Maharashtra Seamless Q1 FY25 earnings call

Tue 30 Jul 2024MAHSEAMLES

In brief

Q1 FY25 EBITDA fell 54% QoQ to Rs.126 cr on lower realisations, a mill shutdown and an inventory markdown to reverse.

Management's tone
Mixed
What was said
Mixed
Guidance
None given
Analyst pushback
High
Stock, next session
−1.85% (Nifty 50 +0.09%)
  • EBITDA fell 54% QoQ to Rs.126 cr, PAT 40% to Rs.136 cr and EPS 40% to Rs.10, with revenue down 4% QoQ.
  • Management put equal weight on three causes: lower sales realisation, a preventive mill shutdown and an inventory markdown.
  • EBITDA per tonne fell from Rs.22,000 to Rs.9,000; the inventory markdown is to reverse once high-value orders are dispatched.
  • Telangana finishing line completion deferred by at least nine months to around December 2025; no volume growth expected in FY25.
  • Order book rose to Rs.1,812 cr from Rs.1,754 cr; 51% is from ONGC and Oil India, and treasury stood at Rs.2,203 cr.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q1 FY25

This quarterA year agoLast quarterMargin
Revenue₹1,151 cr−5.9%−5.3%
EBITDA (excl. other income)₹124 cr−49.0%−53.9%10.8% (19.9% a year ago)
Net profit₹129 cr−37.4%−40.8%11.2% (16.9% a year ago)
EPS (₹)₹9.65−37.4%−40.8%

From the company's filed results for the quarter ended 30 Jun 2024 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

Where management's figures differ from the filing

  • PAT (Q1 FY25): said PAT Rs.136 crores, down 40% QoQ; filed Net profit to owners ₹129.27 cr. Management's headline PAT exceeds filed net profit to owners; no reconciliation and no standalone or consolidated basis was stated.
  • EPS (Q1 FY25): said EPS Rs.10 per share; filed EPS ₹9.65. EPS stated on the call is above the filed EPS; management did not reconcile the difference or state the basis.

What moved the numbers, as management explained it

  • Sales realisation fell on increased competition, lower raw material prices and Chinese dumping; EBITDA per tonne fell from Rs.22,000 to Rs.9,000.
  • Preventive maintenance shutdown in one mill cost around 15,000 tonnes of production; the mill restarted in the first week of July 2024.
  • Undispatched high-value orders left earmarked inventory marked down to lower quarter-end raw material prices to comply with accounting standards; management says it reverses on dispatch. (one-off)
  • ERW dispatch mix was about 20% oil and gas and 80% water in Q1 FY25, which management said lowered ERW margins.
  • Management attributed the rise in other expenses, put at around Rs.16 crores by the analyst, to the preventive maintenance shutdown.
  • March quarter dispatches of around 95,000 tonnes were hit by an order expected in March but received in the second week of April, affecting the comparison base.

The numbers management led with

  • Treasury balance: Rs.2,203 crores as on 30 June 2024
  • Order book: Rs.1,812 crores (up from Rs.1,754 crores)
  • EBITDA per tonne: Fell from Rs.22,000/tonne to Rs.9,000/tonne in Q1 FY25
  • Capital expenditure plan: Rs.852 crores from FY24 to FY26; minimal in FY24, marginal in FY25, majority in FY26

Guidance

Guidance on this call

WhatForWhat management said
Announced capital expenditure planFY24-FY26Capital expenditure plan of 852 crores for FY24-FY26; management confirmed a major portion in FY26 and marginal spend in FY25
Telangana finishing line completion (Telangana unit)FY26Telangana finishing line completion expected by December 2025, deferred by at least nine months; not a hard stop
Volume growthFY25No volume growth expected in FY25
Volume growthFY26FY26 volume growth only once the Telangana finishing line is completed and open for commercial production
EBITDA per tonne normalisationQ2 FY25Inventory markdown to reverse as high-value orders dispatch, restoring a normalised EBITDA per tonne, hopefully in Q2 FY25
ERW EBITDA per tonne (ERW pipes)—ERW EBITDA per tonne generally between Rs.6,000 and Rs.11,000 plus or minus 1,000 at both ends, depending on product mix
Dispatch normalisationQ2 FY25Mill resumed production in the first week of July; normalisation of dispatches expected in the second quarter
ERW dispatch volume (ERW pipes)—ERW pipes dispatches to remain in the range of 80,000 to 1,05,000 tonnes every year, with no capacity expansion
Hot mill upgrade—Hot mill upgrade only after the Telangana finishing line is in place and running at full capacity
Sales realisation—Realisations not expected to fall further in a material manner beyond current levels

What changed since the Wed 22 May 2024 call

WhatOn the Wed 22 May 2024 callOn this call
Telangana finishing line completion (delayed)Telangana finishing line capex INR 184 cr targeted for completion in FY25Deferred by at least nine months, now expected to be completed by December 2025
Volume ramp from Telangana (delayed)Volume ramp in FY26 after the finishing line is installedNo volume growth in FY25; FY26 growth only once the line is completed and open for commercial production
Capex plan (restated)FY25 capex approximately INR 200 crores for modelling purposesRs.852 crore plan for FY24-FY26, with FY25 spend marginal and most spending in FY26
Seamless EBITDA per tonne (not repeated)Margins expected to remain above INR 15,000 per tonEBITDA per tonne fell to Rs.9,000 from Rs.22,000; no forward floor was reiterated
Order book (raised)INR 1,753 cr, 60% from ONGC and Oil IndiaRs.1,812 cr from Rs.1,754 cr; 51% ONGC and Oil India, 70-75% excluding ERW and Telangana
Treasury (raised)All-time high of INR 1,859 crRs.2,203 cr as on 30 June 2024
Shutdown production loss (held)~15,000 tons lost in Q1 FY25Confirmed around 15,000 tonnes; mill resumed in the first week of July
Dividend and buyback (restated)Dividend doubled to INR 10/share for FY24 vs INR 5/share for FY23FY24 dividend described as quadrupled versus FY22; no dividend or buyback update for the current year

The business

By business

Seamless pipes

Q1 FY25 earnings were hit by lower sales realisations, a preventive shutdown in one mill and an inventory markdown on undispatched high-value orders; 4 lakh tonnes made and dispatched.

EBITDA per tonne Rs.9,000 in Q1 FY25 vs Rs.22,000 · Production loss around 15,000 tonnes from the shutdown · Q1 FY25 manufacture and dispatch 4 lakh tonnes · Annual capacity 5,50,000 tonnes · Capacity utilisation generally 70% to 80% · Global seamless pipes market around 10 million tonnes · India seamless pipes market around 0.9 million tonnes

Outlook: Mill resumed in the first week of July 2024; dispatch normalisation and markdown reversal expected from Q2 FY25; realisations not expected to fall materially further.

Treasury

Treasury stood at Rs.2,203 crores at 30 June 2024, improved more than anticipated and was generating good returns; more than a third of Q1 earnings came from treasury.

Treasury Rs.2203 crores as on 30 June 2024 · More than 1/3rd of total earnings from treasury segment

Exports

Exports have not revived and have been slow for more than a year; the company does not export to the Middle East and sour service subsea inquiries have not converted into orders.

Outlook: Exports to remain slow; management sees no scope for supernormal margins in the Middle East given Chinese presence.

Telangana unit and capex

No significant capex was spent in Q1 FY25; equipment purchase orders were placed after negotiations ended, and the Rs.852 crore FY24-FY26 plan is back-ended with FY25 spend marginal.

Announced capex plan Rs.852 crores for FY24-FY26 · Equipment order gestation period 12 months · Completion expected by December 2025 after a deferral of at least nine months

Outlook: Finishing line expected by December 2025, not a hard stop; FY26 volume growth only after commercial production; hot mill upgrade follows Telangana.

ERW pipes

ERW dispatches were about 20% oil and gas and 80% water in Q1 FY25, which management said lowered segment margins; the segment contributes 6-7% of total EBITDA and is not being expanded.

ERW dispatches 80,000 to 1,05,000 tonnes every year · ERW contributes 6% to 7% of total EBITDA · Q1 FY25 mix around 20% oil and gas and 80% water · ERW EBITDA per tonne Rs.6,000 to Rs.11,000 plus or minus 1,000

Outlook: Dispatches to remain within 80,000-1,05,000 tonnes a year with no capacity expansion; per-tonne EBITDA depends on product mix.

Balance sheet, capex and funding

  • Treasury at Rs.2,203 crores as on 30 June 2024; no ICDs to unrelated entities and no corporate guarantees outstanding.
  • No significant capex expenditure in Q1 FY25; purchase orders placed for pending equipment with a 12-month gestation period.
  • Announced capex plan of Rs.852 crores for FY24-FY26, with a major portion now expected in FY26 and FY25 spend marginal.
  • Working capital: almost the entire order book is hedged with raw material; inventory bought for high-value orders was marked down as raw material prices fell.
  • Telangana finishing line completion deferred by at least nine months to around December 2025, back-ending capex phasing.

The industry, as management sees it

Capital goods and infrastructure spend in general, and oil & gas specifically, continue to see strong medium-term demand; this directly supports the seamless pipes market. Globally the seamless pipes market is ~10 million tonnes with India ~0.9 million tonnes; ONGC + Oil India alone offer ~100,000 tonnes/annum demand for exploration. Substitution risk from welded pipes remains limited to diameters above 22 inches which are outside the seamless product range.

Risks management named

  • Chinese dumping pressure on realisations in certain segments, with anti-dumping process being long-drawn
  • Inventory mark-down risk recurring if raw material prices fall against open order book exposure
  • Exports to US and Canada have not revived for over a year
  • Realisation downside if competitive intensity remains elevated despite raw material stability

Q&A

Q&A was dominated by three threads: (i) pressure on management to quantify the inventory markdown and explain raw material price collapse, which Bengani refused to put a number on; (ii) capex pacing where management deferred FY25 vs FY26 split detail to the next call and confirmed Telangana is delayed by at least 9 months; (iii) demand and export outlook where management conceded US/Canada exports have not revived for more than a year and refused to disclose subsea pipe geographies citing competition. A bullish subplot was treasury (>1/3 of earnings) and order book quality (51% ONGC + Oil India). The 'no problem in operations' closing was delivered against persistent analyst scepticism on the markdown quantum and capex deferral.

Not answered directly

  • Inventory markdown quantum in rupee terms
  • FY25 vs FY26 capex split under the Rs.852 cr plan
  • Segment-level impact of Chinese imports
  • Geography of sour service subsea pipe inquiries
  • Saudi / Middle East opportunity disclosure
  • Quantum of Chinese imports into India in tonnage

Asked for a number, answered without one

  • Inventory markdown amount: Management declined to quantify it, saying all three factors had equal weightage and the markdown would reverse when the orders are dispatched.
  • Capex split between FY25 and FY26: Management declined to split the plan now and said a definitive figure would be given in the next earnings call.
  • Capex spent in Q1 FY25: Management said there was no significant capex expenditure in the quarter and that purchase orders had been placed for certain equipment.
  • Chinese imports: affected segments and tonnage: Management declined to name the affected segments, saying it did not want to disclose, and did not quantify import tonnage.
  • US and Canada share of global demand: Management said it did not know, referring the analyst to databases and saying exact percentages were difficult to communicate.
  • ERW revenue for the coming year: Management gave a dispatch tonnage range of 80,000 to 1,05,000 tonnes a year instead of a revenue figure, noting no ERW capacity expansion.
  • Telangana unit production in Q1 FY25: Management said specific mill-wise production details are not given out.

Every question, with its answer

  1. 1. Inventory markdown mechanics

    Pratiksha, Aequitas Investments

    Question. Can you elaborate on why there was a marked-down on inventory?

    Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. High-value orders were backed by inventory purchased for those orders. During the quarter, raw material prices fell. The mill where those high-value orders were to be manufactured was under preventive maintenance shutdown, so the orders could not be dispatched. Inventory not dispatched had to be marked down to comply with accounting standards; this reverses when the orders are eventually dispatched.

    Follow-up. How would this quarter (Q1 FY25) be without that inventory loss? And is there a similar risk on current order book?

    Answer. Not a traditional speculative inventory loss — orders are backed by raw material purchases. Mill resumed first week of July. Depends on whether raw material prices fall or rise; if they fall further, similar situation, if not, reverse. Don't know where raw material prices go.

  2. 2. Mill shutdown production loss

    Pratiksha, Aequitas Investments

    Question. What was the production loss due to the shutdown in tonnage terms?

    Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Production loss in tonnage terms around 15,000 tonnes. However, WIP was finished and dispatched, which cushioned the impact.

    Follow-up. Execution period for drilling pipes in order book? And is margin profile better for cylinder pipes vs other products?

    Answer. Drilling pipes have a very long execution period. Margin profile for all high-value addition pipes is better than regular pipes; cylinder pipes are high value addition; we are one of two manufacturers of cylinder pipes; we want to grow the value-added share of dispatches.

  3. 3. Chinese import impact by segment

    Pratiksha, Aequitas Investments

    Question. Which segments are most affected by Chinese imports?

    Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. I don't want to do that right now.

    Not answered directly.

  4. 4. Selling price outlook

    Radha, B&K Securities

    Question. Do you expect pricing to remain stable for the rest of the year or further realization pressure?

    Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Raw material pricing cannot be commented on. Selling price is not expected to fall significantly from where it is right now.

    Follow-up. Will realizations fall more in subsequent quarters if raw material prices stay similar, given Chinese imports are still being addressed?

    Answer. Difficult to comment as the process is not controlled in a manner allowing a reasonable forecast; need to wait and watch as multiple entities and processes are involved.

    Not answered directly.

  5. 5. Hedging policy

    Radha, B&K Securities

    Question. What percentage of order book is hedged with raw material vs kept open?

    Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Almost the entire order book is hedged with raw material; an insignificant portion is kept open.

  6. 6. Export markets (US/Canada/Saudi)

    Radha, B&K Securities

    Question. What is the size of US/Canada market vs the 10 million-tonne global seamless demand, and are Saudi opportunities opening up?

    Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. We don't export to the Middle East; exports have been slow for more than a year. Market in US and Canada is very big, but they have not revived for us. On US/Canada split, the analyst has access to more databases; exact percentages difficult to communicate without specific data.

    Follow-up. What is the quantum of imports from China to India for seamless pipes in tonnage?

    Answer. It is impacting us, which is why realization has fallen so significantly — no specific tonnage figure given.

    Not answered directly.

  7. 7. Attribution of EBITDA miss

    Pradeep Rawat, Yogya Capital

    Question. Can you give weightage to each of the three reasons for the EBITDA drop?

    Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Equal weightage for all three factors.

    Follow-up. Where are we on hydrogen market seamless pipes, and how big is the opportunity?

    Answer. We are not supplying pipes for the hydrogen segment; hydrogen pipes are not being manufactured in the seamless segment in India.

  8. 8. Capex schedule (Telangana and hot mill)

    Pradeep Rawat, Yogya Capital

    Question. What was production from the Telangana unit, and when will Telangana capex and hot mill upgrade be commissioned?

    Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Telangana unit is part of Maharashtra Seamless; mill-wise production details not given out. Telangana finishing line was expected by March 2025, will in all probability be deferred by at least 9 months — orders recently placed with 12-month gestation. So completion likely by December 2025 (guidance, not hard stop). Hot mill upgrade will only happen after Telangana is in place to compensate for production loss; no volume growth expected in FY25, only in FY26 once Telangana is complete.

  9. 9. FY25 vs FY26 capex split

    Jatin Damania, SVAN Investments

    Question. Of the Rs.852 cr CAPEX plan, will most be spent in FY26 and only marginal in FY25? Can you quantify the FY25 vs FY26 split?

    Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Yes, that is correct. Don't want to give a figure now; will update in the next earnings call with a definitive figure. FY24 capex was minimum; will update on cash flow and CWIP phasing next time.

    Not answered directly.

  10. 10. Inventory markdown reversal

    Jatin Damania, SVAN Investments

    Question. Will the inventory mark-down be entirely reversed when the mill resumes and high-value orders dispatch?

    Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Yes, definitely what will happen; whether in full in the September quarter or the December quarter depends on order execution timing. Some reversal expected in Q2 FY25; would prefer all in September quarter so normalised EBITDA per tonne reflects going forward.

  11. 11. Raw material price movement

    Vinay Nadkarni, Hathway Investments

    Question. What is the average drop in raw material prices this quarter as a percentage? Was the top-line fall just pass-through?

    Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Drop is significant — EBITDA per tonne fell from Rs.22,000/tonne to Rs.9,000/tonne. No, not pass-through; three factors impacted EBITDA per tonne (already communicated). Don't want to specify a number for the markdown; irrelevant to what you want to calculate. Relevant point is that the markdown reverses when orders dispatch.

    Follow-up. Worry is whether the 15,000-tonne shutdown loss hits Q2 since WIP carried Q1 — where does that production show up?

    Answer. Mill started first week of July. Typical manufacturing is 110,000 tonnes earlier; dispatch in 100,000-115,000/quarter. March quarter dispatched around 95,000 tonnes (one order delayed to second week of April). June quarter: maintenance shutdown caused ~15,000-tonne production loss.

    Partly answered.

  12. 12. Inventory markdown quantum

    Satyan Wadhwa, Profusion Investment Advisors LLP

    Question. What was the actual inventory marked down on the high-value order — amount in rupees?

    Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. No inventory loss in the traditional sense; all orders hedged with raw materials; most of those orders were high-value manufactured in the mill under shutdown; raw material prices fell during the period; accounting standards required mark-down; will reverse once order executed. Not quantifying; three factors had equal weightage.

    Not answered directly.

  13. 13. Subsea pipe export geographies

    Deepak Mandhana, Avighna Investments

    Question. You mentioned penetration of newer export regions for sour service subsea seamless pipes — which countries or regions are these?

    Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Marketing sour service subsea seamless pipes in export market; not yet been successful. Have had encouraging inquiries but none yet crystallised into orders. Don't want to disclose geographies because competition is also there in those sectors.

    Follow-up. What revenue quantum from city gas distribution ERW pipe tenders in coming year? Has ERW realization held up vs seamless?

    Answer. ERW dispatches in range of 80,000 to 1,05,000 tonnes every year; not expanding capacity so will remain in this range. ERW realizations have fallen but to a lower extent than seamless. Don't think realizations will fall materially further beyond current levels; markdown will reverse.

    Not answered directly.

  14. 14. Buyback and ERW mix

    Shruti Mulchandani, Unifi Capital

    Question. Any update on buyback? And what was the mix of oil & gas and water in ERW for the quarter?

    Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. No update on buyback; FY24 dividend quadrupled vs FY22; no further update on dividends or buyback for current financial year. Q1 mix: ~20% oil & gas, 80% water in ERW — which has led to lower ERW segment margins.

    Follow-up. Do you see this mix reversing in the coming quarter? What is general oil & gas demand?

    Answer. Mix is difficult to predict at the start of the quarter; ERW EBITDA per tonne generally between Rs.6,000-Rs.11,000/tonne (plus or minus Rs.1,000). ERW is only 6-7% of total company EBITDA. Better indicator of oil & gas demand is current order book in which 51% is from ONGC and Oil India, plus significant balance from broader oil & gas sector.

    Partly answered.

  15. 15. Middle East export non-participation

    Pradeep Rawat, Yogya Capital

    Question. Why don't we sell to the Middle East when peers benefit from that market?

    Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Peers sell different products in the Middle East, not seamless pipes. Middle East has no anti-dumping duties on China, China dominates there with no scope for supernormal margins. We don't divert energies to markets where good margins aren't available.

    Follow-up. How big is the seamless pipes market for oil & gas in India and globally? With strong cash, why not expand ERW?

    Answer. Globally seamless pipes market ~10 million tonnes; India ~0.9 million tonnes; ONGC and Oil India demand ~100,000 tonnes/year for exploration. We are a seamless pipes manufacturer; ERW was set up only to service existing seamless customers; not an area of focus for capital allocation.

  16. 16. Welded vs seamless substitution

    Pradeep Rawat, Yogya Capital

    Question. Is there substitution of seamless pipes by large diameter welded pipes in infrastructure, building and auto segments?

    Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Large diameter welded pipes used in various segments against seamless pipes; seamless not manufactured beyond 22 inch while large diameter is 22-40 inches — separate segments; seamless primarily used in oil & gas, not infrastructure. Large diameter pipes not used in auto; auto uses low diameter seamless or cold drawn seamless; we don't supply significantly to auto.

  17. 17. Q1 capex and capacity utilisation

    Vinay Nadkarni, Hathway Investments

    Question. What was the CAPEX spent in Q1? And can you share capacity utilisation?

    Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Not significant CAPEX expenditure in Q1; did place orders for some equipment that was pending negotiation. Capacity utilisation on the lower side because one mill under shutdown. Annual capacity 550,000 tonnes; manufactured and dispatched 400,000 tonnes against that. Capacity utilisation generally in 70-80% range though product mix affects tonnage-based utilisation.

    Follow-up. Other expenses grew ~Rs.16 cr in Q1 — any one-off? And can you confirm the ~Rs.190 cr gap between cash accretion and cash profit as inventory markdown?

    Answer. Preventive maintenance shutdown had some impact on the increase in other expenses. On the cash math — 'No, it is not that' — no confirmation of Rs.190 cr markdown figure.

    Not answered directly.

  18. 18. Order book composition

    Pratiksha, Aequitas Investments

    Question. Is the 51% ONGC + Oil India share of order book for the total company and not just ERW? Any reason for fall in ERW order book?

    Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Correct, the 51% number is for the total company; split is detailed in the presentation slides. No significant reason for ERW order book fall — just timing of order confirmations; pipeline healthy; lag issue not demand issue. Excluding ERW segment and Telangana, ONGC/Oil India/other oil & gas share of order book would shoot up to 70-75%.

  19. 19. Shutdown nature

    Amit Kumar, Determined Investments

    Question. Was the maintenance shutdown planned or unplanned?

    Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Planned; communicated in May during the Q4 FY24 earnings call; and communicated to the Stock Exchange on 12 June.

What was said

Topic by topic, in the order it was spoken

Q1 FY25 Miss Explained — Three Drivers · Kaushal Bengani (DGM, IR & Finance)

  • Earnings impacted QoQ and YoY in Q1 FY25 due to (i) fall in sales realization from rising competition and Chinese dumping in select segments; (ii) preventive maintenance shutdown at one mill which meant high-value oil & gas orders could not be executed; (iii) inventory mark-to-market on high-value orders not dispatched as raw material prices fell.
  • Shutdown mill has resumed production at the start of Q2 FY25; normalization of dispatches expected from the September quarter.
  • Inventory mark-down is required to comply with accounting standards; will get nullified when the underlying high-value orders are dispatched in subsequent quarters.

Financial Snapshot · Kaushal Bengani (DGM, IR & Finance)

  • Revenue decline of only 4% QoQ in Q1 FY25, but EBITDA fell 54% to Rs.126 cr; PAT fell 40% to Rs.136 cr; EPS of Rs.10.
  • QoQ and YoY patterns are similar across parameters, reasons already explained.
  • EBITDA per tonne collapsed from Rs.22,000 to Rs.9,000 in Q1, driven by the three factors above with equal weightage.

Five Operating Highlights · Kaushal Bengani (DGM, IR & Finance)

  • Treasury at Rs.2,203 cr as on 30 June 2024 — has improved more than anticipated and is generating good returns; >1/3 of total Q1 FY25 earnings came from the treasury segment.
  • Order book increased from Rs.1,754 cr to Rs.1,812 cr; 51% of total order book from ONGC and Oil India, with substantial further exposure to the broader oil & gas sector.
  • Zero ICDs to unrelated parties and zero corporate guarantees outstanding — commitment made to shareholders two years ago fully and completely resolved.
  • FY24 dividend quadrupled versus FY22; no specific dividend distribution plan yet announced.
  • Capital goods, infrastructure and specifically oil & gas continue to see strong medium-term demand, supporting seamless pipes order book replenishment.

In their words

I can say with the fullest of confidence that there is no problem in operations and no problem in execution. It has just been a function of quite a few things amalgamating at the same point in time and thereby causing a disproportionate effect. I hope that quite a lot of these factors will normalize in the coming quarters, and it would be good to be vindicated later on.
Kaushal Bengani (DGM, Investor Relations and Finance, Maharashtra Seamless Limited)
It is not an inventory loss in the sense that people perceive it, because when you say inventory loss one imagines a speculative position which has been taken and loss has been incurred on account of that speculative activity. In our case, we had earmarked the order with inventory.
Kaushal Bengani (DGM, Investor Relations and Finance, Maharashtra Seamless Limited)
At least two of those reasons are temporary and one off in nature and may be a function of the accounting standards that we follow rather than a question mark on the operations of the company.
Kaushal Bengani (DGM, Investor Relations and Finance, Maharashtra Seamless Limited)

To check next time

What management committed to on this call, or the dates they gave.

  • Whether the inventory markdown reverses in Q2 FY25 as high-value orders dispatch, restoring per-tonne EBITDA.
  • Dispatch normalisation after the mill resumed in the first week of July 2024.
  • The promised definitive FY25 and FY26 capex split of the Rs.852 crore plan.
  • Equipment delivery progress against the 12-month gestation and the December 2025 Telangana target.
  • Whether sales realisations hold after Chinese dumping pressure and the outcome of discussions with authorities.
  • Any dividend or buyback update for the current financial year, still not announced.

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Tue 30 Jul 2024₹655.60−1.85%+0.09%
5 sessions Mon 5 Aug 2024₹617.55−7.55%−3.14%
20 sessions Tue 27 Aug 2024₹691.60+3.54%+0.73%

From the close of Mon 29 Jul 2024, ₹667.95: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

Maharashtra Seamless's other calls

  • Q2 FY27Sat 14 Nov 2026Tone: Mixed
  • Q1 FY27Sat 8 Aug 2026Tone: Confident
  • Q3 FY26Thu 29 Jan 2026Tone: Defensive
  • Q2 FY26Wed 5 Nov 2025Tone: Defensive
  • Q1 FY26Thu 31 Jul 2025Tone: Defensive
  • Q4 FY25Tue 27 May 2025Tone: Cautious
  • Q3 FY25Tue 28 Jan 2025Tone: Confident
  • Q2 FY25Tue 29 Oct 2024Tone: Confident
  • Q4 FY24Wed 22 May 2024Tone: Confident