Solarium Green Energy Q2 FY26 earnings call
In brief
H1 FY26 revenue up 43% YoY, EBITDA up 36%; 1 GW module plant targets mid-Jan 2026 commissioning, 75-80% utilization by Q2 FY27
- Management's tone
- Confident
- What was said
- Leaned positive
- Guidance
- None given
- Analyst pushback
- Low
- Stock, next session
- +1.05% (Nifty 50 +0.40%)
- H1 FY26 revenue grew 43% YoY, gross margins up 65%, EBITDA up 36% and PAT up 22%, though moderated by monsoon and GST 2.0 rollout
- Order book visibility: INR 229 cr unexecuted, INR 209 cr L1 orders, and bidding pipeline of INR 900+ cr
- 1,000 MW solar module plant in Ahmedabad targets mid-Jan to end-Jan 2026 commissioning; 75-80% utilization by Q2 FY27 end
- 1,200 MTPA structure manufacturing commissioned July 2025; expected 5% cost advantage and 0.3-0.5% EPC margin benefit
- Finance cost elevated by one-off defense receivable delays (BSF, MES) due to Operation Sindoor; INR 20-25 cr received in October, clearing by December
An AI read of the company's transcript · the filing
The numbers
The quarter, Q2 FY26
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹117 cr | — | — | |
| EPS (₹) | ₹4.42 | — | — |
From the company's filed results for the quarter ended 30 Sept 2025 (consolidated), not from the call.
What moved the numbers, as management explained it
- Prolonged monsoon across India and GST 2.0 rollout in Sept 2025 caused demand/supply postponement, moderating H1 revenue growth (one-off)
- Solarium Saarthi franchisee initiative (450 new channel partners) drove margin expansion; commissions to stabilize as scale grows
- Defense project receivables (BSF, MES) delayed May-Aug 2025 due to Operation Sindoor; one-off impact of INR 20-25 cr received in October, clearing by December (one-off)
- Employee cost up 80% YoY (H1 to H1) due to manufacturing foray and sales team expansion, but flat H2 FY25 to H1 FY26
- Structure manufacturing (1,200 MTPA, commissioned July 2025) provides ~5% cost advantage; partially offsets margin pressure from trading-to-EPC shift
The numbers management led with
- 1,200 MTPA module mounting structure facility commissioned: July 2025; estimated 5% cost advantage on ~10% of solar plant cost
- 1 GW solar module manufacturing plant commissioning: Mid-January 2026 to end-January 2026; TOPCon technology (upgradeable to HJT)
- Order book visibility (unexecuted + L1 + bidding pipeline): INR229 cr unexecuted + INR209 cr L1 + INR900+ cr bidding pipeline
- Module plant standalone economics at 85% utilization: INR1,000+ cr revenue potential; 12-13% EBITDA margin standalone
Guidance
Guidance on this call
| What | For | What management said |
|---|---|---|
| Module plant commissioning (Module Manufacturing) | — | fully operational plant will be end of January. The target is somewhere between mid-January to end of January |
| Module plant standalone EBITDA margin (Module Manufacturing) | — | on the EBITDA level, if we see that plant standalone, that should be able to operate at 12% to 13% margin |
| Module plant standalone revenue at 85% utilization (Module Manufacturing) | — | as a standalone unit, plant will be able to generate anywhere about INR1,000 crores plus revenue, if we'll be able to operate it at 85% |
| Module plant capacity utilization (Module Manufacturing) | Q2 FY27 | anywhere between 75% to 80%. And the target for that is before Q2 end |
| EPC margin benefit from structure manufacturing | — | margin benefit at an overall, only on the EPC segment part, to about 0.3% to 0.5%, effectively |
| Structure manufacturing cost advantage | — | an estimated 5% cost advantage |
| Defense project receivables clearance (Government) | — | we expect to clear that off by December itself |
| Q4 FY26 working capital deployment from IPO proceeds (Module Manufacturing) | Q4 FY26 | in Q4, we expect anywhere between INR60 crores to INR70 odd crores worth of working capital required for the operations |
| Unexecuted order book execution | Q1 FY27 | in terms of unexecuted order book is something, I'd say, not later than Q1 next year. Most of it will get executed within this year |
| L1 order execution timeline | — | from the time we receive the LOAs, our expectation to execute them is anywhere between 9 to 12 months |
| Long-term cell supplier agreements (Module Manufacturing) | Q4 FY26 | by the end of Q4, we'll have long-term agreements with most of our suppliers |
What changed since the Mon 5 May 2025 call
| What | On the Mon 5 May 2025 call | On this call |
|---|---|---|
| Order book visibility (restated) | ₹363 cr FY26 revenue visibility: ₹120 cr unexecuted order book + ₹243 cr PSU L1 orders pending LOA | INR 229 cr unexecuted + INR 209 cr L1 + INR 900+ cr bidding pipeline |
| EBITDA margin band (not repeated) | First-ever EBITDA margin band of 11-13% given | Not mentioned |
| Residential expansion cities (raised) | Scale residential rooftop across 15+ new cities/warehouses in FY26 with Solar Saarthi channel model | Footprint expanded to 25 new cities with ~450 new channel partners in H1 FY26 |
| DCR panel situation (restated) | ₹17 cr of residential orders pushed to Q1 FY26 due to DCR panel shortage; corporate tie-up announced to mitigate | Module plant can use both DCR and non-DCR cells; non-DCR to continue for 1.5-2 years |
| IPO proceeds deployment (restated) | Deploy IPO funds primarily into working capital alongside bank leverage | Bank credit lines used; IPO funds held to build credit history; deployment of INR 60-70 cr expected Q4 FY26 |
| 1 GW module manufacturing (new) | Not mentioned | 1,000 MW module plant commissioning by mid-Jan to end-Jan 2026; INR 1,000 cr+ standalone revenue at 85% utilization |
| Avoid IPP focus (not repeated) | Avoid IPP entry for next couple of years; focus on capital-light EPC model | Not mentioned |
The business
By business
Residential
32% of H1 FY26 revenue; footprint expanded to 25 new cities with ~450 new channel partners onboarded via Solarium Saarthi
32% of H1 FY26 revenue · 25 new cities added · ~450 new channel partners
Outlook: Ongoing expansion; reduction in working capital cycle noted in residential business
Government
36% of H1 FY26 revenue; execution track record strong across multiple states; main contributor with INR 229 cr unexecuted order book
36% of H1 FY26 revenue · INR 229 cr unexecuted order book · INR 209 cr L1 orders · INR 900+ cr bidding pipeline
Outlook: we don't expect the contribution to go down. Either it will remain there or increase
Module Manufacturing
1,000 MW automated module plant in Ahmedabad under commissioning; TOPCon tech, can use both DCR and non-DCR cells; targets mid-Jan to end-Jan 2026 go-live
1000 MW capacity · INR 1,000 cr+ standalone revenue at 85% utilization · 12-13% standalone EBITDA margin
Outlook: First revenue expected Q4 FY26; 40-50% utilization in first 2 months, 75-80% by Q2 end FY27
Structure Manufacturing
1,200 MTPA structure manufacturing facility commissioned in July 2025; expected to give ~5% cost advantage and 0.3-0.5% margin benefit on EPC
1200 MTPA capacity · 5% cost advantage · 0.3-0.5% EPC margin benefit
Outlook: Will support captive consumption; cost benefit on structure (~8-10% of solar plant)
Balance sheet, capex and funding
- Finance cost elevated due to working capital; one-off tied to defense project receivables (BSF, MES) delayed by Operation Sindoor, May-Aug 2025
- INR 20-25 cr of defense receivables received in October; expected to clear fully by December 2025
- Working capital needs: INR 80-100 cr specifically for module manufacturing plant; already on balance sheet
- Q4 FY26 expected working capital deployment: INR 60-70 cr from IPO proceeds for module plant operations
- Bank credit lines secured; IPO funds held back to build credit history and as buffer; no additional cost on company
- No specific debt or cash levels stated; finance cost to remain similar in absolute terms but normalize from Q4 as one-off clears
The industry, as management sees it
Management views the Indian distributed solar sector as structurally robust — installations growing ~40% YoY in 2025 vs ~25% in 2024, supported by PM Surya Ghar Yojana, GST 2.0 (5% on modules/inverters), and 96-97% unorganized share offering consolidation runway. Module pricing volatility seen as cyclical, not structural — driven by raw material softening not capacity glut, with effective installed capacity lower than headline GW after utilization haircuts and demand continuing to outstrip supply.
Risks management named
- Finance cost elevated due to working capital strain from delayed BSF/MES defense project receivables (May–Aug 2025)
- H1 revenue moderated by prolonged monsoon and demand postponement from GST 2.0 rollout in September 2025
- Employee cost up ~80% YoY due to manufacturing foray headcount ramp (management expects flat h-on-h)
Q&A
Q&A was dominated by module plant economics (commissioning timeline, utilization curve, standalone vs captive economics, EBITDA uplift potential). Working capital strain from BSF/MES defense receivables — explicitly framed as a one-off tied to Operation Sindoor — drew multiple follow-ups. Competitive positioning vs larger players (Adani, Waaree, Tata) was another focal point, with management arguing execution depth is the moat against bigger but execution-light rivals. Management formally declined quantitative guidance citing organizational youth, the only material deflection on the call.
Not answered directly
- Forward growth/EBITDA guidance for H2 FY26 and FY27 (refused citing organizational youth)
- Short-term provisions increase breakdown (deferred offline)
Asked for a number, answered without one
- H2 FY26 growth: Refrained from guidance citing organization being very young; pointed to EPC growth doubling every year FY23-25 and order pipeline visibility
- FY27 growth over FY26: Said FY27 will be in addition to past EPC growth trajectory; module plant at 75-80% utilization will add further revenue
- Forward EBITDA margin: Refrained from guidance; only cited module plant standalone EBITDA margin of 12-13% and structure manufacturing cost benefit of 4-5%
- Module plant cost advantage: Said cost advantage and supply advantage will be there but not yet estimated; standalone revenue potential of INR 1,000 cr+ at 85% utilization given
- BESS share of bidding pipeline: Said difficult to answer; some bids include BESS but no number handy for percentage; other latest technologies also present in tenders
Every question, with its answer
1. Module plant commissioning & economics
Maitri Shah, Sapphire Capital
Question. When do we expect the 1 GW module plant to commission — Q4 FY26 or Q1 FY27? Are we planning cell manufacturing? When can utilization reach 85%? And what cost/margin benefits should we expect in Q4 FY26 and FY27 from structure + module integration?
Answer, Himanshu Garg, Chief Financial Officer. Module plant expected commissioned by mid-January 2026 — machines ship from China this week, arrive India mid-December, then ~15-20 days trial runs; fully operational by end-January 2026. Cell manufacturing is forward-looking; will update after module plant is commissioned. Initial utilization: 40-50% for the first couple of months, target 75-80% utilization before Q2 FY27 end. Structure plant delivers ~5% cost advantage on ~10% of solar plant cost, equivalent to 0.3-0.5% EBITDA uplift on EPC. Module plant standalone at 85% utilization can generate INR1,000+ cr revenue at 12-13% EBITDA margin.
2. DCR cell compatibility
Maitri Shah, Sapphire Capital
Question. Will the module manufacturing unit be capable of using DCR cells, which will likely be compulsory from June 2026?
Answer, Himanshu Garg, Chief Financial Officer. Yes. The unit is being installed with TOPCon technology (latest globally, upgradeable to HJT in 3-4 years) and is capable of using both DCR and non-DCR cells.
3. Forward guidance & seasonality
Maitri Shah, Sapphire Capital
Question. What guidance can you provide on seasonality, H2 FY26 growth, FY27 growth over FY26, and EBITDA margins?
Answer, Himanshu Garg, Chief Financial Officer. We continue to refrain from forward guidance given the organization is still very young. In transparency: EPC segment grew 4x from FY23 to FY25 (doubled every year) and we expect that trajectory to continue based on the order pipeline (INR230 cr unexecuted, INR210 cr L1). FY27 will add incremental module revenue once utilization crosses 75-80%.
Not answered directly.
4. Margin drivers & sustainability
Ansh Singh, AG Investments
Question. What were the key drivers of the EBITDA margin expansion in H1 FY26 and how sustainable are they?
Answer, Himanshu Garg, Chief Financial Officer. Solarium Saarthi franchisee initiative is the main driver — onboarding franchisee partners is generating higher margin orders, though commissions outgo is higher now; as the initiative scales, commissions will stabilize and margins sustain.
5. Module plant project status
Ansh Singh, AG Investments
Question. What is the current status of the 1 GW module plant — land, machinery and pending approvals?
Answer, Himanshu Garg, Chief Financial Officer. Machines ship from China this week, reach India port by third week of December. Installation ~2 weeks, trial runs 2-3 weeks; fully operational by mid-to-end January 2026.
6. Working capital & trade receivables
Ansh Singh, AG Investments
Question. Trade receivables are up significantly. How are you managing receivables, payables and inventory as you scale?
Answer, Himanshu Garg, Chief Financial Officer. One-off delay in trade receivables from government-linked projects — specifically defense-linked (BSF and MES, Border Security Force and Military Engineering Services). Both agencies were unreachable from May to August 2025 due to Operation Sindoor (India-Pakistan conflict). No delays from NTPC or other government projects or residential. Cash collection resumed August-September; INR20-25 cr received in October; expect full clearance by December.
7. Employee cost trajectory
Ansh Singh, AG Investments
Question. Employee cost rose ~80% YoY. How should we expect employee cost to behave in H2 FY26 and FY27?
Answer, Himanshu Garg, Chief Financial Officer. Employee cost was a constant h-on-h (H2 FY25 to H1 FY26) — there has been no further increase between halves. No further increments expected; rather some efficiency expected. The manufacturing facility will generate its own contribution and not add back to existing employee base.
8. Residential payment cycle & customer journey
Vinay Lakhera, RatnaTraya Capital
Question. What is the payment cycle on the residential and commercial side? When does subsidy get disbursed — at the end? And from which point is Solarium's involvement with the customer?
Answer, Himanshu Garg, Chief Financial Officer. Residential: negligible credit; AR runs 7-10 days. Customer pays INR10,000-20,000 token advance, then 100% before dispatch. Credit is offered only on finance-linked cases (third-party FI disbursement) or bulk files guaranteed by RWAs. Subsidy is disbursed only after government portal file approval; Solarium is involved from first step through subsidy receipt. Solarium offers end-to-end handholding including in-person bank visits for subsidized loans at <7% from mandated PSU banks.
9. Competitive intensity & geography
Vinay Lakhera, RatnaTraya Capital
Question. Is the competition geography-specific (one player per region), and as larger solar/pump players enter rooftop, will size or execution matter more?
Answer, Himanshu Garg, Chief Financial Officer. Competition is geography-specific. Major competition is from local installers (electricians). 96-97% of the business is still unorganized. Bigger players like Adani, Waaree, Tata are only selling modules or kits — none of them are executing rooftop. Solarium's execution-led model plus backward integration is the differentiator.
10. Cell sourcing, DCR mandate, bidding pipeline
Shruti Malpani, Aarth AIF
Question. Where will cells be sourced from — China or domestic? Is this only assembly? Will you use DCR cells after the 31 Aug 2026 mandate?
Answer, Himanshu Garg, Chief Financial Officer. Module manufacturing process is essentially integration/assembly using latest fully-automated machines from Jinchen (top-2/3 global supplier). Initial sourcing is non-DCR cells; will move to DCR cells as Indian DCR capacity ramps in 2 years. Non-DCR remains usable for projects bid before 31 Aug 2025 — INR900+ cr order pipeline was bid before that date, providing 1.5-2 years of execution runway. India-level pipeline exceeds 100 GW; many tenders were bunched in August 2025 ahead of the mandate.
11. Industry outlook, Q4 revenue ramp, IPO proceeds deployment
Shruti Malpani, Aarth AIF
Question. What is the industry outlook for rooftop solar given China restrictions on >300 Wh/kg cells? Can we expect module sales from REI orders to flow into Q4 FY26 or spill into Q1 FY27? And why are IPO proceeds for working capital not yet deployed?
Answer, Himanshu Garg, Chief Financial Officer. China restrictions don't affect us — we've actually seen some softening in non-DCR module pricing. We expect module revenue to start flowing in Q4 FY26. Sales team already hired including Sandeep Banodiya (ex-Krannich Global Germany lead); cross-selling already underway. IPO working capital proceeds not yet deployed to build credit history and secure cheaper bank lines — no additional cost to the company. Will deploy INR60-70 cr in Q4 FY26 for manufacturing working capital needs (~INR100 cr required at 85% utilization).
12. Short-term provisions & distribution segment definition
Shruti Malpani, Aarth AIF
Question. Short-term provisions rose from INR4 cr to INR10 cr — what drove this? And what exactly is the 'distribution sales' segment — is it the Saarthi program?
Answer, Rohit Jindal, Vice President, Finance and Accounts. Rohit Jindal did not have the short-term provisions breakdown handy and offered to revert offline. Separately, Himanshu Garg clarified that the 'distribution sales' segment is a pure trading business (~70% of segment) where Solarium imports modules (e.g. from Trina) — a negative working capital business with modest margin capture.
Not answered directly.
13. Structure & module EBITDA impact
Shikhar Gupta, Individual Investor
Question. What is the final EBITDA impact from the structure manufacturing 5% cost advantage? And will module manufacturing also improve margins straightforwardly?
Answer, Himanshu Garg, Chief Financial Officer. Structure plant impact is 0.3-0.5% EBITDA uplift on EPC (5% on ~10% of solar plant cost). Module plant impact: any captively-consumed module (~50% of solar plant cost) can add 10-12% EBITDA margin per module. Targeting 40-50% captive consumption initially over 6-9 months; full margin benefit scales as acceptance grows. Expect 5-7% gross margin improvement if modules consumed in-house.
14. Finance cost normalization & government segment outlook
Maitri Shah, Sapphire Capital
Question. How will finance cost normalize over the next two quarters given the defense receivables issue? Given manufacturing debt, will absolute finance cost remain elevated? And do you expect government segment contribution to drop given the receivable pressure?
Answer, Himanshu Garg, Chief Financial Officer. Finance cost bloated specifically in Q3; will normalize from Q4 as defense collections come in (INR20-25 cr already received in October, full clearance by December). Absolute finance cost may remain at similar or slightly higher level given manufacturing debt, but normalized as a % of revenue. Government segment contribution is expected to hold or grow — defense receivable delay was strictly one-off with BSF/MES during Operation Sindoor. No delays with NTPC, HPPL or other government entities. Order pipeline remains intact; majority of orders are non-defense.
15. B2C app economics, BESS EPC vs manufacturing
Maitri Shah, Sapphire Capital
Question. Is the B2C app a new revenue source or a customer experience tool? Are you planning to enter BESS manufacturing or just EPC? What % of the INR900 cr bidding pipeline is BESS?
Answer, Himanshu Garg, Chief Financial Officer. B2C app is purely a customer experience tool to improve retention and conversion — not a revenue source. On BESS: Solarium already executes energy storage contracts (Leh-Ladakh, Northeast, air force stations) and will continue bidding. No BESS manufacturing planned — focus remains on module vertical integration. Does not have the exact BESS percentage in the INR900 cr pipeline handy but confirmed there are BESS-included tenders.
Partly answered.
16. Order book execution timeline, win ratio, module pricing outlook
Maitri Shah, Sapphire Capital
Question. What is the execution timeline for the INR229 cr unexecuted order book and INR209 cr L1? What is your bidding win ratio? And given module pricing volatility, isn't new plant commissioning a risk?
Answer, Himanshu Garg, Chief Financial Officer. Unexecuted order book: most to be executed within FY26; not later than Q1 FY27. L1 orders: 9-12 months from LOA receipt. Win ratio on number of bids: 25-30% — but value ratio is skewed by order size variability (INR5 cr to INR1,000 cr bids). On module pricing volatility: not the first cycle the industry has seen this; softening is driven by raw material cost decline not new capacity. Effective installed capacity is lower than headline 100-130 GW after utilization adjustment (70-75% utilization = 20-30 GW effective haircut). Demand growing 40% YoY vs 25% last year.
17. Cell supplier contracts
Shruti Malpani, Aarth AIF
Question. What kind of agreements do you have with Chinese cell suppliers — long-term or order-by-order?
Answer, Himanshu Garg, Chief Financial Officer. Currently order-by-order — leveraging relationships from the erstwhile manufacturing facility. Expect long-term agreements to be signed by end of Q4 FY26 with most suppliers. Avoiding cost lock-ins given module price volatility; no supply challenges foreseen.
What was said
Topic by topic, in the order it was spoken
H1 FY26 Business Overview · Ankit Garg (Chairman & MD)
- H1 FY26 was a strong growth period for the Indian solar sector
- Supported by PM Surya Ghar Yojana, GST 2.0 implementation, and renewable infrastructure momentum
- Healthy demand environment for distributed solar solutions where Solarium has built a 5-year foundation
- However, growth was moderated by prolonged monsoon and demand postponement from GST 2.0 rollout
H1 FY26 Financial Performance · Ankit Garg (Chairman & MD)
- Revenue grew 43% YoY
- Gross margins up 65%
- EBITDA up 36% YoY
- Profit after tax up 22% YoY
- GST rate cut on modules and inverters from 12.5% to 5% (~5% composite reduction) expected to accelerate solar adoption in subsequent quarters
Workforce & Finance Cost Dynamics · Ankit Garg (Chairman & MD)
- Employee count increased driven by the company's foray into manufacturing
- Proactive investment in sales and execution teams
- Finance cost elevated due to working capital requirements from delayed government receivables
- Defense link projects specifically impacted short-term liquidity and interest expense
Business Segment Mix · Ankit Garg (Chairman & MD)
- Residential contributed 32% of H1 FY26 revenue; government projects 36%
- Residential footprint expanded to 25 additional cities via Solarium Saarthi Initiative
- ~450 new channel partners onboarded in H1
- Government order book remains robust with strong execution track record across multiple states
Order Book & Pipeline Visibility · Ankit Garg (Chairman & MD)
- Unexecuted order book: INR229 crores
- L1 orders (awaiting LOA): INR209 crores
- Bidding pipeline: over INR900 crores
- Provides clear visibility for growth over next several quarters
Backward Integration & Manufacturing Milestones · Ankit Garg (Chairman & MD)
- 1,200 MTPA module mounting structure manufacturing facility commissioned in July 2025
- Estimated 5% cost advantage on structure (which is ~10% of solar plant cost)
- Next milestone: 1,000 MW automated solar module manufacturing plant in Ahmedabad
- Will position Solarium as a vertically integrated player and strengthen long-term competitiveness
Digital Initiatives · Ankit Garg (Chairman & MD)
- Investing in B2C application for the residential segment
- Provides real-time order tracking, payment updates and related functionalities
- Designed to enhance customer experience and retention
H2 FY26 Priorities & Outlook · Ankit Garg (Chairman & MD)
- Successful commissioning of module manufacturing plant
- Strengthening residential franchisee network
- Scaling execution in government and turnkey segments
- Driving cost efficiencies through integration and operational discipline
- Management remains confident about sustaining growth trajectory
In their words
Still, like, today, more than 96%-97% of the business is unorganized.
A lot of people get confused in terms of, okay, Adani is doing the rooftop and Waaree is doing rooftop. But in actual, nobody is doing the rooftop, including Tata. So, they are only supplying the products. Nobody is there in terms of executing.
We continue to refrain from any sort of guidance, given we are still very, very young in terms of organization.
To check next time
What management committed to on this call, or the dates they gave.
- 1,000 MW module plant commissioning by mid-Jan to end-Jan 2026
- First revenue from module sales expected Q4 FY26
- Working capital normalization as defense receivables (BSF, MES) clear by December 2025
- Module plant utilization 40-50% in first 2 months of operation
- Long-term cell supplier agreements to be signed by end of Q4 FY26
- Q4 FY26 finance cost normalization (one-off from defense project delays to clear)
Transcript
We have not transcribed this call's recording. Read the company's transcript (PDF).
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Mon 17 Nov 2025 | ₹302.90 | +1.05% | +0.40% |
| 5 sessions Fri 21 Nov 2025 | ₹283.70 | −5.35% | +0.61% |
| 20 sessions Fri 12 Dec 2025 | ₹241.40 | −19.47% | +0.53% |
From the close of Fri 14 Nov 2025, ₹299.75: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.