Deccan Gold Mines Q4 FY26 earnings call

Tue 19 May 2026DECNGOLD

In brief

Deccan Gold raised ₹315 cr via rights issue, became debt-free; Jonnagiri sold first gold; Altyn Tor full production due August 2026

Management's tone
Optimistic
What was said
Leaned positive
Guidance
First guidance issued
Analyst pushback
High
Stock, next session
+11.55% (Nifty 50 −0.14%)
  • Management needs additional ₹60-100 cr to complete Kyrgyzstan, plus ~₹1,000 cr over 1-2 years for Bhalukona (₹400 cr plant) and Spain (₹500 cr).

An AI read of the company's transcript · the filing

The numbers

The quarter, Q4 FY26

This quarterA year agoLast quarterMargin
Revenue₹0.6 cr+5300.0%+1348.8%
EBITDA (excl. other income)₹-10 cr——-1690.6% (-196772.7% a year ago)
Net profit₹7.6 cr−47.2%—1283.3% (131318.2% a year ago)
EPS (₹)₹0.44−43.6%—

From the company's filed results for the quarter ended 31 Mar 2026 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

Where management's figures differ from the filing

  • Other income (Q4 FY26): said ~₹18.3 cr interest income plus ~₹13 cr forex gain (~₹32 cr total); filed ₹8.74 cr. Management's ~₹32 cr split likely refers to full-year FY26, while filed Q4 standalone Other income is ₹8.74 cr; not consolidated to quarter.

What moved the numbers, as management explained it

  • Rights issue of ₹315 cr closed; ~₹219 cr used to retire debt (Hira Group + Godavari Power & Ispat largest), making Deccan debt-free by FY26-end. (one-off)
  • First gold sales from Jonnagiri trial (~100 kg by March 2026) flowed as 26% share of associate Geomysore's first profit — defining quarter for revenue recognition. (one-off)
  • ~₹55 cr of rights-issue proceeds diverted into Geomysore to maintain the 26% stake (originally earmarked for Kyrgyzstan), creating an additional ~₹60-100 cr funding gap for Altyn Tor.
  • Other income ~₹18.3 cr interest (15% on Kyrgyzstan debt) plus ~₹13 cr forex gain (dollar-denominated loan to Altyn Tor).
  • EBITDA before other income negative (~₹10 cr) reflecting pre-revenue cost base across India HQ + overseas project offices.
  • Net profit to owners of ₹7.62 cr includes other income (interest + forex) on top of small associate share; revenue of just ₹0.59 cr since Jonnagiri is associate (not consolidated). (accounting)

The numbers management led with

  • Rights issue proceeds: ₹315 crore raised in rights issue
  • Debt repayment: ₹219 crore of debt repaid; company became debt-free
  • Jonnagiri production guidance: 600kg in FY27, 800kg in FY28, 1 ton/year peak
  • Jonnagiri revenue guidance: ₹900 crore revenue in FY27
  • Kyrgyzstan production guidance: 160kg in FY27; 300-350kg in FY28; 700-800kg beyond as underground mining starts
  • Kyrgyzstan funding requirement: ₹100 crore outer limit (₹60 crore minimum) needed in next 3 months

Guidance

Guidance on this call

WhatForWhat management said
Debt-free status (Deccan Gold (consolidated))FY26Company becomes debt-free by end-FY26 after ~₹219 cr repayment from rights issue
Jonnagiri FY27 revenue (Jonnagiri Gold (Geomysore))FY27FY27 revenue ~₹900 cr at current prices
Jonnagiri FY27 EBITDA margin (Jonnagiri Gold (Geomysore))FY27FY27 EBITDA margin ~75%
Jonnagiri FY27 PAT (Jonnagiri Gold (Geomysore))FY27FY27 PAT ~₹470 cr
Deccan attributable PAT from Jonnagiri FY27 (Jonnagiri Gold (Geomysore))FY2726% to Deccan equivalent ~₹120 cr
Jonnagiri FY27 production (Jonnagiri Gold (Geomysore))FY27FY27 production ~600 kg
Jonnagiri FY28 production (Jonnagiri Gold (Geomysore))FY28FY28 production ~800 kg, could be 1 ton
Jonnagiri peak production (Jonnagiri Gold (Geomysore))FY29Peak ~1 ton/year within next couple of years
Altyn Tor FY27 production (conservative) (Altyn Tor (Kyrgyzstan))FY27FY27 conservative ~160 kg starting August
Altyn Tor FY28 production (Altyn Tor (Kyrgyzstan))FY28FY28 production 300-350 kg
Altyn Tor FY27 revenue (Altyn Tor (Kyrgyzstan))FY27FY27 revenue ~₹300 cr
Altyn Tor FY27 PAT (Altyn Tor (Kyrgyzstan))FY27FY27 PAT ~₹100 cr (60% to Deccan ~₹60 cr)
Altyn Tor FY27 PAT margin (Altyn Tor (Kyrgyzstan))FY27FY27 PAT margin ~30%
Altyn Tor steady-state PAT margin (Altyn Tor (Kyrgyzstan))FY30Going forward PAT margin 40-45%
Altyn Tor EBITDA margin (peak) (Altyn Tor (Kyrgyzstan))FY30Peak EBITDA ~70-75%
Bhalukona indicative resource (Bhalukona Ni-Cu-PGE)FY27Indicative Ni-equivalent resource 70,000-80,000 tonnes
Bhalukona possible first production (Bhalukona Ni-Cu-PGE)FY29Possible first production ~FY29 after 18 months from lease
Bhalukona processing plant capex (Bhalukona Ni-Cu-PGE)FY28Bhalukona processing plant capex ~₹400 cr
Tungsten (Spain) processing plant capex (Logrosán Tungsten-Tin (Spain))FY29Spain processing plant capex ~₹500 cr
Bhalukona mining lease application (Bhalukona Ni-Cu-PGE)FY27Mining lease application by April 2027
Tungsten (Spain) mining lease application (Logrosán Tungsten-Tin (Spain))FY27Mining lease application by Oct/Nov 2026
Altyn Tor full production (Altyn Tor (Kyrgyzstan))FY27Full-scale commercial production by August 2026; inauguration Aug 15 or Aug 31
2030 Deccan share of gold + gold-equivalent (Deccan Gold (consolidated))FY30~5 tons gold + gold-equivalent by 2030
Larger funding plan FY27-FY28 (Deccan Gold (consolidated))FY27-FY28~₹800-1,000 cr (~$100m) over next 1-2 years via equity + debt

What changed since the Thu 20 Nov 2025 call

WhatOn the Thu 20 Nov 2025 callOn this call
Rights issue of ₹315 cr (achieved)~₹315 cr rights issue announced; awaiting BSE principal approval₹315 cr raised; ~₹219 cr used to repay debt; company now debt-free
Altyn Tor (Kyrgyzstan) FY27 production (cut)~350 kg/yr steady-stateConservative ~160 kg for FY27; rising to 300-350 kg in FY28
Altyn Tor full-scale production start (delayed)Trial production within ~2 weeks; full ramp post-February 2026Gravity circuit commissioned; Merrill-Crowe by June, full leaching by end-July, full production by August 2026
Jonnagiri FY27 production (held)500-750 kg FY27; eventual peak ~1 ton/yr~600 kg FY27, ~800 kg FY28, possibly 1 ton
Jonnagiri FY27 financials (new on this call) (new)Not separately quantifiedRevenue ~₹900 cr, EBITDA ~₹630 cr (~75%), PAT ~₹470 cr; 26% to Deccan ~₹120 cr
Bhalukona Ni-Cu-PGE project (new)Not discussedDiscovery with drill hits incl. 2.6m at 1.01% Ni, 0.29% Cu; mining lease application April 2027
Logrosán Tungsten (Spain) project (new)Not discussed4 holes / ~1,500m drilled; all hit W-Sn zones; mining lease application Oct/Nov 2026
Kyrgyzstan PAT margin (restated)35-40% steady-state~30% in FY27 rising to 40-45% once high-grade ore accessed in 4-5 years

The business

By business

Jonnagiri Gold (26% via Geomysore, India)

Open-pit mining on east block ongoing; refined 999 gold sold to Indian jewellers; ~100 kg produced by March 2026 (~30 kg/month); profitability already flowing through to Deccan; expansion beyond 1,000 tpd requires public hearing.

~100 kg refined gold produced by March 2026 · ~30 kg/month produced March/April · FY27 production ~600 kg · FY27 revenue ~₹900 cr · FY27 EBITDA ~₹630 cr (~75%) · FY27 PAT ~₹470 cr · 26% to Deccan ~₹120 cr · FY28 production ~800 kg, possibly 1 ton · East pit resource ~12 tons · Total resource target ~32 tons

Outlook: FY27 production ~600 kg rising to ~800 kg FY28 and possibly 1 ton; peak ~1 ton/yr; resources targeted to 32 tons (~1 Moz) in ~1 year; expansion beyond 1,000 tpd pending public hearing.

Altyn Tor Gold (60%, Kyrgyzstan)

Gravity circuit commissioned; producing concentrates; Merrill-Crowe circuit to commission in June for Doré bar; full leaching circuit and tailing dam by end-July; full-scale commercial production targeted August 2026; FY27 production guided conservatively at ~160 kg.

FY27 production ~160 kg (conservative) · FY28 production 300-350 kg · 700-800 kg from high-grade mine in 4-5 years · FY27 revenue ~₹300 cr · FY27 PAT ~₹100 cr · Deccan 60% share ~₹60 cr · AISC ~$1,054/oz · Royalty 5% + 14% revenue share to government · Peak EBITDA ~70-75% · Peak PAT margin 40-45% · ~1.6 mt tailings + low-grade stockpiles

Outlook: Full production start August 2026 (inauguration Aug 15 or Aug 31); gravity concentrates → Doré bar June 2026; FY27 ~160 kg conservative, rising to 300-350 kg FY28 and 700-800 kg once high-grade mine accessed in 4-5 years; underground (3-4 yrs) for ~800 kg peak.

Bhalukona Ni-Cu-PGE (100%, Chhattisgarh)

First-ever drill program on 30 sq km composite license; 7 holes / 1,200m completed; hole-1 intersected 30m ~0.4% Ni incl. 2.6m at 1.01% Ni, 0.29% Cu, 0.2 g/t Pd; air-mag and ground geophysics support 200-300m depth; mining lease application targeted April 2027.

1,200m diamond core drilled · 7 holes complete · Hole-1: 30m ~0.4% Ni · Hole-1: 2.6m at 1.01% Ni, 0.29% Cu, 0.2 g/t Pd · Composite license 30 sq km · Indicative resource 70,000-80,000 t Ni-equivalent · Plant capex ~₹400 cr · Possible production ~FY29 · Mine life ~15 years

Outlook: Fast-track mining lease application by April 2027; indicative resource of 70,000-80,000 t Ni-equivalent (~7-8 t gold equivalent); 2,000-3,000 tpd plant for ~₹400 cr; possible first production around FY29.

Kalevala Gold (Finland, up to 51%)

Three projects (Syrjäla, Pahkalampi, 4P) held via Mineral Exploration Network; combined resource target ~6-7 t; one mining license being pursued; deferred drilling until Kyrgyzstan commissioned.

Syrjäla resource ~2 t · Pahkalampi resource ~2 t · 4P four zones identified · Average grade 5-10 g/t · Total target ~6-7 t · Future capex ~₹500 cr · Stake up to 51% (eventually subsidiary)

Outlook: Deferred drilling to focus funds on Kyrgyzstan, Bhalukona, Spain; mining license pursued subject to environmental clearances; underground operation expected; possible production by 2030.

Mozambique Lithium-Tantalum and Copper-Gold (100%)

Surface work identified 4-5 pegmatite zones for lithium-tantalum (targeting >4% Li concentrate); Tete Province copper-gold anomalies up to 10 g/t Au and 3.85% Cu; drilling deferred pending funds.

Highest Cu-Au samples: 10 g/t Au, 3.85% Cu · Target 100 tpd processing plant · Planned scale to 1,000 tpd / 3 mt ore · 2-3 year scale timeline

Outlook: Drilling to commence soon (Bhalukona + tungsten funded first); 100 tpd plant for next year with scaling to 1,000 tpd over 2-3 years; lithium demand rising 9x in India.

Logrosán Tungsten-Tin-Gold (Spain, up to 95%)

MoU with Mineral Exploration Network via Dubai entity; targeting 51% for €1.76m, up to 95% over phases; 4 holes / ~1,500m drilled, all intersecting tungsten-tin zones; UV-visible scheelite in core; prior drill hits incl. 8m at 0.32% WO₃.

~1,500m drilled, 4 holes · Prior hits: 8m at 0.32% WO₃ · 3m at 0.42% WO₃ · 1m at 96.2 g/t Au · Tungsten mineralization to ~300m depth · 51% for €1.76m · up to 95% via phases · Plant capex ~₹500 cr · Mining lease application by Oct/Nov 2026

Outlook: Mining lease application by October/November 2026; assays pending in ~10 days; capex ~₹500 cr; potential 'Bhalukona of Europe' per management.

Tanzania Gold (100%, exploration)

3 of 5 tenements relinquished after surface sampling failed to identify continuous mineralized zones; 2 retained for follow-up work; reduced focus due to funding and better results elsewhere.

5 original licenses · 3 relinquished · 2 retained · Stake-up to 51% (eventually subsidiary)

Outlook: Re-enter exploration on 2 retained tenements in FY27; full focus deferred to Kyrgyzstan, Bhalukona, Spain.

Ganajur Gold (India, under litigation)

Under litigation at Supreme Court alongside Indocil; additional articulations made to state/centre/NITI Aayog/PMO given India's gold import curbs; case hearings scheduled post court holidays.

30-month timeline to production if case won · Potential 8-9 month saving if env clearance in 6 months

Outlook: Strategy: common approach with Indocil, policy advocacy; awaiting next court hearings post summer recess.

Balance sheet, capex and funding

  • Rights issue ₹315 cr raised; ₹219 cr repaid debt (Hira Group + Godavari Power & Ispat), ₹32 cr invested into Kyrgyzstan, ₹55 cr into Geomysore rights (to hold 26%); company now debt-free.
  • Additional funding need: ~₹60-100 cr for Kyrgyzstan completion (deadline EGM day-after-call for related-party transaction approval).
  • Bhalukona processing plant capex ~₹400 cr (~1,000 tpd reference from Jonnagiri); possible production FY29; mining lease application April 2027.
  • Spain Tungsten plant capex ~₹500 cr; mining lease application Oct/Nov 2026.
  • Larger funding planned ~₹800-1,000 cr (~$100m) over next 1-2 years via equity + debt (FPO + debt), timed after Kyrgyzstan commissioning + Bhalukona/Spain drill results.
  • Kyrgyzstan investments booked as debt at 15% interest; will repay from project revenues; underground capex ~₹50-100 cr (decline) funded from internal accruals.

The industry, as management sees it

India is actively debating gold import restrictions and self-sufficiency; domestic gold production saves ₹1,500 crore in forex per ton; government increasingly supportive of domestic mining as gold imports have increased nine-fold. Kyrgyzstan's gold mining sector contributes 10% of government revenue, making it a priority sector with strong JV partner support from Kyrgyzaltyn (government-owned).

Risks management named

  • Ganajur project remains in Supreme Court; Indocil case outcome uncertain; government policy intervention being sought
  • Kyrgyzstan weather delays: winter conditions (minus 30°C) halt civil construction; money transfer delays from Indian banks up to a month
  • Funding gap: ₹400-500 crore required for Bhalukona processing plant; ₹800-1,000 crore total needed across projects by 2030
  • Jonnagiri expansion to 2,000 tpd requires public hearing and environmental approvals (6-8 months for clarity)
  • Tanzania exploration yield insufficient continuous zones; two tenements retained, focus reduced

Q&A

Q&A was exceptionally active with 23 analyst/investor questions covering funding strategy, project timelines, unit economics, governance, and capital allocation. Strongest pushback came from Deviinder Gupta (NIPCCD) on shareholder communication failures, unanswered emails, and the need for a concrete capital raise blueprint; he also disclosed Mark Creasy's rights issue participation and advocated for a Dhanteras FPO at ₹10 EPS with a 45x PE multiple. Multiple investors probed the Bhalukona drill results and resource potential, the ₹100 crore Kyrgyzstan funding gap, and whether internal accruals could bridge the gap. Management gave direct answers on costs, margins, and timelines but was deflective on promoter identity specifics and deferred Rajiv Agarwal's questions due to audio issues.

Not answered directly

  • Employee cost sequential decline — inaudible questions from Rajiv Agarwal
  • Specific promoter identity beyond 'Australian' — declined to name

Asked for a number, answered without one

  • Potential revenue from Tungsten and Bhalukona in 3 years: For Tungsten, management said 'too early' to provide numbers; for Bhalukona, gave only 'very, very indicative' geological numbers that could 'significantly change with drilling'.
  • Bhalukona lease-to-production timeline: Bhalukona mining lease by April 2027 (next April); construction ~18 months so possible first output ~FY29; Tungsten lease by Oct/Nov 2026; no consolidated roadmap given.
  • FY28-FY30 profit and total funding split equity/debt: Management gave ~₹180 cr combined for FY27 only (Jonnagiri + Kyrgyzstan) and ~₹800-1,000 cr (~₹1,000 cr) total funding need but did not split FY28-FY30 or equity vs debt.
  • Geomysore IPO or value unlock: No formal board decision; 'possibility' of IPO being 'frequently discussed' but nothing concrete; no immediate dilution in Geomysore as Jonnagiri expansion funded from internal accruals.
  • FY27 gold-price assumption for guidance: Management said calculations use ~₹15,000/g (~$4,000/oz after discount of ~$500) — below market; not tied formally to FY27 P&L guidance numbers.
  • Jonnagiri cost of production: Stated ~₹3,000/g production cost vs ~₹16,000/g market = ~75% gross margin; no per-ounce AISC disclosed for Jonnagiri (only Kyrgyzstan ~$1,054/oz).

Every question, with its answer

  1. 1. Hedging policy

    Aditya Bhutra, Avora Advisors

    Question. What hedging policy is being adopted given topline exposure to global gold price fluctuations?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. All cash flow projections use conservative assumptions: ₹15,000/gram for India (below current market price) and ~$4,000/oz for Kyrgyzstan (below LBMA/LME). No formal hedging policy is in place as the discounted assumptions provide a buffer against gold price falls.

  2. 2. Royalty rates and unit economics

    Raman KV, Sequent Investments

    Question. What is the government duty/royalty rate in India and Kyrgyzstan? What is the unit economics — cost per gram to produce gold vs market price, and revenue-to-EBITDA flow?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. India: 4% royalty to Andhra Pradesh government + 1.28% district mining fund and National Mineral Exploration Trust = 5.28% total from top line. Kyrgyzstan: 5% royalty to government. Unit economics: at ~1 gram per tonne feed grade, production cost is ~₹3,000/gram; current market price ~₹16,000/gram — EBITDA margin ~70-75%. Kyrgyzstan all-in-sustaining cost ~$1,054/oz at $4,000 gold price; PAT margin ~30-35% in FY27, improving to 40-45% in FY28.

  3. 3. Production costs, other income, gold sales, Finland ownership

    Charchit Maloo, Genuity Capital

    Question. Three questions: (1) Are there production issues due to crude price increases? (2) What is the breakup of other income? (3) Who are you selling the 100kg gold to and at what realization? (4) Who are the other owners in the Finland project?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. (1) Crude impact minimal — <5% on overall cost; Kyrgyzstan fuel sourced from Kazakhstan at lower prices than India. (2) Other income: ~₹18.3 crore interest income (on loans to subsidiaries at 15%) + currency exchange gains. (3) India: refined 999 gold bars sold to Indian jewellers at Indian Bullion Jewellers Association price. Kyrgyzstan: doré bar sold to National Bank (right of first refusal) at LBMA price minus refining charges. (4) Finland and Spain partner is Mineral Exploration Network, owned by Russian geologists based in Europe.

    Follow-up. Follow-up: Going forward, can we expect the same other income in FY27/FY28?

    Answer. Other income depends on exchange rate movements (dollar-denominated loans) and interest income from subsidiary loans at 15%. Exchange gains arose from USD loans; interest income continues as long as funding is outstanding.

  4. 4. Capex per mine and gold sales format

    Ashit Kothi, Almondz Global Securities

    Question. What are the capex requirements for each mine as they become operational? What is the working capital requirement with multiple locations? How will gold be sold — as doré bar or gold coin?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. 1,000 tpd plant capex (like Jonnagiri): ~₹350-400 crore. Underground mining incremental capex: ₹50-100 crore. India: refined 999 gold bars sold to jewellers. Kyrgyzstan: doré bar sold to National Bank. Working capital managed through internal accruals as projects ramp up.

  5. 5. Cash flows, funding sequencing, Bhalukona capex

    Manish Gupta, MoneyGrow Asset Private Limited

    Question. Three linked questions on cash flows: (1) Will any funds come from Geomysore via dividends or IPO value unlock? (2) Is the ₹100 crore for Kyrgyzstan needed in the next 3 months for construction or post-operational capacity addition? (3) Once both projects are running by end of FY27, can we expect dividend flows, and how do we fund Bhalukona (₹400 crore) without a chicken-and-egg problem?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. (1) Geomysore IPO is a possibility discussed but no board decision; first year no dividends likely as expansion capital needed. (2) ₹100 crore is the outer limit; actual requirement is ~₹60 crore for next 2-3 months (plus contingency). (3) Kyrgyzstan investment is debt at 15% interest — repayments flow back to Deccan from first revenue (not as dividends but as debt repayment). Geomysore PAT (~₹120 crore) may not come as dividends in FY27; use will be for Jonnagiri expansion. Kyrgyz debt repayments will partially fund operations. Bhalukona funding to be planned post-August after drill results confirm resource scale.

  6. 6. Revenue potential of tungsten and Bhalukona; Jonnagiri ramp-up

    Viraj Mahadevia, MoneyGrow Asset Private Limited

    Question. What is the potential revenue generation from the Spain Tungsten and Bhalukona Nickel projects 3 years from now? Can Jonnagiri ramp up to 1 ton+ within 12-15 months?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. Tungsten: too early to quantify; awaiting SA results. Bhalukona: indicative resource of 70,000-80,000 tonnes nickel equivalent (~7-8 tonnes gold equivalent value); 2,000-3,000 tpd plant for ~15 years — numbers are broad geological estimates. Jonnagiri ramp to 1 ton/year is achievable in next 2-3 years as expansion permissions are obtained.

    Partly answered.

  7. 7. Project delay causes and Bhalukona production timeline

    Amish Kanani, Knowise Investments

    Question. Are project delays due to capital constraints, operating environment issues, or manpower/license constraints? When should we look for Bhalukona as a production trigger — what year?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. Jonnagiri delay: additional environmental clearances required in 2024, then construction completion. Kyrgyzstan delay: money transfer delays from Indian banks (up to 15-30 days each), plus winter climate (minus 30°C stops civil construction for 3-4 months). Bhalukona: mining lease application deadline April 2026; drilling and beneficiations tests ongoing; after lease grant, ~18 months to construct processing plant — production possible around 2028-2029 if all goes well.

  8. 8. Promoter funding, financing options, Kyrgyzstan hurdles

    Imran Ghani, Individual Investor

    Question. Which key shareholders/promoters are interested in providing debt or equity? Are they Australian? Why not do a preferential allotment or private placement instead of debt? Are there any visible hurdles for Kyrgyzstan?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. Key promoters are Australian; cannot disclose further details at this stage. Discussions cover both debt and equity options. No visible hurdles for Kyrgyzstan — team of 130 Indian experts deployed from February; remaining work is minor; doré bar production expected from June. Bank transfer delays are the main historical constraint but now managed.

    Partly answered.

  9. 9. Bhalukona and Spain tungsten timelines

    Chirag Khandelwal, Individual Investor

    Question. What is the realistic calendar year to submit the formal mining lease application for Bhalukona? What is the timeline for the Spain Tungsten project?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. Bhalukona: mining lease application by April 2026 (mandatory deadline; may get 6-month extension). Spain Tungsten: mining lease application by October-November 2025. Bhalukona production timeline: ~18 months after lease grant = approximately 2028-2029.

  10. 10. Kyrgyzstan underground capex, Ganajur timeline, overall roadmap

    Aniket Gogate, Individual Investor

    Question. Can we allocate more funds to Kyrgyzstan for underground mining now? What is the capex for underground mining? If Ganajur case is won, what is the indicative timeline and capital requirement? What is the 3-5 year roadmap and capex per mine across all projects?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. Kyrgyzstan underground: cannot start now — need more drilling to design underground operation (takes 1.5-2 years); will be funded from Kyrgyz internal accruals; incremental capex ₹50-100 crore. Ganajur (if Indocil case won): 12-15 months for clearances + 15 months construction = 2.5-3 years to first gold. 3-5 year roadmap: Bhalukona mining lease by April 2026, production ~2028-2029 (₹400 crore capex); Spain lease by Oct-Nov 2025, production ~2028-2029 (₹500 crore capex); Finland underground mining; Mozambique LCT production.

  11. 11. Gold price assumption and Kyrgyzstan PAT margin guidance

    Darshan Chandra, OM Investment

    Question. What gold price assumption is used in FY27 guidance? What is the targeted PAT margin for Kyrgyzstan in FY28 (vs 30-35% this year)?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. Gold price assumption: ₹15,000/gram for India calculations, ~$4,000/oz for Kyrgyzstan (conservative, below market). Kyrgyzstan PAT margin expected to improve from 30-35% in FY27 to 40-45% in FY28 as operational efficiency increases.

  12. 12. Government support and total funding requirement

    Harish, Toro Wealth Managers

    Question. What government support is expected for promoting gold and mineral mining? What is the total funding requirement for the 2030 roadmap across equity and debt?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. India: state government (Andhra Pradesh) actively supporting Jonnagiri — district collector converting government land; 900+ people employed. Kyrgyzstan: government joint venture partner Kyrgyzaltyn handles approvals. Total funding needed: ₹800-1,000 crore (~$100 million) for next 1-2 years across Bhalukona, Spain, and other projects. Planned as equity (FPO/QIP) plus debt; two operating mines will make debt access easier.

  13. 13. Jonnagiri land acquisition, Geomysore dilution, reverse merger

    Manan Shah, Moneybee Investment Advisors

    Question. Has land acquisition at Jonnagiri concluded? Will Jonnagiri self-fund expansion or require further capital from Deccan? Is there risk of further dilution in Geomysore? Any discussions on reverse merger of Geomysore into Deccan?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. Jonnagiri land acquisition ongoing — government land and ceiling land conversion underway with district collector's support. No further investment into Geomysore needed; internal accruals will fund expansion. No further dilution in Geomysore expected. Reverse merger attempt was made previously but did not proceed due to valuation issues; discussions continue but no timeline or guarantee.

  14. 14. Contact details, royalty rates, EBITDA assumptions, strategic investors

    Nikhil Chandak, Shanghvi Family Office

    Question. Please include contact details in presentations — difficult to reach anyone. Can you provide details on royalty rates and operating costs per project to understand EBITDA estimates? Who are Godavari Power and Lloyds — strategic investors or partners?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. Contact details will be added to future presentations. India royalty: 5.28% total; Kyrgyzstan: 5% + 17% revenue share to JV partner. Jonnagiri: production cost ~₹3,000/gram at market price ₹16,000/gram = 70-75% EBITDA. Godavari Power & Ispat and Hira Group are former lenders whose debt was repaid via rights issue proceeds; not strategic partners.

  15. 15. FY28-30 profit trajectory and promoter identity

    Kunal Shah, Heartwood Financial Services

    Question. FY27 profitability ~₹180 crore — what is the trajectory for FY2028-2030? Is the promoter providing debt and equity the Australian promoter?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. FY28-30 trajectory: Jonnagiri PAT grows as production scales to 800kg-1 ton; Kyrgyzstan PAT grows as volumes increase and PAT margin improves to 40-45%; combined growth will be substantial. Promoter is Australian; details cannot be disclosed further at this stage.

    Partly answered.

  16. 16. Kyrgyzstan fund usage, gold end product, nickel sales

    Jhalak Jain, Chhattisgarh Investment Limited

    Question. What is the usage of the ₹100 crore in Kyrgyzstan? Is the end product from Jonnagiri doré bar or refined gold? Where will gold be sold — India or abroad? Where will nickel concentrate be sold?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. ₹100 crore for Kyrgyzstan: completion of leaching circuit, tailing dam, working capital for first 2-3 months. Jonnagiri end product: refined 999 gold bars (not doré). Gold sales: India only (cannot export gold) — sold to jewellers at IBJA price. Kyrgyzstan: doré bar sold to National Bank at LBMA price minus refining charges. Nickel concentrate: to be sold to Indian copper smelters (Adani, Vedanta); Vedanta's license borders the Bhalukona project.

  17. 17. Capital deployment, team utilization, investor communication, Ganajur strategy

    Deviinder Gupta, NIPCCD

    Question. ₹180 crore PAT translates to ~₹10 EPS — how will it be utilized given massive capex needs? I recommended raising ₹1,000 crore earlier; what is the updated capital raise blueprint? What is the team doing post-Kyrgyzstan completion — idle or deployed? Why are investor emails unanswered? What exactly has been done on Ganajur in the past 3 months?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. ₹120 crore from Geomysore may not come as dividends in FY27 (expansion capital needed). Kyrgyz debt repayments (15% interest) will flow back to Deccan from first revenue. Team: process engineers retained to design Bhalukona/Spain plants; site engineers will be recruited into operating projects. Email response policy being formalized and sent to board. Ganajur: (1) coordinating legal strategy with Indocil lawyers, (2) intensified outreach to state/central governments, NITI Aayog, PMO — advocating domestic gold production to save forex (₹1,500 crore/ton saved); detailed steps cannot be disclosed publicly.

    Follow-up. Follow-up: Please confirm Mark Creasy (main promoter of AIR/Rama Mines) participated in the rights issue. Is the team ready for an FPO at 30 days' notice?

    Answer. Mark Creasy's participation in the rights issue is confirmed (learned through own research). FPO paperwork is in advanced stages with merchant bankers; standardized formats ready; will be initiated once resources and budget finalized. Suggested timing: Dhanteras.

  18. 18. Jonnagiri monthly production

    Sandeep Mathivanan, MoneyGrow Asset

    Question. What is the gold production at Jonnagiri for March and April 2026?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. March: ~30 kg; April: ~30 kg (data still being compiled).

  19. 19. Promoter selling activity

    Deepak Pandey, Sagun Capital

    Question. Have past promoters been selling after results/updates? Are any promoters still looking to sell?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. Key promoters (Yandal Investments ~10%, Halcyon ~5%) are not selling. Smaller retail shareholders within promoter group may sell but have had no sales in last 3 months. Mark Creasy contributed to rights issue and is willing to extend further funding. Sales visible in market are from retail shareholders, not key promoters.

  20. 20. Jonnagiri plant visit and cost of production

    Chetan Shah, Prime Corporation

    Question. Can a plant visit to Jonnagiri be arranged? What is the cost of production for Jonnagiri and Altyn Tor?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. Plant visit will be arranged after the Chief Minister's inauguration (planned next month). Jonnagiri production cost: ~₹3,000/gram. Kyrgyzstan all-in-sustaining cost: ~$1,054/oz.

  21. 21. Employee cost, other income, Kyrgyzstan taxes

    Rajiv Agarwal, Sterling Capital

    Question. Why has employee cost declined sequentially for the last two quarters? What constitutes the big increase in other operating income? What royalties and taxes apply to the Kyrgyzstan project?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. Audio quality poor; questions inaudible. Participant asked to rejoin queue.

    Not answered directly.

  22. 22. Next production-ready mine and Bhalukona resource capacity

    Paras Chheda, Purple One Vertex Ventures

    Question. Which is the next mine after Jonnagiri and Kyrgyzstan to come into production? If Bhalukona, what are the expected nickel-copper-PGE resource base and processing capacity?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. Bhalukona is the next project closest to production. Anticipated resource: 70,000-80,000 tonnes nickel equivalent (~7-8 tonnes gold equivalent value). Proposed processing capacity: 2,000-3,000 tpd for ~15 years mine life. Open-pit mining feasible due to wide mineralized zones.

  23. 23. Internal accruals for capex, Bhalukona metal distribution, gold byproducts

    Charchit Maloo, Genuity Capital

    Question. If FY2027-28 generates good cash flows, why can't we fund the ₹100 crore capex from internal accruals? What is the percentage distribution of nickel, copper, and PGE metals in Bhalukona? What other metals are recovered when mining gold and are they saleable?

    Answer, Dr. Hanuma Prasad Modali, Managing Director. No dividends expected from Geomysore in FY27 (expansion capital needed); Kyrgyz debt repayments not yet started. Bhalukona distribution: ~0.4% Ni, ~0.3% Cu, 0.3-0.4 g/t Pd+Pt (PGE as credit). Jonnagiri/Kyrgyzstan/Finnish gold projects: free-milling gold, minimal silver byproduct — not material. Spain tungsten project: gold credits from tin-tungsten intersections (e.g., 1m at 96.2 g/t Au). Bhalukona nickel concentrate to be sold to Indian smelters (Adani, Vedanta).

What was said

Topic by topic, in the order it was spoken

Company Overview & Vision · Dr. Hanuma Prasad Modali (MD)

  • Deccan Gold Mines: India's first company dedicated to gold and critical minerals; listed on BSE and NSE
  • Partner in India's first private gold mine post-independence (Jonnagiri); developing gold mine in Kyrgyzstan
  • Portfolio: 26% in Geomysore (Jonnagiri), 60% in Altyn Tor Kyrgyzstan, 100% Tanzania, up to 51% in Kalevala Gold Finland, 100% Bhalukona (Chhattisgarh), tungsten in Spain
  • Vision by 2030: 2 gold mines operating (1 ton/year each), India's first Nickel-Copper-PGE mine, Mozambique LCT production, Finland and Spain production

Q4 FY26 Highlights · Dr. Hanuma Prasad Modali (MD)

  • ₹315 crore rights issue successfully completed; all outstanding debt (₹219 crore) cleared; company debt-free
  • Geomysore Services (26% associate) started revenue from trial production; refinery set up; first profit recorded
  • Kyrgyzstan: gravity circuit commissioned, producing gold concentrates; Merrill-Crowe circuit to be commissioned June 2026
  • Bhalukona: discovery of Nickel-Copper-PGE mineralization announced to market; first drill hole results released

Jonnagiri Gold Project Update · Dr. Hanuma Prasad Modali (MD)

  • Open pit mining operational at 1,000 tpd; metallurgy simple with >90% gold recovery; results match 2016-18 test work predictions
  • Current resource: 12 tons in east block; drilling active in west and south blocks targeting 32 tons (1 million oz) total
  • Mine life: ~10-12 years for east pit (extendable to 15+ years); production FY27: 600kg refined gold; FY28: 800kg; peak: 1 ton/year
  • FY27 economics: revenue ~₹900 crore, EBITDA 75%, PAT ~₹470 crore; Deccan attributable (26%): ~₹120 crore
  • Expansion to 2,000 tpd requires public hearing and environmental approvals; clarity expected in 6-8 months
  • Refined gold (999 bars) sold to Indian jewellers at Indian Bullion Jewellers Association price

Kyrgyzstan Altyn Tor Project Update · Dr. Hanuma Prasad Modali (MD)

  • Gravity circuit commissioned; Merrill-Crowe (intensive leaching) circuit to be commissioned first week of June 2026
  • Tailing dam and full-scale leaching circuit under construction; target completion: end of July 2026
  • Full commercial production from August 2026; inauguration planned on Aug 15 (India Independence Day) or Aug 31 (Kyrgyz Independence Day)
  • 1.6 million tons of tailings and low-grade stockpiles available at ~1.1 g/t; sufficient for 4 years without new mining; significantly reduces opex
  • Revenue sharing: 83% to company, 17% to Kyrgyz government JV partner (Kyrgyzaltyn); PAT margin ~30-35% in FY27, improving to 40-45% in FY28
  • FY27: 160kg production, revenue ~₹300 crore, PAT ~₹100 crore (Deccan 60% = ₹60 crore); FY28: 300-350kg
  • Underground mining (higher grade >3 g/t) planned after 4-5 years; to be funded from internal accruals; incremental capex ₹50-100 crore
  • 130 Indian experts deployed on site with large local team; revised resource estimate to be submitted to state reserve by end of June 2026

Bhalukona Nickel-Copper-PGE Project · Dr. Hanuma Prasad Modali (MD)

  • 30 sq km composite license (seamless prospecting to mining lease); 100% owned by Deccan Gold Mines
  • Rock chip sampling, drone-based magnetic surveys, NGRI geophysical surveys completed; targeting mineralization up to 500m depth
  • 1,200m diamond core drilling completed across 7 drill holes; 1.3 km mineralized zone covered
  • Hole 1: 3 mineralized layers totalling 60m width; 30m of potentially economic sulphide mineralization at 0.4% Ni; high-grade zone: 2.6m at 1.01% Ni, 0.29% Cu, 0.2 g/t Pd
  • All drill holes contain disseminated and massive sulphide mineralization; massive sulphides yield >1% Ni
  • Mineralization proven to 200m depth in holes 2 and 3; open at depth
  • Target: prove open-pit mineable resource; apply for mining lease by April 2026; processing plant capex ~₹400 crore
  • Anticipated resource: 70,000-80,000 tonnes nickel equivalent (~7-8 tonnes gold equivalent); plant capacity 2,000-3,000 tpd for ~15 years
  • Concentrate to be sold to Indian copper smelters (Adani, Vedanta); Vedanta license borders the project site

Finland, Mozambique, Tanzania & Spain Projects · Dr. Hanuma Prasad Modali (MD)

  • Kalevala Gold (Finland): 3 project areas; Syrjäla (~2 tons, expanding to 4 tons), Pahkalampi (~2 tons at 3.5 g/t), 4P (4 zones, no drilling yet); central processing plant planned; mining license applications in progress
  • Mozambique: LCT exploration (4-5 pegmatite zones identified, drill targets ready) and copper-gold in Tete Province (best surface result: 10 g/t Au, 3.85% Cu); drilling on hold due to funding focus on other projects
  • Tanzania: 3 tenements relinquished; 2 retained with encouraging values; exploration focus reduced
  • Spain Logrosan Tungsten: MoU signed for up to 95% stake (€1.76 million for 51%); 4 drill holes (1,500m) completed; all intersected tungsten-tin zones; SA results pending in 1-2 weeks; also a Gold-Tin-Tungsten project (1m at 96.2 g/t Au intersected); mining lease application by Oct-Nov 2025; capex ~₹500 crore

Ganajur Project Status · Dr. Hanuma Prasad Modali (MD)

  • Ganajur project under Supreme Court with Indocil case; detailed hearings to resume after court holidays
  • Company in touch with Indocil for potential business association; legal strategy coordinated with Indocil's lawyers
  • Intensified outreach to state and central governments, NITI Aayog, and Prime Minister's Office; advocating domestic gold production to save forex
  • EBITDA potential of Ganajur is 2x Jonnagiri due to higher grades; favorable outcome could mean production in 2.5-3 years after clearances

Financial Overview & Capital Allocation · Dr. Hanuma Prasad Modali (MD)

  • Rights issue: ₹315 crore raised; ₹219 crore deployed to clear all debt (Hira Group, Godavari Power & Ispat); ₹32 crore invested in Kyrgyzstan; ₹55 crore invested in Geomysore rights issue to maintain 26% stake
  • Funding gap: ₹100 crore outer limit (₹60 crore minimum) required to complete Kyrgyzstan in next 3 months; discussions with key shareholders and promoter group for debt/equity
  • EGM called for related party transaction approval (promoter participation in funding); EGM day after tomorrow
  • Post-August 2026: plan larger capital raise (equity + debt) once Kyrgyz commissioning confirmed, Bhalukona and tungsten drill results available
  • Total capex requirement through 2030: ₹800-1,000 crore; Bhalukona plant: ~₹400 crore; Spain plant: ~₹500 crore; Jonnagiri 2,000 tpd expansion: additional capex
  • Deccan investment in Kyrgyzstan treated as debt at 15% interest; repayments will flow back to Deccan from first revenue

In their words

This quarter is something which a significant development has happened. One of our associate companies that is Geomysore has recorded a profit and we could show some profit as a 26% shareholder of that Company. So that I believe is a significant step in the Company's history itself because as you all know, we went through different difficult phases, but now I think we are looking forward into something big.
Dr. Hanuma Prasad Modali (MD, Deccan Gold Mines)
By end of July, we will have the full scale leaching circuit, which would take us to the peak capacity about 1 kilo per day. So, the production forecast for FY2027, we have taken a conservative estimate of about 160kg.
Dr. Hanuma Prasad Modali (MD, Deccan Gold Mines)
We discovered nickel, copper, palladium mineralization in Bhalukona project, which I firmly believe that it is one of the significant steps in terms of the Company. It will take the Company long way into the future.
Dr. Hanuma Prasad Modali (MD, Deccan Gold Mines)

To check next time

What management committed to on this call, or the dates they gave.

  • Altyn Tor Merrill-Crowe circuit commissioning in first week of June 2026 (first Doré bars).
  • Altyn Tor full leaching circuit + tailing dam ready by end-July 2026.
  • Altyn Tor inauguration on August 15 or August 31, 2026; FY27 production run-rate.
  • Bhalukona drill results from holes 2 & 3 (mineralisation to 200m already identified).
  • Tungsten (Spain) assay results due in ~10 days from call; mining lease application by Oct/Nov 2026.
  • Closure of additional ₹60-100 cr funding for Kyrgyzstan and shareholder approval of related-party transaction at EGM.

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Tue 19 May 2026₹135.87+11.55%−0.14%
5 sessions Mon 25 May 2026₹148.26+21.72%+1.61%
20 sessions Tue 16 Jun 2026₹201.75+65.64%+1.43%

From the close of Mon 18 May 2026, ₹121.80: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

Deccan Gold Mines's other calls

  • Q2 FY27Fri 20 Nov 2026Tone: Mixed
  • Q1 FY27Wed 12 Aug 2026Tone: Confident
  • Q2 FY26Thu 20 Nov 2025Tone: Defensive