  • CFO commits to 60-70% YoY revenue growth in FY25 on Rs 711 cr H1 base; PAT margin guided at 16-18% sustained.
  • Order book at all-time high of 2.41 GW (1.2 GW IPP + 1.1 GW CPP), of which ~70-80% won in FY25.
  • Standalone net debt is zero; FY25-end long-term debt guided at Rs 400-500 cr for Khavda IPP project.
  • Net realization on GUVNL PPA at Rs 3/unit (blended Rs 4-5/unit); IPP EBITDA margin 85-90%, will lift blended PAT margin to 20-22% as IPP mix rises.
  • Related-party EPC contract with group co KP Energy on GUVNL 1 GW hybrid project — arm's length per CFO; KP Energy set to list on NSE on Nov 14.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q2 FY25

This quarterA year agoLast quarterMargin
Revenue₹360 cr+67.2%+3.4%
EBITDA (excl. other income)₹133 cr+86.5%+1.6%36.9% (33.1% a year ago)
Net profit₹69.8 cr——19.4% (0% a year ago)
EPS (₹)₹5.55−42.3%−49.4%

From the company's filed results for the quarter ended 30 Sept 2024 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

The numbers management led with

  • IPP order book: 1.26 gigawatts — largest in company history
  • CPP order book: 1.148 gigawatts
  • CPP order book value: Rs 2,500-3,000 crores (at Rs 2.5-3 cr per MW)
  • 10 GW capacity target by 2030: Long-term ambition vs ~507 MW installed today

Guidance

Guidance on this call

Revenue growth guidance of 60-70% over FY24 base; PAT margin guidance maintained at 16-18% (could rise to 20-22% as IPP mix lifts); OPM guidance of 32-33% full-year FY25; CPP order book (1.1 GW) to be executed by September 2025; IPP order book (1.2 GW) to complete by mid-FY27; FY25-end long-term debt at Rs 400-500 cr; debt-to-equity will not exceed 2:1; net realization Rs 4-5/unit blended; CUF uplift of 3-4% with single-axis trackers.

The business

The industry, as management sees it

Management sees strong, multi-year demand momentum in Indian renewables driven by central schemes (PM-Surya Ghar, etc.), state discom tenders (GUVNL, MAHAGENCO) and growing C&I captive demand from conglomerates. No shortage of order flow at industry level; the differentiator is hybrid (wind+solar) execution capability. Module price weakness is viewed as positive for developers like KPI.

Risks management named

  • Execution ramp-up from ~30-65 MW quarterly run-rate to ~1.15 GW in next 12 months
  • Working capital / trade receivable cycle stretches when onboarding large discom customers
  • IPP revenue only begins after full project energization under GUVNL PPA — no partial booking
  • Dependence on panel/wind turbine pricing trends for IPP IRR economics (target 15-16% project IRR)
  • Related-party transactions (KP Energy EPC, Sun Drops Energia private placement) require continuous governance scrutiny

Q&A

Q&A was dominated by order-book and execution questions, with analysts probing how a company that has historically commissioned 30-65 MW per quarter will deliver 1.15 GW over the next 12 months; management attributed the apparent ramp gap to milestone-based revenue recognition versus actual physical progress. Strong pushback surfaced on (a) the related-party KP Energy EPC contract — multiple investors raised governance flags and were given arm's-length assurances, (b) margin sustainability as GUVNL reverse-bidding PPA rates drop to Rs 3/unit, addressed with the IPP EBITDA margin of 85-90% argument, and (c) capital structure, including the recent bonus issue rationale (CFO framed it as shareholder reward, not economic dilution). Cash-flow-from-operations questions got a concrete answer — Rs 59 cr positive in H1 vs Rs 57 cr negative in March — attributed to receivables normalization. International expansion remained evasive ('nascent stage') despite multiple probes.

Not answered directly

  • International expansion plans — no specifics given, only 'nascent stage'
  • Exact value of EPC contract awarded to KP Energy — pending financial closure
  • Stake percentage given to promoter in Sun Drops Energia subsidiary — 'on public domain' but CFO did not cite figure
  • Battery energy storage (BESS) entry decision — 'no call taken at present'

Every question, with its answer

  1. 1. FY25 revenue guidance

    CA Garvit Goyal, Nvest Analytics Advisory LLP

    Question. What is the FY25 revenue (topline) guidance given the current order book and inflow pipeline?

    Answer, Salim Yahoo, Chief Financial Officer. Already done Rs 711 cr in H1, which is ~75% of FY24 full year. Expects 60-70% growth over FY24 topline as minimum, with potential upside — supported by sufficient order book for execution.

    Follow-up. How sustainable are current margins given the industry environment, and what is the outlook for topline and margins over the next 2-3 years?

    Answer. Order potential is not an issue — all listed peers have full order books. KPI's USP is execution capability backed by decade of hybrid (wind+solar) experience. On margins, H1 is structurally higher due to milestone billing where some low-cost milestones are booked (especially during monsoon). Full-year PAT margin guidance maintained at 16-18%.

  2. 2. Competitive positioning

    CA Garvit Goyal, Nvest Analytics Advisory LLP

    Question. How will competition evolve for upcoming orders given all players have strong order books?

    Answer, Salim Yahoo, Chief Financial Officer. Order flow will continue for all players given sector potential. KPI differentiates on execution track record — 'all the orders that we have got because of our execution capabilities'. Hybrid (wind+solar) capability is rare among listed peers.

  3. 3. Order book size & vintage

    Sagar Tanna, Alchemie Ventures

    Question. What is the outstanding CPP/EPC order book in crores? How much was won in FY25? What is the H2 pipeline?

    Answer, Salim Yahoo, Chief Financial Officer. Total CPP order book is ~1.1 GW (some with material, some without). At Rs 2.5-3 cr per MW, the order book value is Rs 2,500-3,000 cr. 70-80% of the Rs 2,500-3,000 cr was won in FY25 itself. Of the Rs 3,000 cr, 40-50% (~Rs 1,200-1,300 cr) is targeted for closure in current year; rest will flow to FY26.

  4. 4. Geographic & bid pipeline expansion

    Aashish Rampuriya, Individual Investor

    Question. What is the bid pipeline beyond the existing order book (in GW or crores)? Status of expansion into Rajasthan, MP, and international markets?

    Answer, Salim Yahoo, Chief Financial Officer. Bid pipeline is 1.5-2 GW, mostly CPP because IPP plate is already full (1.2 GW). On geography: Maharashtra already operational (MAHAGENCO); Rajasthan and Andhra at final discussion stage. International at nascent stage — multiple inquiries received, but no details to share yet; KPI will compete internationally soon.

    Follow-up. Are nearby state conversations primarily corporate CPP deals? And can you clarify the order given to KP Energy that also includes solar work despite KP Energy being wind-specialized?

    Answer. Yes, nearby state focus is CPP because IPP requires state-specific financial closure and regulatory approvals. On KP Energy: the GUVNL 1 GW IPP tender is hybrid (wind+solar); KP Energy has both capabilities and is already working in the region, so giving the entire order (including solar component) to them leverages existing manpower rather than setting up parallel teams.

    Not answered directly.

  5. 5. Subsidiary related-party transaction

    Aashish Rampuriya, Individual Investor

    Question. What was the recent private placement in a subsidiary via the group promoter? What stake was given?

    Answer, Salim Yahoo, Chief Financial Officer. Subsidiary Sun Drops Energia Private Limited received a private placement from promoter. Rationale: promoter had infused large unsecured loans to support capex; rather than repay, promoter was given a small equity stake — better than curtailing cash flows. Stake percentage figure is 'on public domain' but CFO did not cite the number.

    Not answered directly.

  6. 6. Execution timeline & funding

    Parth Kotak, Plus91 Asset Management

    Question. Anticipated timelines for executing the Rs 2,200-2,300 cr order book, especially MAHAGENCO? With QIP of Rs 1,000 cr done and debt prepayment, how does management view future funding — debt or equity?

    Answer, Salim Yahoo, Chief Financial Officer. CPP order book (1.1 GW) targeted for completion by September 2025 on average; about 50% of order book to be executed in FY25, 50% flows to FY26. On funding: 1.2 GW IPP will require phased debt, including Rs 500-600 cr for Khavda and additional debt for the 370 MW hybrid + 250 MW solar GUVNL project. Debt-to-equity will not exceed 2:1; target ~1.5:1 even with full expansion capex.

  7. 7. IPP margin sustainability

    Drishtant, Individual Investor

    Question. Given reverse bidding on GUVNL, can you sustain similar margins and deliver 15-18% PAT margin over 3-5 years?

    Answer, Salim Yahoo, Chief Financial Officer. IPP EBITDA margins on GUVNL will be 85-90% because once plant is set up, only nominal O&M cost remains. Blended EBITDA currently 33-37%; as IPP mix rises, PAT margin of 16-18% today could move to 20-22%. Last year IPP was 13-14% of revenue vs CPP at 86% — mix shift will drive margin expansion.

    Follow-up. Rough estimate of the 3,000 acres of land value, especially own-land portion. And on cash flows: can we expect improvement in CFO/FCF given working capital build with larger clients?

    Answer. Own land is 500-600 acres at Rs 1.5-2 cr/acre (~Rs 1,000 cr total value) but carried at Rs 100 cr in books; rest is 27-28 year lease land. On cash flows: negative CFO in March 24 (Rs 57 cr negative) was temporary due to upfront investment for bigger orders and milestones. H1 FY25 turned positive at Rs 59 cr — receivables down, working capital cycle improved; expects to maintain and improve going forward.

  8. 8. Governance, related-party, capital structure

    Drishtant, Individual Investor

    Question. What's the idea behind getting a Group CEO? Will margins be maintained on orders given to KP Energy (related-party governance)? Why a bonus issue economically?

    Answer, Salim Yahoo, Chief Financial Officer. Group CEO: as KPI grows, stronger team required — incoming person has deep wind/renewable industry credentials; complements existing ex-GETCO, GEDA, banking, policy expertise on the board. On KP Energy: arm's length, no cross-holding between the two listed entities, all compliance met. On bonus: Dr. Faruk Patel's vision is to make shareholders feel valued through both dividends and bonuses — 'whenever we grow, we will keep our share of our shareholders' — and this will continue.

    Partly answered.

  9. 9. Capital structure, execution timeline, US policy

    Gaurav Sharma, Anujay Properties

    Question. With growth rate higher than ROE, will there be equity dilution or more debt to fund current order book? Tentative date of completion of 2.41 GW order book? US renewable policy impact on the company?

    Answer, Salim Yahoo, Chief Financial Officer. Equity already in place for current order book; no dilution needed this year and possibly the next. Post that, will reassess in two years. CPP completion by September 2025; IPP completion by mid-FY27 in phases. US policy: KPI is a domestic developer, not a panel manufacturer — exporter/manufacturer peers are the ones exposed; if there is a panel price war, KPI benefits as a buyer. India momentum (PM-led schemes) is intact.

    Follow-up. Faruk sir mentioned adding 2,000 acres of land bank — how is this funded and is it for current or future order book? Who is your closest listed competitor?

    Answer. Land acquisition is a continuous process for both current and future orders — will not be acquired in one go at one location. Land and evacuation (~2.3 GW) are the two key renewables assets. Closest listed peer: Adani Green is most comparable; Waaree and Sterling Wilson are partial matches (manufacturing or solar-only); no exact twin exists for KPI's hybrid IPP+CPP model.

  10. 10. Order book value conversion & IPP/CPP economics

    CA Amit Kumar, Individual Investor

    Question. At Rs 3 cr per MW, is the 2.41 GW order book worth ~Rs 7,200 cr? Please explain IPP vs CPP models.

    Answer, Salim Yahoo, Chief Financial Officer. IPP cannot be converted to rupee terms that way — revenue is over 22-25 years of power sale, not project execution. CPP order book of ~1.2-1.3 GW = Rs 2,500-3,000 cr. IPP: own capital + plant + PPA sale of power (25 years). CPP: build plant for customer, sell the plant (one-time revenue), then O&M + lease revenue for 25 years.

  11. 11. Execution ramp & revenue recognition

    Pavan, Fident

    Question. How will you ramp from ~30-65 MW quarterly commissioning to 1.15 GW in next 12 months? Does cost of goods sold relate only to CPP?

    Answer, Salim Yahoo, Chief Financial Officer. Revenue is milestone-based; megawatt capacity reflects only fully energized projects. Partial execution (60-80%) shows up in revenue but not in MW counted — that's why Rs 700 cr revenue may show low MW addition. Cost of goods sold is entirely CPP-related; all IPP capex gets capitalized.

    Follow-up. What are IPP per-unit realizations going forward (Q1: Rs 7.38, Q2: Rs 8.13) and project-level efficiency? Grid evacuation/transformer availability risks?

    Answer. Existing C&I IPP plants: Rs 6-7/unit. GUVNL PPA: Rs 3/unit blended (wind Rs 3.25-3.30, solar Rs 0.70-0.80). Net realization going forward Rs 4-5/unit as IPP mix shifts towards GUVNL's 1 GW. Land bank and evacuation already secured — execution capability is the differentiator. Confident of meeting timelines as before.

  12. 12. OPM sustainability & related-party margin

    Mayank Manikya, Individual Investor

    Question. Operating profit margin stepped up to 37-38% from 31-32% — is this sustainable? Will margins be maintained if orders are subcontracted to KP Energy?

    Answer, Salim Yahoo, Chief Financial Officer. H1 OPM is structurally higher because of milestone billing with low-cost milestones. Full-year OPM range will be 32-33%, in line with FY24. On KP Energy subcontracting: this is KPI's own IPP capex, not CPP order — capex order goes outside anyway; KPI gives KP Energy similar margins as outside players; no margin impact for KPI since it is capex.

  13. 13. Revenue mix, capex recovery, debt

    Preet Jain, Jain Securities

    Question. Future revenue mix: private vs government? Payback period for IPP capex? FY25-end total debt? ROE trajectory post-IPP? GUVNL completion timeline? MAHAGENCO order nature? Retail/rooftop plans?

    Answer, Salim Yahoo, Chief Financial Officer. IPP mix: ~80% government (GUVNL) + 20% C&I. CPP mix: ~50-50 government (MAHAGENCO) and private (Aditya Birla, Ayana). IPP payback 7-8 years at project level. FY25-end long-term debt Rs 400-500 cr (Khavda capex). ROE 28-29% currently; will rise as IPP profitability adds. GUVNL completion by FY26-27 end in phases. MAHAGENCO is CPP — KPI only executes, no power sale. Ground-mounted only — no retail rooftop, though small CPP for MSMEs (2-3 MW) exists.

  14. 14. 1 GW capacity milestone

    Nishant Sharma, Savitri

    Question. Target is 1 GW by March 2025; current 507 MW done — can we expect 500 MW in next 2 quarters?

    Answer, Salim Yahoo, Chief Financial Officer. Group-level 1 GW target already achieved; KPI standalone will also hit the milestone.

  15. 15. Business model uniqueness & IRR

    Pawan Kumar, Shade Capital

    Question. Elaborate on unique business model vs peers. With module prices dropping, will KPI bid for PPAs at even lower prices while maintaining IRRs? What IRR do you target?

    Answer, Salim Yahoo, Chief Financial Officer. Two segments: IPP (own capital, sell power 22-25 yr PPA, high EBITDA) and CPP (build plant on own land, sell plant + O&M + lease). Module price drop is welcome — current procurement already lucrative; lower costs → higher IRR. Target project-level IRR 15-16% but will review on case-by-case basis.

  16. 16. IPP revenue recognition, GUVNL timing, hydrogen

    Akhilesh Kumar, Adpro Technologies

    Question. How is IPP revenue accounted — at milestones or only after full energization? For GUVNL, when will actual revenue start? Green hydrogen plans under KPI or separate entity?

    Answer, Salim Yahoo, Chief Financial Officer. IPP revenue depends on PPA terms. For utility-scale (GUVNL): entire plant must be energized before revenue booking starts — so no revenue till full commissioning. For C&I (1-15 MW PPAs): revenue starts as each MW completes. So current quarterly revenue is entirely from C&I customers (L&T, Colourtex, UPL, Meghmani, Tata Motors). Most GUVNL revenue will come after a couple of years. Green hydrogen is a separate group company; KPI may supply green power to it.

  17. 17. BESS roadmap & CUF improvement

    Aashish Rampuriya, Individual Investor

    Question. BESS entry plans — under KPI Green or separate entity? Has solar CUF/PLF improved with trackers and bifacial panels (from ~20% to 22-24%)?

    Answer, Salim Yahoo, Chief Financial Officer. No BESS call taken yet — at nascent stage; likely separate company if it scales, but may need KPI support. On CUF, trackers + bifacial + robotic cleaning + NOC-room 24/7 monitoring give 3-4% uplift — new projects seeing 23-24% CUF.

    Not answered directly.

  18. 18. International plans & IPP revenue mix

    Samrat Shah, Individual Investor

    Question. Plans outside India? Can H2 see IPP % of revenue rise above current 13-14% to improve margins?

    Answer, Salim Yahoo, Chief Financial Officer. International still nascent — MoUs done, in talks, will take time to materialize. On IPP mix: H1 was 13-14% IPP, rest CPP. Full year will not see dramatic shift. But after 1.2 GW IPP is completed, IPP share will move to over 30% of revenue (matching Faruk sir's NDTV Profit guidance).

    Not answered directly.

  19. 19. Group structure & related-party clarification

    Subash, Value Investments

    Question. Confirm: KP Energy order is for KPI's CAPEX (IPP), arm's-length margins. Clarify Faruk sir's 'Rs 1 cr PAT per day' (Rs 365 cr) — group or company-level? Will KP Energy have its own concall?

    Answer, Salim Yahoo, Chief Financial Officer. KP Energy understanding confirmed. Rs 365 cr PAT/day target is a group-level vision, already achieved at group. KP Energy listing on NSE on 14 Nov; will have its own concall.

  20. 20. KP Energy contract specifics

    Nayan Shah, Individual Investor

    Question. Value and execution timeline of the order subcontracted to KP Energy?

    Answer, Salim Yahoo, Chief Financial Officer. Order is KPI's own IPP capex (hybrid wind+solar), executed by KP Energy as EPC contractor. Exact value not finalized pending financial closure; substantial in nature with possibly some panels purchased directly by KPI. Execution timeline 1.5 years for the entire hybrid project.

    Not answered directly.

  21. 21. Related-party rationale & IPP pipeline

    Lehar Jain, Giriraj Infocom India Private Limited

    Question. Are financial constraints forcing related-party subcontracting? Will KPI be unable to bid for IPP going forward and see profitability decline over 3 years?

    Answer, Salim Yahoo, Chief Financial Officer. Not financial constraints — capex will have both equity and phased debt, no constraint. KP Energy chosen for timeline efficiency and hybrid expertise. IPP bidding paused only because current hands are full; once current order completes (1-1.5 yrs) and balance-sheet leverage review done, will resume aggressive IPP bidding. Bulk NTPC orders are typically CPP anyway; discom (GUVNL) and C&I handle IPP.

  22. 22. Milestone revenue & merchant sale flexibility

    Pavan, Fident

    Question. Revenue booking at various milestones? Under GUVNL PPA, can units be sold on merchant basis before full commissioning?

    Answer, Salim Yahoo, Chief Financial Officer. Milestone plan: full 1.2 GW within 1-1.5 years. CPP 1.1 GW to close by September 2025. On GUVNL merchant sale: unless entire plant is commissioned and PPA allows, no merchant sale permitted.

    Partly answered.

  23. 23. Subsidiary progress

    Akhilesh Kumar, Adpro Technologies

    Question. Status of subsidiary absorbed from promoter (Sun Drops Energia / Kpark Sunbeat) — any contribution yet?

    Answer, Salim Yahoo, Chief Financial Officer. Subsidiary taken for its 100+ MW evacuation approval and land bank. 10 MW plant already commissioned; additional plants being set up. Land was in the books of Kpark Sunbeat (subsidiary).

What was said

Topic by topic, in the order it was spoken

Welcome & MD Apology · Siddharth Thakur (EA to MD)

  • MD Dr. Faruk Patel could not attend due to another engagement but expected to join later
  • CFO Salim Yahoo to lead the call and address all questions in the interim
  • Set the agenda: H1 FY25 financial overview followed by strategic growth updates before opening Q&A

H1 FY25 Financial Highlights · Salim Yahoo (CFO)

  • Total revenue from operations at Rs 711.3 cr, up 75% YoY from Rs 406 cr in H1 FY24
  • EBITDA grew 87% to Rs 266.9 cr vs Rs 142.5 cr, reflecting efficient operations and cost management
  • PAT doubled to Rs 135.9 cr vs Rs 68 cr (100% growth); basic EPS at Rs 11.03 (up 76% from Rs 6.27)
  • Net debt zero on standalone basis as of 30 September 2024 — a key milestone for the half-year

Business Updates & Strategic Initiatives · Salim Yahoo (CFO)

  • IPP segment: 171 MW installed, 1.26 GW order book — the largest in company history
  • CPP segment: 336 MW installed, 1.148 GW order book; both segments show strong execution capability
  • Technology adoption: single-axis solar trackers, bifacial panels, AI-driven robotic cleaners to maximize generation
  • Cumulative CO2 emissions reduction of 43,69,449 tons via green energy projects

Outlook & Future Plans · Salim Yahoo (CFO)

  • 10 GW installed capacity target by 2030, driven by mix of IPP and CPP projects
  • Geographic diversification: Maharashtra MAHAGENCO project in execution; plans for Rajasthan and Andhra Pradesh
  • International expansion in nascent stage — inquiries received from multiple geographies
  • Sustainability remains core to strategy; future focus on stakeholder value enhancement

In their words

Our installed IPP capacity as of H1 FY25 is 171 MW. And we have orders in hand for IPP of around 1.26 gigawatts, which is the biggest order book till date in the KPI's book.
Salim Yahoo (CFO, KPI Green Energy)
One of the biggest achievements of KPI in this particular half year was the net debt zero on standalone basis. So, KPI as on 30th September was net debt zero. So, there was no outstanding debt.
Salim Yahoo (CFO, KPI Green Energy)
KPI is one of the players who has more than a decade of experience, whether it is wind, whether it is solar. So, very few player has these kinds of capabilities, both wind and solar, and we have those capabilities... it is one of the strong executor.
Salim Yahoo (CFO, KPI Green Energy)

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Mon 11 Nov 2024₹502.45−4.79%−0.03%
5 sessions Mon 18 Nov 2024₹517.85−1.88%−2.88%
20 sessions Tue 10 Dec 2024₹538.80+2.09%+1.91%

From the close of Fri 8 Nov 2024, ₹527.75: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

KPI Green Energy's other calls

  • Q2 FY27Fri 13 Nov 2026Tone: Mixed
  • Q1 FY27Wed 12 Aug 2026Tone: Mixed
  • Q4 FY26Tue 12 May 2026Tone: Confident
  • Q3 FY26Wed 28 Jan 2026Tone: Confident
  • Q2 FY26Tue 11 Nov 2025Tone: Confident
  • Q1 FY26Wed 6 Aug 2025Tone: Confident
  • Q4 FY25Mon 19 May 2025Tone: Confident
  • Q3 FY25Tue 11 Feb 2025Tone: Confident