO and CFO. Standard wire capacity is ~23-24 lakh coils per month (using 90-metre box as unit); utilisation slightly above 65%. Auto cable is ~80% utilised; agri seasonal with low Q2 occupancy. Company-level wire asset utilisation is ~65-70%.

    Follow-up. Does the INR4,200 crores FY24 wires number include auto and agri or is it pure wires?

    Answer. Pure wires — auto and agri are excluded.

  8. 8. Industry capacity

    Achal Lohade, Nuvama Institutional Equities

    Question. Any comparable industry-level capacity figures for wires and cables?

    Answer, Mahesh Viswanathan, Deputy CEO and CFO. Only IEEMA publishes, and member transparency varies; MCA mandated capacity disclosures pre-2014 but that requirement was removed, so industry-level data is limited.

    Follow-up. While copper has been volatile, peers have reported 20%+ volume growth in wires — is there any structural difference in sourcing/hedging?

    Answer. Declined to comment on peer practices. We buy on month averages with provisional pricing settled month-end; we do not take long calls on copper. Corrected that KEI reported +9% in wires (not volumes); Polycab's cable revenue grew 24% with EBIT margin 12.3% (down 231 bps). Everyone faced wires-side pressure; Finolex's participation in power cables is sub-INR200 crore (plus INR200 crore JV) versus an INR25,000 crore market.

    Not answered directly.

  9. 9. Power cable capacity

    Achal Lohade, Nuvama Institutional Equities

    Question. Are there plans to add capacity in power cables, and how is the demand situation there?

    Answer, Mahesh Viswanathan, Deputy CEO and CFO. Strong demand, does not see demand falling. But it is tender-driven, L1-based; customer mix is heavy on distribution-side power utilities with collection/timing risk. Many peers show DSO of 60-70+ days; Finolex's DSO is 14-15 days. Some industry practices are not comfortable for us, so we will stay selective.

    Follow-up. On communication cables, segment EBIT is 2-2.5% — will BSNL orders be similar or materially different at company level?

    Answer. Should be better than current. Two drags: realisations (fiber pricing) and low government procurement volume depressing utilisation and fixed cost absorption. Government accounts for ~60% of segment buy, has been absent 18 months. Historically 7-8% segment margin; should start climbing once procurement resumes — will take time to reach historical.

  10. 10. BSNL execution period

    Achal Lohade, Nuvama Institutional Equities

    Question. What is the execution/supply period for the BSNL cables tender?

    Answer, Mahesh Viswanathan, Deputy CEO and CFO. Current BSNL tender — 3-year installation period, followed by 7-year maintenance. Cable is ~10% of each package on average (range 9-11%); rest includes erection, active and passive electronics, etc. Package values can vary slightly with concentration of other elements.

    Follow-up. Capex outlook for FY25, FY26 and FY27?

    Answer. Major capex: preform plant Phase 1 (100 MT glass ≈ 4M km fiber) commissioning in 2 weeks, Q4 FY25 production; fiber draw capacity 4M→6M km with equipment arrival Q2 FY26, then→8M km; cable capacity shell ready, decision post-BSNL clarity (equipment lead time 7-8 months). E-beam installed, awaiting BIS to launch as ISI product. Auto cables Roorkee commissioning Dec-24. Total programme ~INR500 crores; INR160 crores in FY24, bulk of rest in FY25 with small overflow FY26. Over the longer term, will evaluate additional wire capex based on demand stability.

  11. 11. FY26 capex

    Achal Lohade, Nuvama Institutional Equities

    Question. Is it fair to say FY26 capex could be INR100-200 crores?

    Answer, Mahesh Viswanathan, Deputy CEO and CFO. Yes, it's possible.

  12. 12. Revenue guidance

    Raman KV, Sequent Investments

    Question. What is the revenue or volume guidance for this year?

    Answer, Mahesh Viswanathan, Deputy CEO and CFO. Last year revenue was just over INR5,000 crores. If copper remains steady, 'towards the INR6,000 crores number'. H1 at INR2,600 crores; typically Q3+Q4 are 60%+ of the full year — that is a directional indicator.

    Follow-up. Can we expect margins around 10%?

    Answer. Q2 margins were low but should track back to normalcy in coming quarters.

  13. 13. Communication cable margin recovery

    Praveen Sahay, Prabhudas Lilladher

    Question. On communication cables (currently 2-2.5% margin) — once utilisation improves, what margin can this business reach?

    Answer, Mahesh Viswanathan, Deputy CEO and CFO. Historically averaging 7-8% in margins; definitely doable. Backward integration of optical fiber (preform plant) will capture margin currently paid to suppliers — either used for competitive pricing or retained for margin expansion.

    Follow-up. In long-gestation project bids, how is raw material price passed through?

    Answer. We build a price variation clause into the bid; for government tenders where prices must be firm, we back-to-back freeze with suppliers at order receipt.

  14. 14. BharatNet project lifespan

    Praveen Sahah, Prabhudas Lilladher

    Question. What is the lifespan of a BharatNet project?

    Answer, Mahesh Viswanathan, Deputy CEO and CFO. Main installation to be completed in 3 years; sales contracts with cable supply include a price variation clause to protect against copper moves during the execution window.

    Follow-up. If we backward-integrate into optical fiber manufacturing, is there a material margin difference vs just cable supply?

    Answer. Yes, normally. Fiber can be up to ~50% of cable cost depending on design; BSNL-type 48F/96F cables would see a material difference. Last 2 years have been distorted by Chinese overcapacity (prices from $4-4.5/km to ~$2.8/km), but this will not last long with 5G picking up.

  15. 15. State coverage & utilisation

    Praveen Sahay, Prabhudas Lilladher

    Question. Which states are covered in this BSNL round, and what's the communication cable utilisation currently?

    Answer, Mahesh Viswanathan, Deputy CEO and CFO. Could not recall offhand which bids the partner won (one of 16 packages). Separately, 7-8 more state DPRs are under evaluation and likely to come out with tenders over the next 3-6 months — including Gujarat, Maharashtra, Karnataka, AP. Current utilisation is high because we are one of the largest suppliers to Bharti Airtel — they fill roughly 60% of capacity.

    Not answered directly.

  16. 16. FMEG business

    Mukesh Patil, Individual Investor

    Question. What is the H1 number for the FMEG business?

    Answer, Mahesh Viswanathan, Deputy CEO and CFO. About INR128 crores at end of H1 vs INR100 crores last year. Volumes doing well in lighting, switches and switchgear; need improvement in fans and water heaters; conduits strong. On track for INR300 crores in FY25 (~40% jump over FY24). Breakeven still around INR250-260 crores. Note: lighting has had strong price erosion offsetting some volume gain.

    Follow-up. What was the volume growth for the wire and cable business in Q2?

    Answer. Overall volume growth ~2%.

What was said

Topic by topic, in the order it was spoken

Copper Volatility & Inventory Liquidation · Mahesh Viswanathan (Deputy CEO and CFO)

  • Started the quarter with high-cost copper inventory built when LME was elevated; first two months spent liquidating both at company and trade levels.
  • LME copper trajectory: ~$10,130 (May) → $9,641 (Jun) → $9,394 (Jul) → $8,963 (Aug); spot dropped below $9,000 by mid-Q2 and re-corrected below $9,000 again at call date.
  • First price increase after 4 months taken on September 29 (+~2%); margins took a hit during the liquidation window.

Q2 Financial Performance — Revenue & Margins · Mahesh Viswanathan (Deputy CEO and CFO)

  • Consolidated revenue Q2 FY25: INR1,312 crores, +7% QoQ and +10% YoY.
  • EBIT margin dropped ~4 percentage points YoY and ~1.5 percentage points QoQ.
  • Volumes were 'steady' given environment; electrical cables should show recovery signs from Q3 onwards.
  • Management view: 'the worst is behind us' on margin.

Communication Cables & Fiber Pricing · Mahesh Viswanathan (Deputy CEO and CFO)

  • Fiber cable volumes +50% QoQ, but realisations fell — drove segment margin to 2-2.5% from historical 7-8%.
  • Fiber pricing: was $4/km 2 years ago, now $2.6-2.7/km landed in India; expects normalcy in 6-8 months as global 5G/data-centre demand recovers.
  • Government procurement has been absent for 18 months — historically ~60% of segment buy; BSNL resumption should drive utilisation and margin recovery.

BSNL / BharatNet Tender Opportunity · Mahesh Viswanathan (Deputy CEO and CFO)

  • Bids opened in early November; partner with whom Finolex has an understanding has won 3 of the bids they participated in (out of 16 packages).
  • Ordering from BSNL expected late this quarter; supplies likely to commence Feb-Mar 2025.
  • Package structure: 3-year execution + 7-year maintenance; cable share ~10% (range 9-11%).
  • Seven to eight state DPRs under evaluation; further tenders expected over next 3-6 months including Gujarat, Maharashtra, Karnataka, AP.

FMEG Growth Trajectory · Mahesh Viswanathan (Deputy CEO and CFO)

  • FMEG H1 FY25 at ~INR128 crores vs ~INR100 crores H1 FY24.
  • FY25 target ~INR300 crores vs INR228-230 crores in FY24 (~40% YoY growth).
  • Break-even threshold of INR250-260 crores expected to be crossed this year.
  • Lighting prices have seen heavy price erosion, partially offsetting volume gains; fans and water heaters remain areas to improve.

Capex Programme & Expansion · Mahesh Viswanathan (Deputy CEO and CFO)

  • E-beam facility (2 accelerators, 1 MeV + 1.5 MeV) installed; awaiting BIS certification to enable ISI-marked product launch.
  • Preform plant (Phase 1, 100 MT glass ≈ 4M km fiber) commissioning in 2-3 weeks; production from Q4 FY25.
  • Fiber draw capacity expansion: 4M km → 6M km (Phase 1) → 8M km (Phase 2); equipment arrival May-June 2025.
  • Auto cable capacity at Roorkee being doubled; machines installed, testing underway, commissioning by Dec-24.
  • Cable capacity already built (8M → 10M km shell); decision pending BSNL ordering clarity.
  • Total programme ~INR500 crores; INR160 crores spent in FY24; bulk of balance in FY25 with small overflow into FY26.

In their words

I believe that as far as the margin corrections are concerned, the worst is behind us, and we should be more stable from now onwards.
Mr. Mahesh Viswanathan (Deputy CEO and CFO, Finolex Cables Limited)
We buy on month averages, we don't take long calls.
Mr. Mahesh Viswanathan (Deputy CEO and CFO, Finolex Cables Limited)
If the volatility continues, then getting back to 12% might take a little longer. That's about it. It will eventually go there, but the journey might be a little longer.
Mr. Mahesh Viswanathan (Deputy CEO and CFO, Finolex Cables Limited)

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Thu 14 Nov 2024₹1,137.35+0.05%−0.11%
5 sessions Fri 22 Nov 2024₹1,116.75−1.76%+1.48%
20 sessions Fri 13 Dec 2024₹1,270.35+11.75%+5.13%

From the close of Wed 13 Nov 2024, ₹1,136.80: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

Finolex Cables's other calls