Solarium Green Energy Q2 FY27 earnings call
In brief
H1 FY27 revenue rose 165% to ₹310.5 cr; management targets 9%-10% H2 EBITDA margin and higher plant utilisation.
- Management's tone
- Mixed
- What was said
- Mixed
- Guidance
- Guidance held
- Analyst pushback
- Medium
- Stock, next session
- −0.37% (Nifty 50 +0.38%)
- H1 FY27 revenue rose 165% to ₹310.5 cr and PAT rose 14% to ₹10.5 cr, despite gross margin falling to 21.6%.
- EBITDA rose 57% to ₹25.6 cr, but margin declined to 8.3% as mix shifted toward lower-margin EPC and module sales.
- Order book rose to ₹720.9 cr, including ₹461.1 cr of EPC and ₹259.8 cr of module supply.
- ALMM's July enlistment left only 2-2.5 months of manufacturing revenue against six months of fixed costs.
- Trade receivables rose to ₹281.9 cr from ₹152 cr in March, making collections management's H2 priority.
An AI read of the company's transcript · the filing
The numbers
The quarter, Q2 FY27
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹310 cr | +165.5% | — | |
| EPS (₹) | ₹5.04 | +14.0% | — |
From the company's filed results for the quarter ended 30 Sept 2026 (consolidated), not from the call.
Where management's figures differ from the filing
- Revenue from operations: said H1 FY27 revenue from operations ₹310.5 cr, up 165% from ₹116.9 cr.; filed Q2 FY27 Revenue: ₹310.47 cr (+165.5% YoY). Management consistently described the reported period as H1 FY27, while the filed block labels the same amount as Q2 FY27.
- EPS: said H1 FY27 basic EPS ₹5.04, against ₹4.42.; filed Q2 FY27 EPS: ₹5.04 (+14.0% YoY). The transcript presents EPS for H1 FY27, while the filed block labels the same figure as Q2 FY27.
What moved the numbers, as management explained it
- Mix shifted toward lower-margin Large EPC and module sales; gross margin fell to 21.6% from 44.4% and EBITDA margin to 8.3% from 14%.
- ALMM's July enlistment left 2-2.5 months of manufacturing revenue against six months of fixed costs; management estimated ₹4.5-5 cr of underutilisation cost.
- Depreciation rose to ₹3.4 cr from ₹0.5 cr because the plant was depreciated for a full half after commissioning. (accounting)
- Finance cost rose to ₹8.3 cr from ₹4.4 cr on the plant term loan and working capital supporting manufacturing and EPC.
- Residential execution shifted toward Kits after warehouse and city fixed costs made the prior end-to-end model less healthy in the immediate P&L.
The numbers management led with
- Order book: ₹720.9 crores, versus about ₹300 crores discussed in June
- Large ground-mount EPC awards: Two 50 MW AC contracts valued at ₹188.5 crores and ₹186.5 crores
- Module manufacturing capacity: 1.23 GW annual automated line at Miroli, Ahmedabad
- Trade receivables: ₹281.9 crores at September 2026, up from ₹152 crores in March
Guidance
Guidance on this call
| What | For | What management said |
|---|---|---|
| EBITDA margin | H2 FY27 | H2 FY27 EBITDA margin is expected in the 9%-10% range. |
| PAT margin | FY27 | FY27 PAT margin is expected to recover to about 5%-6%. |
| Order book execution | FY27 | More than 60%-70% of the order book is expected to be executed within the year. |
| Large EPC contract execution timeline | FY27 | The two large EPC contracts are targeted for execution by end-March. |
| Residential run rate including Kits (Residential installations) | H2 FY27 | Residential revenue including Kits is expected at an ₹8-10 cr monthly run rate over the next 1-2 months. |
| Kits gross margin (Solar Kits) | — | Solar Kits gross margin is expected at about 15%-18%. |
| Kits EBITDA margin (Solar Kits) | — | Solar Kits EBITDA margin is expected at about 10%-12%. |
| Manufacturing captive consumption | H2 FY27 | Captive consumption of 50%, 60% or 70% remains on the cards and is foreseen soon. |
| Revenue growth | FY27 | Management expects similar growth to continue, with module sales adding to revenue. |
| Plant utilization (Manufacturing) | H2 FY27 | Management aims to raise plant utilisation now that ALMM enlistment is in place. |
| Kit distribution network (Solar Kits) | H2 FY27 | Management plans to scale the Kit distribution network to more states and cities. |
| Receivables | H2 FY27 | Management aims to reduce receivables as EPC milestones are built and collected. |
| Cash flow | H2 FY27 | Management expects cash flow to improve as collections are received. |
| Finance cost as a share of revenue | H2 FY27 | Management expects finance cost as a share of revenue to decline as collections improve. |
| Finance cost | FY27 | Finance cost is not expected to increase further and should remain near recent levels. |
What changed since the Tue 2 Jun 2026 call
| What | On the Tue 2 Jun 2026 call | On this call |
|---|---|---|
| Order book size (raised) | Order book ₹300+ cr. | Order book ₹720.9 cr: ₹461.1 cr of EPC and ₹259.8 cr of module supply. |
| FY27 order-book execution (cut) | ~100% executed in FY27. | More than 60%-70% of the ₹720.9 cr order book is expected to be executed within the year. |
| EBITDA margin (restated) | FY27 exit EBITDA margin guidance of 10%-12%. | H2 FY27 EBITDA margin expected at 9%-10%; no full-year figure was given. |
| Residential revenue run rate (restated) | ₹16-18 crores monthly by end-FY27, including Solar Kits. | ₹4-5 cr monthly excluding Kits; ₹8-10 cr including Kits expected over the next 1-2 months. |
| Ground-mounted EPC contracts (raised) | One 50 MW Maharashtra win worth ₹185 cr; 300 MW pipeline with 60% conversion expected in 2-3 months. | Two 50 MW AC contracts worth ₹188.5 cr and ₹186.5 cr; EPC order book ₹461.1 cr. |
| Manufacturing captive consumption (restated) | 50%-60% of production targeted for captive consumption in FY27. | About ₹90 cr was captively consumed; higher captive use remains on the cards, but no H1 split was given. |
| Solar Kits (achieved) | PAN-India distribution through Solar Kits was planned for 20,000+ PM Surya Ghar EPC vendors. | Kits generated ₹4.5-5 cr in their first 1.5 months and were reported within residential. |
| FY27 capex (not repeated) | No major capex foreseen in FY27; focus on execution and ramp-up. | Not mentioned |
The business
By business
Manufacturing
Manufacturing sales were ₹113.4 cr, but ALMM's July delay left 2-2.5 months of revenue against six months of fixed costs; September utilisation was 75%-80%.
Manufacturing sales ₹113.4 cr · Revenue share 36.5% · Plant capacity 1.23 GW · September utilisation 75%-80% · Captively consumed modules about ₹90 cr · Segment gross margin 14%-15%
Outlook: Management aims to raise utilisation after ALMM enlistment and said higher captive consumption remains on the cards.
Large EPC / C&I and Government projects
C&I and government projects contributed ₹147.9 cr; two 50 MW AC contracts worth ₹188.5 cr and ₹186.5 cr are to use in-house modules.
Revenue ₹147.9 cr · Revenue share 47.6% · Contract 1 50 MW AC · Contract 1 value ₹188.5 cr · Contract 2 50 MW AC · Contract 2 value ₹186.5 cr · EPC order book ₹461.1 cr · Segment gross margin 25%
Outlook: The two contracts are targeted for completion by end-March, with in-house module supply and subcontract margins already secured.
Residential installations
Residential revenue was ₹37.6 cr and remained the highest-margin business; the model shifted toward Kits and city distributors to reduce warehouse and city fixed costs.
Revenue ₹37.6 cr · Revenue share 12.1% · Gross margin 35%-40% · PM Surya Ghar installations 11,400 · Portal rating 4.8 out of 5 · Current monthly run rate excluding Kits ₹4-5 cr
Outlook: Residential revenue including Kits is expected at an ₹8-10 cr monthly run rate over the next 1-2 months, with distribution expanding beyond six launch cities.
Solar Kits
The 25-item branded kit generated ₹4.5-5 cr from mid-August to September 30 and is reported within the residential business.
Revenue ₹4.5-5 cr · Kit contents 25 items · Expected gross margin 15%-18% · Expected EBITDA margin 10%-12%
Outlook: Management expects 15%-18% gross margin and 10%-12% EBITDA margin, and plans to appoint exclusive city distributors and expand to more states and cities.
Product sales
Product sales, including modules and inverters sold, contributed ₹11.6 cr, or 3.7% of H1 revenue.
Revenue ₹11.6 cr · Revenue share 3.7%
Balance sheet, capex and funding
- Total borrowing was ₹189.1 cr: ₹73.6 cr of long-term loans and ₹115.5 cr of short-term loans.
- Cash and bank balances were ₹35.6 cr.
- Trade receivables rose to ₹281.9 cr from ₹152 cr in March; management made reduction an H2 priority.
- Inverter inventory fell to ₹40.7 cr from ₹99.7 cr as modules were dispatched into EPC and external orders.
- Finance cost was ₹8.3 cr versus ₹4.4 cr; management expects its share of revenue to fall as collections improve.
- Further equity raise is not currently on the cards; management will revisit it if execution creates a funding need.
The industry, as management sees it
Rooftop demand remained policy-supported: PM Surya Ghar had reached 50 lakh households and 14.8 GW, with ₹22,000 crores allocated for FY27, while the module GST rate fell to 5%. Cell supply was already above 50 GW and DCR capacity rose from 20 GW to 42 GW in six months, suggesting the supply gap was narrowing and easing the ALMM cell timeline.
Risks management named
- Module-plant underutilization before ALMM listing left fixed costs across only 2-2.5 months of manufacturing revenue
- Mix shift toward lower-margin EPC and module sales compressed consolidated margins
- Trade receivables increased to ₹281.9 crores, raising cash-conversion and finance-cost pressure
- Large ground-mount EPC contracts depend on timely milestones, execution and customer collections
- Residential expansion created high fixed costs, prompting a capital-light Kits and distributor pivot
- Residential scale and execution in Gujarat remain uncertain, with no quantified commitment
Q&A
Discussion centered on EPC concentration and execution, module-plant utilization and margin normalization, and the cash tied up in receivables; individual investors directly challenged prior EBITDA and residential targets. Management was specific on payment milestones, Kits economics and segment margins, but deferred post-quarter collections and plant break-even economics and declined to provide a FY27 revenue target.
Not answered directly
- Post-September collection amount
- Module-plant fixed-cost and break-even economics
- FY27 revenue target
- Main-board migration plan
Asked for a number, answered without one
- FY27 revenue: Management declined numerical guidance and said similar growth would continue, with module sales adding to revenue.
- Plant fixed cost and break-even: Management declined to discuss the details on the call and offered to answer them separately.
- Post-September collections: Management had no number, said quite some had already been collected and offered to share the data by email.
- H1 plant utilisation and dispatch: Management gave September utilisation of 75%-80% but did not provide the H1 average or MW dispatched.
- Receivables from large EPC contracts: Management said most related to the preceding two months and older receivables were recovered, without quantifying the contract share.
- DCR cell economics: Management confirmed DCR supply and discussed market availability, but gave no module-cost or manufacturing-margin impact.
- H2 and FY28 order-book revenue: Management quantified more than 60%-70% execution within the year but gave no H2 revenue or FY28 split.
- H1 captive versus external module split: Management said about ₹90 cr was captively consumed but gave no actual percentage split or external-sales amount.
Every question, with its answer
1. Large EPC contracts
Nayan Agarwal, SIC Wealth Management
Question. The two 50 MW contracts represent roughly ₹375 crores, or about 80% of the EPC order book. Who are the customers, what are the payment terms, and what execution or counterparty risks apply?
Answer, Himanshu Garg. The contracts are with the Maharashtra State Government DISCOM/Mahagenco. Payments are milestone-linked, with the project value split into about 10-12 milestones and payment generally received 15-30 days after each milestone; land acquisition was given as an early billable milestone. The respondent did not quantify delay, performance or counterparty risk.
Partly answered.
2. Borrowing and finance cost
Nayan Agarwal, SIC Wealth Management
Question. Does the company expect borrowing and full-year finance costs to increase further from the current level?
Answer, Himanshu Garg. Management said it does not expect a further material rise in borrowing or finance cost because most plant funding is already in place, ALMM is operational and working-capital needs have peaked. Finance cost should remain broadly similar to that of recent months.
3. DCR cell supply
Nayan Agarwal, SIC Wealth Management
Question. Has Solarium signed with a domestic cell supplier, and how will DCR cells affect module costs and manufacturing margins?
Answer, Himanshu Garg. Management confirmed that its first DCR supply had been secured. Industry cell supply was already above 50 GW and management expected the earlier supply-demand gap to narrow over the next 6-9 months; the strict implementation deadline had also been extended from June to December 31. It did not quantify the effect on module cost or manufacturing margin.
Partly answered.
4. Order-book execution
Nayan Agarwal, SIC Wealth Management
Question. How will the more than ₹700 crore order book be executed, what revenue is expected in H2 FY27, and how much will be delivered in FY28?
Answer, Himanshu Garg. Most of the order book should execute during FY27, led by the two large contracts. When the analyst proposed 50%-60% execution this year, management said it would be more than 60%-70%. No FY28 order-book split or H2 revenue figure was provided.
Partly answered.
5. Receivables and working capital
Yug Jain, Individual Investor
Question. How should the rise in receivables from about ₹152 crores in March to almost ₹282 crores be reconciled with the earlier low-working-capital guidance, and how much relates to the two large EPC contracts?
Answer, Himanshu Garg. Management said receivables broadly tracked revenue growth, most older balances had been recovered, and a majority of the ₹280-plus crore balance related to module dispatches during the two months following ALMM listing rather than long-outstanding amounts. It did not quantify how much was linked to the two EPC contracts.
Partly answered.
6. Post-quarter collections
Yug Jain, Individual Investor
Question. How much has the company collected from receivables after September 30?
Answer, Himanshu Garg. Management said the exact post-September collection figure was not available on the call, although a significant amount had already been collected. It offered to share the detailed number separately by email.
Not answered directly.
7. Module-plant utilization
Yug Jain, Individual Investor
Question. What was average module-plant utilization in H1, and how many megawatts were dispatched during the half?
Answer, Himanshu Garg. Management said an H1 average was difficult to interpret because the plant was largely unutilized during the first couple of months while awaiting ALMM enlistment. Utilization was about 75%-80% in September, but the MW dispatched during H1 was not disclosed.
Partly answered.
8. Residential cash-flow cycle
Yug Jain, Individual Investor
Question. Under a PM Surya Ghar home loan, what is the sequence of cash flows between the household, bank and Solarium, and does the subsidy ever remain on Solarium's books?
Answer, Himanshu Garg. Management said the subsidy never sits on Solarium's books. For private NBFC financing, disbursement generally occurs before materials are dispatched from the warehouse, while for public-sector banks dispatch occurs only after the installation is complete.
9. ALMM-II order protection
Yug Jain, Individual Investor
Question. How much of the approximately ₹260 crore module order book requires commissioning by December 31 under ALMM-II, and would orders be lost if projects slipped into January?
Answer, Himanshu Garg. Management said the entire module order book relates to non-DCR imported cells and remains permitted under the relevant implementation framework even beyond December 31, 2026. It said the order book would remain intact if supply slipped to the deadline.
10. Solar Kits revenue
Yug Jain, Individual Investor
Question. How much revenue did Solar Kits generate in H1, and in which reported segment is it included?
Answer, Himanshu Garg. Kits began operating only in mid-August. Management said Solarium generated approximately ₹4.5-5 crores of Kits revenue from mid-August through September 30, which is currently reported within the residential business.
11. EBITDA-margin guidance
Garima Jain, Individual Investor
Question. Does management still stand by the prior guidance of 9%-9.5% EBITDA-margin protection and a 10%-12% FY27 exit, and what H2 margin is needed after H1 EBITDA margin was around 8%?
Answer, Himanshu Garg. Management attributed the consolidated margin decline to the shift toward lower-margin EPC and module sales, while claiming segment-level margins had not deteriorated. It estimated ₹4.5-5 crores of fixed costs were incurred without corresponding production during roughly three months of ALMM-related underutilization; without that delay, H1 EBITDA margin would have been about 9.5%-10%. Management remained confident of 9%-10% in H2 but did not explicitly reaffirm the 10%-12% FY27 exit ambition.
Partly answered.
12. EPC subcontracting economics
Garima Jain, Individual Investor
Question. Can management explain the subcontracting of both 50 MW contracts, including the roughly ₹35 crore spread, module sourcing, Solarium's site role, delay risk and execution timetable?
Answer, Himanshu Garg. Management confirmed the subcontracting structure and said the spread had been secured but was not yet recognized in the books. The structure materially reduces Solarium's working-capital exposure, requires the projects to use Solarium modules and fixes the module supply price and margin. Execution is targeted by the end of March 2027, although the detailed site role and allocation of delay risk were not explained.
Partly answered.
13. Equity raise and listing roadmap
Garima Jain, Individual Investor
Question. Is there any plan to raise equity or migrate the company to the main board during the next 12 months?
Answer, Himanshu Garg. Management said a further equity raise was not currently on the cards. It may assess future funding needs if contract execution and the next stage of growth require capital, but there was no active discussion or timetable. The main-board migration question was not addressed.
Not answered directly.
14. Residential run rate and strategy pivot
Garima Jain, Individual Investor
Question. The prior call indicated ₹10-12 crores of monthly residential revenue excluding Kits and ₹16-18 crores including Kits by December, versus only ₹37.6 crores in H1. Why did the run rate fall, what is it now, and does the new figure include Kits?
Answer, Himanshu Garg. Management said expanding company-operated warehouses created fixed costs that weakened near-term residential profitability. It therefore pivoted toward Kits and city distributors to preserve EBITDA margins with a lower fixed-cost base, while residential gross margin remained about 35%-40%. Management added that deeper execution in Gujarat could lift revenue materially but declined to provide a numerical commitment.
Follow-up. Can you just reconfirm the run rate that is today?
Answer. The current run rate is about ₹4-5 crores per month excluding Kits and approximately ₹8-10 crores per month including Kits over the next 1-2 months.
15. Module order pipeline
Garima Jain, Individual Investor
Question. What is the update on the 300 MW module-manufacturing pipeline discussed on the previous call?
Answer, Himanshu Garg. Management confirmed approximately ₹260 crores of module-supply orders in hand. Larger discussions were continuing, but they remained forward-looking, and no specific update was provided on the previously discussed 300 MW pipeline.
Partly answered.
16. Captive versus external module sales
Shikha, Individual Investor
Question. What was the H1 split between captive module consumption and external sales, and how confident is Solarium of selling the balance of its 1.23 GW capacity given the 217 GW ALMM-listed industry capacity?
Answer, Himanshu Garg and Ankit Garg, Chairman & Managing Director for Ankit Garg's portion; Himanshu Garg's designation was not stated. Himanshu Garg said captive consumption remained low because the plant was largely idle during the first months, with about ₹90 crores of modules consumed captively, although the share was expected to rise as projects progressed. Ankit Garg said the 217 GW figure was nameplate capacity that included M10 products contributing about 35% of the listed capacity and likely to be removed as the supply chain shifted toward G12. DCR capacity had risen from 20 GW to 42 GW in six months, and management did not currently see a cell shortfall.
Partly answered.
17. Segment gross margins
Shikha, Individual Investor
Question. What are the gross margins for the EPC, manufacturing and residential segments?
Answer, Himanshu Garg. Management provided gross-margin ranges of approximately 35%-37% for residential, 25% for the C&I and Government segment and 14%-15% for manufacturing.
18. Plant economics and break-even
Shikha, Individual Investor
Question. What is the module plant's fixed cost per half, including people, power, interest and depreciation, and at what utilization does it break even at EBITDA and PAT levels?
Answer, Himanshu Garg. Management declined to provide the plant's fixed-cost and break-even economics on the call because it required more detail and offered to answer separately.
Not answered directly.
19. Solar Kits unit economics
Shikha, Individual Investor
Question. How does the city-distributor model work, who holds inventory, what margin does a distributor earn, and what working capital is required?
Answer, Himanshu Garg. Solarium sources 25 kit items in batches of roughly 100, 500 or 1,000 and supplies distributors in truckload lots. Inventory remains on Solarium's books until dispatch to installers. Management expects a 15%-18% gross margin and 10%-12% EBITDA margin at scale, although the total working-capital requirement was not quantified.
Partly answered.
20. FY27 revenue guidance
Yug Jain, Individual Investor
Question. What full-year FY27 revenue target is management setting after H1 revenue of ₹310 crores and a ₹720.9 crore order book?
Answer, Himanshu Garg. Management explicitly declined to provide an FY27 revenue target, saying it was too early. It nevertheless expected similar growth to continue with the addition of module sales over the next half after losing a couple of months to the delayed manufacturing start.
Not answered directly.
21. PAT-margin outlook
Yug Jain, Individual Investor
Question. What PAT margin should investors expect for FY27 after the H1 PAT margin of roughly 3.4%-3.5%?
Answer, Himanshu Garg. Management indicated that PAT margin could return to approximately 5%-6% as the lost module-sales contribution resumes. It did not clearly distinguish whether the range applies to H2 FY27 or the full year.
Partly answered.
What was said
Topic by topic, in the order it was spoken
Integrated Four-Business Model · Ankit Garg (Chairman & Managing Director)
- H1 FY27 was the first half in which manufacturing, large EPC, residential installations and Solar Kits operated together.
- The integrated model allows Solarium to use captive modules in its own EPC, residential and Kits businesses while selling surplus output externally.
- Ankit said H1 revenue had already exceeded the company's full FY25 revenue before handing the financial review to Rohit Jindal.
Rooftop Solar Policy Tailwinds · Ankit Garg (Chairman & Managing Director)
- PM Surya Ghar had benefited 50 lakh households with 14.8 GW of rooftop capacity, according to the August 2026 MNRE release cited by management.
- The Union Budget allocated ₹22,000 crores to PM Surya Ghar for FY27, compared with a revised ₹17,000 crores for FY26.
- A GST reduction from 12% to 5% on modules, inverters and balance-of-system items became effective September 25, lowering household installation costs.
Module Manufacturing Ramp-Up · Ankit Garg (Chairman & Managing Director)
- The 1.23 GW automated module line at Miroli, Ahmedabad was commissioned in March 2026 and produces TOPCon and PERC bifacial modules up to 725 Wp in G12 format.
- ALMM-I enlistment in July 2026 allowed Solarium to begin supplying modules; manufacturing generated revenue for only about 2-2.5 months against six months of fixed costs.
- Management expects higher utilization to absorb the fixed-cost base as module volumes increase.
- Solarium's own panels carry the consumer-facing brand and account for roughly 60% of the value of a rooftop system.
Large EPC Strategy and Order Book · Ankit Garg (Chairman & Managing Director)
- Solarium won two 50 MW AC ground-mount contracts in April 2026 valued at ₹188.5 crores and ₹186.5 crores.
- The two awards create approximately 130 MW DC of captive module offtake for the Miroli plant.
- Management has stopped bidding for distributed rooftop tenders and now focuses on a limited set of technically demanding, single-site projects.
- The order book reached ₹720.9 crores, comprising ₹461.1 crores of EPC and ₹259.8 crores of module supply, compared with about ₹300 crores discussed in June.
- Management cited projects for BARC, the Indian Air Force, Border Security Force, MES, NTPC and Gujarat Urban Business Development, including high-altitude sites in Leh.
Residential Business and Market Position · Ankit Garg (Chairman & Managing Director)
- Solarium continued to manage the full residential customer journey, from enquiry and survey through financing, installation, net-metering approval and subsidy claims.
- Management described residential installations as its highest-margin business.
- Solarium was registered on the PM Surya Ghar portal with over 11,400 installations and a 4.8-out-of-5 rating.
- The company received the Urja Chakra for the second position in India for residential installations under the government scheme.
- DRDO certified Solarium's absorption of solar thermal technology for heating shelters in cold conditions, with a license running through January 2036.
Solar Kits and Distributor Expansion · Ankit Garg (Chairman & Managing Director)
- Solarium Kits launched during H1 as a 25-item branded package with five years of insurance on the installed system.
- The kit model was designed to reach empanelled installers and smaller vendors that Solarium's own teams cannot serve economically.
- Exclusive city distributors were being appointed from July, starting with Surat, Rajkot, Anand, Pune, Kota and Kolkata.
- The distributor model seeks to preserve residential margins while reducing the fixed costs associated with company-operated warehouses.
Second-Half Operating Priorities · Ankit Garg (Chairman & Managing Director)
- Raise utilization of the newly ALMM-listed module plant and spread fixed costs over larger production volumes.
- Complete the two large ground-mount EPC contracts on schedule.
- Scale the Solarium Kits distribution network across additional states and cities.
- Reduce receivables as EPC milestones are achieved and customer collections are received.
H1 Financial Performance and Mix · Rohit Jindal (Chief Financial Officer)
- Segment mix was 47.6% C&I and Government projects, 36.5% manufacturing, 12.1% residential and 3.7% product sales.
- Gross margin compressed because the revenue mix shifted toward lower-margin EPC and module sales rather than residential installations.
- Employee and other expenses grew much more slowly than revenue, although plant underutilization kept EBITDA margin below the prior-year level.
- Finance costs increased because of the module-plant term loan and working capital supporting manufacturing and EPC execution.
- Depreciation stepped up as the plant operated for a full half and was available for use.
Borrowings, Receivables and Cash Flow · Rohit Jindal (Chief Financial Officer)
- Total borrowings were ₹189.1 crores, including ₹73.6 crores of long-term loans and ₹115.5 crores of short-term loans, against cash and bank balances of ₹35.6 crores.
- Trade receivables rose to ₹281.9 crores from ₹152 crores in March as revenue and EPC execution expanded.
- Inverter inventories fell to ₹40.7 crores from ₹99.7 crores as modules were dispatched into EPC and external orders.
- Management expects milestone collections to improve cash flow and reduce finance cost as a proportion of revenue.
In their words
This was the first half in which all four parts of our business were operating together
We have stopped bidding for distributed rooftop tenders, where capital is tied up across hundreds of sites and released only after each one is certified.
Utilization of the plant has to rise. Margins have to be recovered as fixed costs are spread over larger volumes. And receivables have to come down as EPC milestones are collected.
To check next time
What management committed to on this call, or the dates they gave.
- Plant utilisation: whether September's 75%-80% level is sustained as management raises utilisation.
- H2 FY27 EBITDA margin: delivery of the 9%-10% range.
- FY27 PAT margin: progress toward the 5%-6% range as module sales recover.
- Large EPC: progress on the two 50 MW contracts and more than 60%-70% order-book execution by FY27-end.
- Receivables and finance cost: reduction from ₹281.9 cr and improvement in finance cost as a share of revenue.
- Solar Kits: whether monthly revenue reaches ₹8-10 cr including Kits over the next 1-2 months.
Transcript
Read along with the recording
The whole call, 195 lines from 8 speakers over 55:15. Click any line to hear it, jump to the Q&A, or find a word. Free with an account.
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Tue 17 Nov 2026 | ₹99.06 | −0.37% | +0.38% |
From the close of Mon 16 Nov 2026, ₹99.43: the call began at 18:00 IST, after the market closed, so that day's close is the base. Adjusted daily closes; the move includes everything else that happened in those sessions.