KPI Green Energy Q1 FY26 earnings call
In brief
KPI Green Q1 FY26: revenue Rs 614 cr (+75% YoY), PAT Rs 111 cr (+68%); targets 60-70% growth; plans Rs 700 cr green bond.
- Management's tone
- Confident
- What was said
- Leaned positive
- Guidance
- Guidance held
- Analyst pushback
- Low
- Stock, next session
- −0.08% (Nifty 50 −0.31%)
- Revenue Rs 614 cr (+75% YoY), EBITDA Rs 217 cr (+64%), PAT Rs 111 cr (+68%); basic EPS Rs 5.28 (+44%); cash profit Rs 163 cr (+92% YoY).
- Three IPP projects under execution worth Rs 5,000 cr (250 MW solar, 370 MW hybrid, 150 MW wind); targeted for phased completion by September 2026.
- Plans Rs 700 cr green bond (AA+ by CRISIL, backed by Garenco AAA); current debt-equity 0.5:1, expected to stay below 2:1 even after NCD and capex.
- Signed three MOUs with Delta Electronics covering BESS, green hydrogen, EV charging infrastructure and advanced solar PV inverters; subsidiary Sun Drops Energia to be IPO vehicle for BESS.
- BESS tender pipeline of Rs 3,000-4,000 cr targeted for bidding in H2 FY26 across Gujarat, Maharashtra, Rajasthan and Andhra Pradesh.
An AI read of the company's transcript · the filing
The numbers
The quarter, Q1 FY26
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹603 cr | +73.3% | +5.9% | |
| EBITDA (excl. other income) | ₹206 cr | +57.5% | +27.7% | 34.1% (37.5% a year ago) |
| Net profit | ₹104 cr | — | +4.9% | 17.2% (0% a year ago) |
| EPS (₹) | ₹5.28 | −51.9% | +4.8% |
From the company's filed results for the quarter ended 30 Jun 2025 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.
Where management's figures differ from the filing
- EBITDA: said Rs 217 cr, +64% YoY (CFO commentary); filed Rs 205.72 cr ex other income, +57.5% YoY. Stated figure appears to include other income of Rs 11.18 cr; filed definition excludes other income.
- PAT (net profit to owners): said Rs 111 cr, +68% YoY; filed Rs 103.95 cr, margin 17.2%. Gap of ~6.8% between stated and filed PAT not explicitly reconciled on the call.
What moved the numbers, as management explained it
- Strong execution across IPP and CPP segments delivered 5th consecutive record quarter, with revenue +75% YoY versus prior-year base of Rs 350 cr.
- PAT growth of 68% YoY outpaced EBITDA growth of 64% YoY, indicating finance cost discipline and annuity contribution from IPP portfolio.
- 250 MW solar and 370 MW hybrid projects were redesigned from tracker-based to fixed-tilt (1:1.4 AC-DC) due to land bifurcation, raising project cost but lifting PLF and IRR.
- 240 MW and 92 MW of new IPP capacity were energised this quarter but COD of GSS substation awaited by September, so generation impact from new capacity deferred to Q3 onwards.
- EPS grew only 44% despite PAT growth of 68%, implying share count expansion from prior fundraising rounds, partially diluting per-share growth.
- Mix shift in Q1 toward service component in milestone billing lifted margins transiently versus prior quarters, with CFO flagging seasonal rotation between service and supply components.
Guidance
Guidance on this call
| What | For | What management said | Filed |
|---|---|---|---|
| Topline growth | FY26 | Topline growth guidance band of 50% to 70% reiterated; CFO expects to touch the guidance given by Chairman. | 55.3%, within the range |
| Topline growth FY27 | FY27 | Indicated 60% growth from FY26 base into FY27. | — |
| PAT margin | FY26 | PAT margin to be maintained in the 16% to 18% range. | 17.7%, within the range |
| IPP EBITDA margin | — | IPP EBITDA margin of 75% to 80%. | — |
| CPP EBITDA margin | — | CPP EBITDA around 20%. | — |
| Blended EBITDA margin | — | Blended EBITDA around 30% to 32%. | — |
| IPP share of revenue (FY26 end) | FY26 | IPP share of revenue to move up to 17% to 18% by end of FY26. | — |
| IPP share of revenue (long-term target) | — | Long-term target IPP share of revenue at 25% of total, balance 75% CPP. | — |
| IPP project completion | — | 1.2 GW of IPP capacity (250 MW solar + 370 MW hybrid) targeted for phased completion by September 2026. | — |
| Capacity to commission in FY26 (IPP) | FY26 | At least half of 1.2 GW new IPP capacity targeted to commission in FY26. | — |
| Debt-equity ratio ceiling | — | Debt-equity ratio to remain below 2:1 even after NCD and projects, versus industry levels of 5-7x. | — |
| Green bond issuance | — | Rs 700 cr green bond being raised; CFO ballpark rate around 8.8%. | — |
| IPP average revenue realisation | — | Average IPP revenue realisation around Rs 3.5 to Rs 3.6 per unit, with Rs 3/unit targeted for 10 GW portfolio. | — |
| BESS bid pipeline (H2 FY26) | H2 FY26 | Bid pipeline of Rs 3,000 to Rs 4,000 cr for BESS tenders in H2 FY26. | — |
Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.
Guided on earlier calls, and what was filed
| What | For | Guided | Filed |
|---|---|---|---|
| Consolidated revenue growth | FY26 | 60–70% (on the Q4 FY25 call) | 55.3%, below the range |
Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.
The business
By business
IPP (Independent Power Producer)
Installed and upcoming IPP capacity 1.7 GW including 503 MW existing; three projects worth Rs 5,000 cr under execution with phased completion to September 2026; GUVNL PPAs of 25 years.
IPP capacity 1.7 GW installed + upcoming · Project execution size Rs 5,000 cr · EBITDA margin 75-80% · Average realisation Rs 3.5-3.6/unit · Generation 6.9 crore units this quarter
Outlook: IPP share of revenue targeted at 17-18% by FY26 end and 25% long-term; half of 1.2 GW new capacity to commission in FY26.
CPP (Captive Power Producer)
Installed and upcoming CPP capacity 2.3 GW; order book 1.8 GW valued at ~Rs 4,000 cr; contribution 86-87% of revenue last year.
CPP capacity 2.3 GW installed + upcoming · Order book 1.8 GW (~Rs 4,000-4,200 cr) · EBITDA margin ~20% · Revenue share 86-87% last year
Outlook: CPP to grow alongside IPP on 60-70% revenue growth target; revenue billed on milestone basis.
BESS (Battery Energy Storage)
New business line routed via subsidiary Sun Drops Energia; three MOUs with Delta Electronics for technology; targeted bid pipeline of Rs 3,000-4,000 cr in H2 FY26.
Tender pipeline Rs 3,000-4,000 cr to bid in H2 FY26
Outlook: Sun Drops Energia DRHP filing in process; subsidiary IPO planned; focus initially on smaller projects (0-35 MW) and bigger projects (35-100 MW) at KPIG Energia.
Group EPC and platforms
EPC execution leveraging sister concerns under KP Group; 108 project sites; OMS, NOC and robot cleaning facilities; 5.9 GW executed plus upcoming portfolio requiring 500+ cleaning robots.
Project sites 108 · Power evacuation 3.2 GW · Land bank 6,275 acres · Workforce 800-900 (560 in KPI standalone)
Outlook: Long-term portfolio target 10 GW; new subsidiaries being formed for evacuation in additional states; international opportunities under discussion.
Balance sheet, capex and funding
- Debt-equity ratio at 0.5:1 currently; expected to remain below 2:1 even after Rs 700 cr NCD and project capex, well below industry level of 5-7x.
- Rs 700 cr green bond issuance in process; rated AA+ by CRISIL, guaranteed by parent Garenco (AAA); CFO targeting rate around 8.8%.
- Land bank of 6,275 acres supporting 3.2 GW of blocked evacuation capacity across 108 project sites.
- Cash profit Rs 163 cr in Q1 FY26, +92% YoY, reflecting annuity income from IPP portfolio.
- No equity dilution expected over next 2-3 years to maintain debt-equity band; promoter holding ~48.70% stable.
- Subsidiary Sun Drops Energia IPO planned; pre-IPO done, DRHP being filed to fund BESS capex needs.
The industry, as management sees it
Management views the sector trajectory as intact despite the sunset of ISTS charge benefits — India still needs 45 GW to be tendered/bid to meet 500 GW non-conventional capacity target by 2030. Policy is moving from conventional to non-conventional power, and Gujarat government has separately committed Rs 1 lakh cr to transmission over five years, supporting renewable build-out. KPI Green is insulated from ISTS policy changes as it does not participate in ISTS tenders.
Risks management named
- Land and evacuation availability are the two main execution hurdles
- Seasonality in Q2 due to monsoon impacts execution run-rate
- Cost shift from tracker-based to fixed-tilt design (AC-DC 1:1 to 1:0.4) raised project cost but PLF also higher, keeping IRR intact
- Government transmission infrastructure growth not keeping pace with renewable capacity build-out (industry-wide)
Q&A
Q&A was dominated by KPI/Sun Drops retail investors and a couple of institutional analysts (Anand Rathi, DB Wealth, Equitree Capital). Discussion clustered around: (1) reaffirmation of 50-70% topline growth and 16-18% PAT margin guidance, (2) the 1.2 GW IPP execution roadmap and design-driven cost detail, (3) BESS go-to-market via Sun Drops Energia with Delta Electronics partnership, and (4) capital structure/green bond terms. No aggressive pushback — the only probing was on the cost-escalation/IRR mechanism and CPP/EBITDA breakdown, both of which management addressed with specifics.
Not answered directly
- CPP installed capacity by March 2026 — management cited milestone-based booking as reason for not committing to a number
Asked for a number, answered without one
- BESS revenue and order book targets: CFO said tender pipeline of Rs 3,000-4,000 cr to bid for in H2 FY26 across Gujarat, Maharashtra, Rajasthan and Andhra Pradesh, but did not specify committed orders or revenue target.
- BESS project margins: CFO said BESS is an evolving business and margins would be tracked closely, with healthy margin preferred; no specific margin figure provided.
- Green bond coupon rate: CFO indicated ballpark around 8.8% but said rate not yet decided; actual pricing pending market process.
- Revenue potential from 10 GW portfolio target: CFO indicated 25% IPP / 75% CPP mix and average realisation of Rs 3/unit for IPP; no total revenue figure or timeline given.
- Workforce target for FY26: CFO said current workforce 800-900 (560 in KPI standalone) but declined a specific headcount target, focusing on revenue per person metric instead.
Every question, with its answer
1. Pledge share release with SBI
Manav, Investor
Question. Any update on the SBI pledge release process that was discussed in the December con-call? Loan had been repaid, and management was in talks with SBI to release the pledge.
Answer, Salim Yahoo, Chief Financial Officer. Request letter already sent to SBI; verbally given green signal, only pending board approval. SBI is one of the largest exposure for KPI in Surat. Estimated timeline: constructive approvals expected by next quarter, with formalities to follow after board sanction. Management 'gung-ho' that SBI board will approve.
Follow-up. Any tentative timeline?
Answer. CFO said he cannot control SBI's board meeting calendar; assured constructive approvals and sanctions by next quarter, with formalities to follow after.
Partly answered.
2. ISTS policy impact and FY26 guidance
CA Garvit Goyal, Nvest Analytics Advisory LLP
Question. Sector-level: any change in government stance on ISTS charges waiver that could negatively impact KPI Green's order inflows in near to medium term? Will the company easily outperform its 50-70% topline growth guidance?
Answer, Alok Das, Group CEO. ISTS charges benefit sunset in June 2025 with trajectory of 100% -> 75% -> 50% for projects beyond 2025. KPI is not participating in any ISTS projects today, so fully insulated. On guidance: Q1 itself delivered 60-70% growth across revenue and profitability parameters; confident of touching the 50-70% guidance given by CMD earlier.
3. Q2 seasonality, PAT margins, risk inventory
Deekshant B., DB Wealth
Question. Three questions: (1) Q2 execution run-rate given heavier monsoon; (2) PAT margins going forward as IPP ramps up; (3) What internal risks does management see that could go wrong?
Answer, Salim Yahoo, Chief Financial Officer. (1) Rainy season does see lower execution sector-wide, but supply components can be built; Q2 will be in line with prior year Q2, with slight curtailment covered later. (2) IPP EBITDA is 85-90% on upcoming projects; PPA rates fixed, so PAT margin sustain-able at 15-20% (currently 16-17%). (3) Major risks are land availability and evacuation; KPI has 3+ GW evacuation approvals and 6,000+ acres land bank, so hurdle probability very low (95-96%+ success). 25-year PPAs with GUVNL (A-rated) eliminate off-take risk. KPEL call scheduled next day for sister-company update.
4. IPP cost/design change, large order pipeline, BESS vehicle
Ashish Rampuriya, Investor
Question. Three questions: (1) ICRA rating report flagged Rs 700 cr cost escalation on one IPP — reason? Will it improve IRR? (2) Update on large order wins that should take care of FY28 revenue. (3) BESS strategy: will KPI Green be the vehicle?
Answer, Salim Yahoo, Chief Financial Officer. (1) Not cost escalation — design change. Initial design was tracker-based with 1:1 AC-DC; land bifurcation forced shift to fixed design with 1:0.4 AC-DC to maintain PLF. Fixed gives PLF 19-20% vs tracker 23% but more panels mean higher absolute generation. IRR will slightly improve. (2) Orders in hand: 3 GW+; CPP order book 1.8 GW (~Rs 4,000 cr); 150 MW GUVNL wind added; 80-90% win rate expected on BESS tenders this quarter. (3) BESS will primarily be housed in subsidiary Sun Drops Energia; KPI Green will only take on very large utility-scale BESS with marquee institutions. Consolidation happens at KPI Green level.
5. Subsidiary structure and Sun Drops Energia listing plan
Akhilesh Kumar, Investor
Question. Why so many subsidiaries doing the same EPC business? Was a subsidiary being planned to be listed separately?
Answer, Salim Yahoo, Chief Financial Officer. Subsidiary structure (vs SPV) is industry standard (Adani, Mahindra Renewables, Aditya Birla all use it) for capital-intensive ring-fenced financing. KPI major subs: KPIG Energia, Sun Drops, K Park, Miyani. Demarcation: 0-35 MW projects in Sun Drops; 35-100 MW in KPIG Energia; larger utility-scale with GUVNL/CIL in KPI Green. Sun Drops Energia is the subsidiary planned for separate listing; DRHP filing process has begun after a small pre-IPO. Also rebuffed the 'cost escalation' framing again, calling it a 'design change' (BMW vs Mercedes analogy). Took feedback to add a group-level slide to PPT.
6. IPP and CPP execution timeline and order book value
Gaurav Sharma, GS Enterprises
Question. Timeline for completion of 1.2 GW IPP and 1.8 GW CPP order book; what is the CPP order book value?
Answer, Salim Yahoo, Chief Financial Officer. 1.2 GW IPP targeting September 2026 (250 MW solar + 370 MW hybrid AC, equating to 350 MW DC and 679 MW DC). CPP order book 1.8 GW = Rs 4,000+ cr (Rs 4,100-4,200 cr) — all unbilled, to be billed on milestone basis with service and supply components. Hard to linearly convert into revenue due to milestone mix.
7. Operational disclosure and IRR mechanism for fixed-tilt design
Anil Sarin, K16 Advisors
Question. Suggestion to add operational data (MW delivered in quarter, CPP vs IPP revenue breakup) to PPT. Further: if cost goes up while revenue/PPA stays the same, why won't IRR suffer?
Answer, Salim Yahoo, Chief Financial Officer. Took feedback on operational disclosure for next quarter. On cost/IRR: PPA allows 15-20% over and above contracted PLF; fixed design's higher panel count (1:0.4) generates more units, increasing revenue; PLF of 19-20% on fixed basis with more panels yields higher total generation and revenue than tracker at 23% with 1:1 ratio, so IRR maintained despite higher capex.
8. 10 GW portfolio revenue model, IPP/CPP mix, EBITDA volatility
Kartik Sharma, Anand Rathi Institutional Equities
Question. Revenue potential from 10 GW portfolio target; split between IPP and CPP at maturity; per MW realization for IPP vs CPP? EBITDA margins down YoY — drivers and stabilization approach?
Answer, Salim Yahoo, Chief Financial Officer. Current IPP/CPP revenue mix: 12-13% IPP / 86-87% CPP. 10 GW target envisages 25% IPP / 75% CPP. Average realization ~Rs 3.5-3.6/unit on existing IPP; aim to maintain ~Rs 3/unit going forward. EBITDA margin volatility: seasonality between service component (higher margin) and supply/material component (lower margin) — typical Q1 service-heavy skew. Blended PAT margin to settle at 16-18%.
9. Green bond pricing and BESS market entry economics
Hardik Gandhi, HPMG Shares and Securities Private Limited
Question. Rate of new green bonds being issued; BESS revenue/order book target and execution timeline/margins?
Answer, Salim Yahoo, Chief Financial Officer. Green bond: AA+ rating from CRISIL secured; bond guaranteed by Garenco (AAA), so expecting best possible rate. CFO's ballpark: ~8.8% given current market. BESS: target 18-24 month execution timeline; margins to be tracked but 'healthy' — won't compromise too much; 1-2 years of business evolution expected. Bid pipeline Rs 3,000-4,000 cr across Maharashtra, Gujarat, Rajasthan, Andhra Pradesh, with tenders expected in H2 FY26.
Partly answered.
10. BESS technology, robot cleaning commercialization, Sun Drops listing structure
CA Garvit Goyal, Nvest Analytics Advisory LLP
Question. Follow-up on BESS — in-house or partner technology? Will solar panel robot cleaning be sold externally? On Sun Drops listing — will existing KPI Green investors get subsidiary shares to avoid EPS dilution?
Answer, Salim Yahoo, Chief Financial Officer. BESS technology: collaborated with Delta Electronics for latest BESS technology. Robot cleaning: 500+ robots installed (up from 180 in Q4); fulfilling internal requirement first; commercialization to be decided by management. Sun Drops: pre-IPO done with KPI as majority; listing will dilute 25% in open market; no SEBI-mandated shareholder quota; KPI will retain 51%+ post-listing, so still consolidated.
11. Combined tender pipeline, new state subsidiaries, ISTS evacuation, international plans
Ashish Rampuriya, Investor
Question. Follow-ups: Rs 3,000-4,000 cr is BESS pipeline — what's the solar/hybrid pipeline? 4 new subsidiaries announced — what for? Progress on 600+ MW ISTS evacuation? Updates on other states and international?
Answer, Alok Das, Group CEO. Solar/hybrid bid pipeline: another Rs 4,000-5,000 cr at any time, making total addressable ~Rs 8,000-9,000 cr (caveat: these are targets to bid, not confirmed orders). New subsidiaries: separate companies formed to secure evacuations in different states. ISTS evacuation: 642+ MW secured, with various discussions in pipeline. Other states: MOUs signed in three states for farming domain; land and evacuation being arranged. International: under discussion, nothing to disclose now.
Partly answered.
12. 1.2 GW IPP phasing, installed capacity, unit generation ramp
Soham, RV Investments
Question. 1.2 GW IPP — added in one go or phased? By FY26 end, what installed IPP capacity? What will be the IPP share of revenue at 60-70% topline growth? Unit generation from current 500 MW?
Answer, Salim Yahoo, Chief Financial Officer. 1.2 GW IPP: phased addition starting this financial year. FY26 end target: at least half of 1.2 GW commissioned (so total IPP 1.0-1.1 GW by Mar 2026). Long-term IPP share target: 25%; expected 17-18% by FY26 end. Last year Q1 IPP capacity 171 MW; new 240 + 50 MW capacity energized in Q1 but COD of GSS substation only by Sept 2025, so Q1 generation of 6.9 cr units was from 171 MW only. By year end: ~35 cr additional units expected from 240 + 92 MW once commissioned.
13. Capacity utilization, per MW economics, segment-level EBITDA
Shubhankar Gupta, Equitree Capital
Question. Of 1 GW installed capacity, how much is utilized? CPP vs IPP revenue per MW economics? EBITDA back-calculation: IPP at 75-80% means CPP at 20%?
Answer, Salim Yahoo, Chief Financial Officer. Q1 utilization: 171 MW energized and generating revenue; total IPP 504 MW but 240+92 MW energized only in Q1 (revenue from Q3). Per MW economics: order book 1.8 GW = Rs 4,000+ cr is a mix of with-panel and BOP-only orders (Aditya Birla order is BOP without panels). Solar: ~Rs 3.25-3.75 cr per MW; wind: Rs 7-7.5 cr per MW. Refused to disclose IPP per MW margin. EBITDA: IPP 75-80%, CPP ~20%, blended 30-32%.
Partly answered.
14. Debt/equity level and capex funding plan
Akhilesh Kumar, Investor
Question. Current debt level and post-NCD debt/equity ratio — will it stay at 1.5? Will further equity raise be needed?
Answer, Salim Yahoo, Chief Financial Officer. Current debt/equity 0.5:1 (very low leverage). With NCD and upcoming capex, will not cross 2:1 — comfortable. Industry is at 5-7x. No equity dilution needed from promoters in near term; profitability accretion to net worth will offset debt growth. Will keep levels below 2:1 for next 2-3 years.
15. CPP capacity build by FY26 end
Gaurav Sharma, GS Enterprises
Question. What CPP capacity can be installed by March 2026?
Answer, Salim Yahoo, Chief Financial Officer. Difficult to commit to exact installed CPP capacity by March 2026 due to milestone-based execution; 1.8 GW is order book in hand. Revenue growth 60-70% in FY26 indicates strong execution. Capacity is booked only on project completion.
Not answered directly.
16. FY27 growth and margin outlook
Ajit Sethi, Eiko Quantum Solutions
Question. Revenue growth target for FY27? PAT margins assumption?
Answer, Salim Yahoo, Chief Financial Officer. FY27: 60% growth assumed (last year Rs 1,700 cr base; 60% from FY25 to FY26, then 60% from FY26 to FY27). PAT margin to be maintained at 16-18%.
17. Net profit margin sustainability and workforce
Samrat Shah, Investor
Question. If IPP share rises from 13% to 17-18% (target 25%), shouldn't net profit margin expand rather than just be maintained? Current workforce and target?
Answer, Salim Yahoo, Chief Financial Officer. PAT margin maintenance, not expansion, because CPP (60-70% growth) will simultaneously grow alongside IPP, offsetting the mix benefit. CPP EBITDA ~20% vs IPP 75-80%, so net effect is stabilization at 16-18%. Workforce: 800-900 total; 560 in KPI Green alone; growing year-on-year; no fixed target — focus is on revenue per person rather than headcount.
18. Evacuation/land sufficiency, promoter holding, DII engagement
Deekshant B., DB Wealth
Question. 3 GW evacuation and 6,000 acres land bank — is this inclusive of September 2026 project execution? Is promoter holding stable for 2-3 years? Suggestion to do more DII roadshows given good FII presence but limited DII holdings.
Answer, Salim Yahoo, Chief Financial Officer. 3.2 GW evacuation and 6,275 acres land bank is inclusive of September 2026 execution; real-time acquisition continues. Promoter holding 48.70% and stable for next 2-3 years. On DII: DII holdings do exist but largely FII-dominated (Vanguard, BlackRock noted as marquee investors); Rs 700 cr NCD fund raise is targeting insurance companies and DIIs; will scale DII engagement as size grows.
19. BESS BOO capital intensity and Sun Drops IPO rationale
Suman Kumar, Investor
Question. On BESS BOO model — if revenue target is Rs 3,000 cr, will KPI need to invest the entire amount upfront and recover from utility?
Answer, Alok Das, Group CEO. Yes — BOO model requires KPI to own the BESS asset. Capital investment upfront, recovered via service revenue from utility. This is precisely why Sun Drops Energia IPO is being planned — to raise dedicated equity for BESS capex. Sun Drops currently has low debt; will leverage as orders execute. Asset sits on Sun Drops books, consolidated into KPI.
20. Gensol re-bid and competitive intensity
Rishabh Chaudhary, Investor
Question. On industry: government re-bidding of tenders that went to Gensol — is KPI participating?
Answer, Salim Yahoo, Chief Financial Officer. Recent re-bids have come at very low prices; KPI participated but not aggressively. The NTPC tender previously won by Gensol has been re-bid and awarded to Sterling and Wilson — open market information.
21. Transmission infrastructure readiness and panel pricing
Akhilesh Kumar, Investor
Question. Industry reports suggest 25% of projects in Gujarat and other states stuck due to transmission line delays. Is evacuation infrastructure already in place for KPI? And how are panel prices trending given India-only sourcing?
Answer, Faruk Patel, Chairman & Managing Director. 3.2 GW evacuation is already in place — substation capacity pre-allocated to KPI; BESS substation line drawn to GSS already. Gujarat government has planned Rs 1 lakh cr investment in transmission over five years; central government also investing heavily. KPI has secured evacuation 2-3 years ahead, so not impacted. GETCO has 1-2 year lead time; discom-side issues are minor. On panels: 1.7 GW of panel capacity already hedged at current rates; all Indian manufacturers; insulated from price moves.
What was said
Topic by topic, in the order it was spoken
Company Introduction & Positioning · Siddharth Thakur (CMD Office, KP Group)
- KPI Green positioned at the forefront of India's fast-growing renewable energy transition industry
- Company incorporated in 2008, leveraging EPC expertise built over 15+ years
- Part of KP Group, with sister companies providing complementary capabilities
- State-of-the-art OMS (Operations Management System), NOC, and robot cleaning facilities integrated into project execution
- Mission framed as 'building a cleaner tomorrow' and contributing to national sustainability goals
Q1 FY26 Financial Performance · Salim Yahoo (CFO)
- Total revenue Rs 614 cr, up 75% YoY from Rs 350 cr in Q1 FY25
- EBITDA Rs 217 cr, up 64% YoY
- PBT Rs 149 cr, up 64% YoY from Rs 91 cr
- PAT Rs 111 cr, up 68% YoY from Rs 66 cr; basic EPS Rs 5.28 vs Rs 3.66 (44% growth)
- Cash profit Rs 163 cr, strong 92% YoY growth
- Fifth consecutive quarter of highest-ever revenue, driven by strong execution, customer trust, and IPP + CPP expansion
IPP Project Pipeline & Revenue Visibility · Salim Yahoo (CFO)
- Three major IPP projects under execution: 250 MW solar (350 MW DC), 370 MW hybrid (679 MW DC), 150 MW standalone wind
- Total execution size Rs 5,000 cr; targeting phased completion by September 2026
- Part commissioning and revenue recognition expected to begin within next few quarters
- All projects backed by 25-year long-term PPAs with GUVNL — one of the best-rated discom paymasters
- Annuity income from growing IPP portfolio cited as key margin and visibility driver
Strategic Developments & Capacity Snapshot · Salim Yahoo (CFO)
- Received LOI from GUVNL for 150 MW grid-connected wind project, bolstering hybrid pipeline
- Three MOUs signed with Delta Electronics India for BESS, green hydrogen, EV charging infrastructure, and advanced solar PV inverters
- Installed + upcoming IPP capacity: 1.7 GW; CPP capacity: 2.3+ GW; cumulative portfolio: 4 GW
- Land bank: 6,275 acres; power evacuation capacity: 3.2+ GW; orders in hand exceed 3 GW
- Presence across 108 project sites in multiple discoms and CTUs; IBM Maximo Renewables NOC for real-time monitoring
Closing Remarks & Management Commitments · Sohil Dabhoya (Whole-Time Director) and Faruk Patel (CMD)
- Sohil Dabhoya thanked investors and reaffirmed commitment to 'growing with purpose'
- Faruk Patel joined late after TV interview, reinforced evacuation/transmission capacity advantage
- CMD committed to better outcomes in next con-call and stable promoter holding for next 2-3 years
- Pledged share release with SBI remains in process, with management expecting SBI board approval by next quarter
- KP Group cross-pollination across KPI, KPIG Energia, Sun Drops Energia, and K Park subsidiaries reiterated
In their words
we are pleased to report yet another record-breaking quarter, making our fifth consecutive quarter of highest-ever revenue, driven by strong execution, customer trust, and continued expansion across both our IPP, that is independent power producer, and CPP, that is captive power producer segments.
we are quite confident that we will be able to touch the guidance which was given by our Chairman & Managing Director, Dr. Faruk sir... we will be able to achieve that most part.
I looking forward the next con-call and I giving you the promise that you will be very happy in next con-call more than this quarter and that is my promise to you people and we are doing the work.
To check next time
What management committed to on this call, or the dates they gave.
- SBI board approval and timeline for release of pledged shares, with CFO targeting constructive approvals by next quarter.
- Phase-wise commissioning of 250 MW solar and 370 MW hybrid IPP projects; CFO targeting half of 1.2 GW capacity in FY26.
- COD of GSS substation for 240 MW + 92 MW new IPP capacity, expected by September 2025, unlocking generation revenue from Q3.
- Progress on Sun Drops Energia DRHP filing for BESS-focussed subsidiary IPO.
- Final pricing and issuance of Rs 700 cr green bond; CFO ballpark around 8.8%.
- BESS tender awards in H2 FY26 from Rs 3,000-4,000 cr bid pipeline across multiple states.
Transcript
We have not transcribed this call's recording. Read the company's transcript (PDF).
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Wed 6 Aug 2025 | ₹532.05 | −0.08% | −0.31% |
| 5 sessions Tue 12 Aug 2025 | ₹514.85 | −3.31% | −0.66% |
| 20 sessions Thu 4 Sept 2025 | ₹489.35 | −8.10% | +0.34% |
From the close of Tue 5 Aug 2025, ₹532.50: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.