GR Infraprojects has issued a notice of termination to NTPC Limited for an EPC contract signed on 23 April 2026. The contract covered Battery Energy Storage System implementation at NTPC's Mouda Super Thermal Power Station (Lot-1). The termination is due to continuing Force Majeure and War Risk circumstances and contractual issues. Financial impact is being assessed and the company has invoked the dispute resolution mechanism.
Contract loss may dent near-term revenue; financial impact under assessment. Likely negative short-term sentiment.