Deccan Gold Mines Q2 FY27 earnings call

Fri 20 Nov 202611:00 ISTDECNGOLD

In brief

Swarnagiri produced 135 kg in Q2 FY27; Altyn Tor was commissioned on 12 September and dispatched its first 1.2 kg of doré.

Management's tone
Mixed
What was said
Leaned positive
Guidance
Guidance held
Analyst pushback
Medium
  • Swarnagiri produced about 135 kg of gold in Q2 FY27, up from 89 kg in Q1, and reached 40-45 kg per month.
  • Swarnagiri ran at a 70% EBITDA margin and about 50% PAT margin; management saw EBITDA easing to 65-67% if gold prices stayed low.
  • Only 50.4 kg of refined bullion was sold while 133 kg of doré and bullion remained; October-November sales should appear in Q3.
  • Altyn Tor was commissioned on September 12, dispatched 1.2 kg of doré, and is processing 30,000 tonnes during its winter trial.
  • The ₹137 crore raise was in collection after BSE approval and is earmarked mainly for Finland and critical-mineral exploration.

An AI read of our transcription of the recording · the filing

The numbers

What moved the numbers, as management explained it

  • Swarnagiri output rose to 135 kg from 89 kg in Q1 as monthly production reached 40-45 kg.
  • Gold recovery of 90-95% supported production, which management linked to prior test work.
  • Q2 sales were 50.4 kg of refined bullion while 133 kg of doré and bullion remained, so output was not fully converted into revenue.
  • The ₹134 crore inventory was valued at production cost, not expected sale price; the carrying value therefore does not represent selling prices. (accounting)
  • The H1 consolidated loss of ₹9.28 crore reflected Swarnagiri's contribution alongside losses and capex at pre-commercial tied-up projects and subsidiaries.
  • At lower quoted gold prices, management said Swarnagiri's 70% EBITDA margin could ease to 65-67%.

The numbers management led with

  • Swarnagiri gold production and run-rate: 135 kg in Q2 FY27 versus 89 kg in Q1; about 40-45 kg per month
  • Kyrgyzstan first doré consignment: 1.2 kg dispatched to the government refinery
  • Exploration fund raise: ₹137 crore raised for Finland, Balukona, Spain and Mozambique
  • Ganajur gold resource and potential: About 9 tonnes at 3.8 g/t open-pit grade; potential production of about 1 tonne per year at 1,000 tpd

The company's filed results for this quarter are not on file with us yet; these are management's own figures from the call.

Guidance

Guidance on this call

WhatForWhat management said
Swarnagiri FY27 gold sales (Swarnagiri gold)FY27We could be reaching anywhere between four fifty to five hundred, if not more.
Swarnagiri annual production (Swarnagiri gold)—We will increase the production at least a thousand kilos per annum.
Swarnagiri long-term production (Swarnagiri gold)—The long term, once all the resources are identified, it could produce around two tons per annum.
Altyn Tor production (Altyn Tor, Kyrgyzstan)FY27As we are targeting about one hundred and eighty kilos in this current financial year.
Altyn Tor production, next year (Altyn Tor, Kyrgyzstan)FY28Further ramp up in terms of three hundred kilos next year.
Altyn Tor underground production (Altyn Tor, Kyrgyzstan)—Six hundred plus kilos going forward when we go into the underground operation.
Finland gold output—That will take it to almost like seven hundred, eight hundred kilos of gold from this project.
Balukona mining-lease applicationH1 FY27We are also planning to lodge, lodge the mining lease application by first half of 2027.
Mozambique commercial productionFY29At least in 2028, this could get into the commercial production.
Balukona productionFY30In twenty twenty-nine is the likely scenario when we are going to have the production.
Ganajur plant startFY31Even if we get it by March 2027, by March 2030 we would be able to run the plant.
Ganajur gold production—Which equates to about a ton per annum in that project.
Ganajur EBITDA margins—The EBITDA margins upwards of seventy, close to seventy-five or even eighty is possible, depending on the gold price.
Indicative capex—Capex will always have an idea; it could be around four hundred crores to six hundred crores.
Gold share of revenueFY27-FY31Sixty percent of our money is going from coming from gold business at least in the next five years.

What changed since the Wed 12 Aug 2026 call

WhatOn the Wed 12 Aug 2026 callOn this call
Swarnagiri FY27 volume basis (restated)500-600 kg Jonnagiri production for FY27.450-500 kg expected FY27 sales as the 133 kg inventory is sold.
Swarnagiri EBITDA margin (achieved)Jonnagiri EBITDA margin to stabilise at 65-70% over the next 1-2 quarters.H1 FY27 Swarnagiri EBITDA margin was about 70%.
Altyn Tor FY27 production (raised)150-160 kg Kyrgyzstan / Altyn Tor production for FY27.About 180 kg was targeted in FY27, subject to winter commissioning.
Altyn Tor FY28 and underground production path (restated)300-350 kg Kyrgyzstan production in FY28.About 300 kg next year, then 600+ kg once underground operations begin.
Finland drilling commencement (delayed)1,500 m drilling from Sept 15, 2026 toward a 2027 feasibility study.Drilling had not started because of BSA approval delays and awaited capital closure.
Mozambique commercial-production timing (delayed)200 TPD concentrate plant by end-2027 or Q1 FY28, expandable to 1,000 TPD.Commercial production was now described as possible at least in 2028.
Ganajur production schedule (held)~1 ton gold/year within 2-3 years if the mining lease was granted.Even with a March 2027 lease, plant operation was put at March 2030, with possible spillover.
Swarnagiri FY28 production target (restated)750-800 kg Jonnagiri production in FY28.At least 1,000 kg per annum with new approvals; around 2 tons per annum long term, without an FY28 figure.

The business

By business

Swarnagiri gold mine, Andhra Pradesh

Produced about 135 kg in Q2 FY27 versus 89 kg in Q1, with 40-45 kg monthly output, 90-95% recovery, 50.4 kg of refined-bullion sales and 133 kg of inventory.

135 kg gold produced in Q2 FY27 · 89 kg gold produced in Q1 FY27 · 40-45 kg production per month · 90-95% gold recovery · 1.4-1.5 g/ton head grade · 50.4 kg refined bullion sold · 109 kg bullion sold in H1 FY27 · 133 kg doré and bullion inventory · ₹134 crore inventory at production cost · 70% EBITDA margin · 50% PAT margin

Outlook: FY27 sales are expected at 450-500 kg; with approvals, production could reach at least 1,000 kg per year and around 2 tons per year long term.

Altyn Tor gold project, Kyrgyzstan

Commissioned on September 12; produced and dispatched 1.2 kg of doré for refining and is processing 30,000 tonnes of ROM and semi-processed material through winter commissioning.

September 12, 2026 commissioning · 1.2 kg first doré consignment · 30,000 tonnes ROM and semi-processed material · 5.67 tonnes total gold available · 4.5 tonnes in-situ gold · 1.69 g/ton in-situ grade · 1.09 tonnes gold in stockpiles and tailings · 17% revenue share to Kyrgyz Altyn · 83% revenue share to Avalon Partners · 60% Deccan ownership of Avalon Partners · 49% effective Deccan revenue stake

Outlook: FY27 target is about 180 kg and FY28 about 300 kg; 600+ kg was cited for the eventual underground phase, after winter commissioning.

Finland gold projects

Exploration licences cover Kuika and Pakalanpi. Drilling of 1,000-1,500 m did not start because of BSA approval delays; the stated plant aim is 800 TPD, conditional on results.

1,000-1,500 m planned drilling · about 3.5 g/ton grade at Pakalanpi · 800 TPD processing-plant aim · 2-2.5 kg gold per day · 700-800 kg annual gold output

Outlook: Drilling is to start once funds arrive; an 800 TPD processing plant and roughly 700-800 kg annual output are conditional on drilling success.

Ganajur gold project, Karnataka

The Supreme Court set a December 1 hearing after observing on November 17 that connected cases would be heard holistically; Deccan is participating as an intervener.

9 tonnes gold resource · 3.8 g/ton open-pit grade · 1,000 TPD plant · 3.2-3.3 kg gold per day · about 1 ton gold per annum · 70-80% EBITDA margin

Outlook: If the lease is granted by March 2027, management said the plant could run by March 2030; about 1 ton per year and 70-80% EBITDA margin were indicated.

Balukona nickel-copper-PGE project

Completed 2,000 m of diamond drilling and 15 holes, identifying a 1.3 km mineralised zone; metallurgical work is under way ahead of a planned mining-lease application.

2,000 m diamond drilling · 15 drill holes · 1.3 km mineralised zone · 0.24% nickel equivalent · 4 million tonnes economic ore · 3,000 TPD potential plant

Outlook: Mining-lease application planned for H1 2027; production likely in 2029, with a pilot-scale option potentially producing concentrate in 2028.

Spain tungsten and gold-antimony projects

Completed about 5,400 m of drilling, including 553 m at Hesa, with tungsten and tin intersections in every completed hole; Maria holes are testing gold and antimony.

5,400 m drilling · 600 m maximum hole depth · 2.3 million tonnes ore · 553 m Hesa drilling · 1,000 ppm antimony · 0% tungsten royalty · 25% corporate tax

Outlook: Further drilling and a mining-lease application are planned; no commercial production date was stated.

Mozambique lithium-tantalum project

Identified multiple pegmatite targets across about 150 sq km; 1,500-2,000 m of drilling was planned but delayed by BSA approvals and pending funding.

150 sq km licence area · 1,500-2,000 m planned drilling · <3% lithium royalty

Outlook: Drilling in Q3 FY27 after funds arrive; commercial production was described as possible at least in 2028.

Asset-acquisition pipeline

Due diligence continued on two gold assets and one graphite asset; management said updates would come soon, but no transaction or production timetable was set.

45 sq km Finnish gold grant · 6 tonnes gold · 9 tonnes silver · 3.3 tonnes gold at brownfield project · >10 tonnes potential gold · 94% graphite recovery

Outlook: Management expects an update on the three assets very soon; no transaction timetable or production date was stated.

Balance sheet, capex and funding

  • ₹134 crore inventory was carried at production cost, including run-of-mine ore, in-circuit gold, doré and bullion.
  • ₹137 crore capital raise: BSE approval had arrived; management expected fund collection to close within 3-4 days.
  • ₹276 crore was lent to Kyrgyzstan at 18% interest, with the interest recognised in Deccan's standalone books.
  • Management indicated capex could be around ₹400-600 crore, without specifying whether the range was per project or combined.
  • Later project funding may come from debt, equity or offtake arrangements; no amount or debt balance was stated.
  • Ganajur construction was put at 18 months after lease clearances, with a possible 6-12 month land-related spillover.

The industry, as management sees it

Management expects critical-mineral demand to rise sharply with energy storage, EVs, batteries, semiconductors and defense spending, while noting that India has already become a net graphite importer. It also viewed Finland and Spain as commercially attractive jurisdictions because of lower royalties, competitive tax rates and the ability to export concentrate to India.

Risks management named

  • Kyrgyzstan's first full winter operation may expose commissioning challenges
  • Ganajur remains subject to a prolonged Supreme Court and High Court process
  • Additional debt or market equity may be required to fund mine development
  • Lower gold prices could compress Swarnagiri EBITDA margins
  • Pre-production subsidiaries may keep consolidated results in loss
  • BSA approval delays pushed back drilling in Finland and Mozambique

Q&A

Discussion was dominated by financing, ramp-up credibility and project timelines, with repeated scrutiny of consolidated losses, inventory accounting and Ganajur legal uncertainty. Management was detailed on operating facts but repeatedly deferred exact Kyrgyzstan FY27 output, consolidated PAT and project lifetime revenue pending winter or beneficiation data. Pushback was moderate and generally framed as clarification rather than adversarial challenge.

Not answered directly

  • Kyrgyzstan FY27 production and winter ramp
  • Exact Kyrgyzstan all-in sustaining cost
  • Consolidated PAT forecasts for FY27 and FY28
  • Lifetime revenue estimates for critical-mineral projects
  • Final PLI support and timing
  • Ganajur Supreme Court resolution deadline
  • Balukona processing route and definitive production timing

Asked for a number, answered without one

  • Lifetime revenue for Balukona, Finland, Spain and Mozambique: Management would not circulate estimates until drilling establishes grade and recoverability, enabling opex and capex estimates.
  • Consolidated PAT and profitability timing: No PAT figure or date was provided; losses were expected to continue until other tied-up projects and subsidiaries reach commercial production.
  • Exact Kyrgyzstan production guidance: Management cited about 180 kg for FY27 and 300 kg for FY28, but wanted 15-20 days of winter operating data before giving exact guidance.
  • Ganajur rupee revenue: Management gave plant output, annual gold production and a margin range, but no rupee revenue estimate.
  • Additional project-funding requirement: The ₹137 crore raise funds exploration; later capex may use debt, equity or offtake arrangements, but no funding quantum was stated.
  • PLI support and timing for nickel and lithium: Management's understanding, not an approved paper, was that 20-30% of capital could be supported; timing awaited process-flow sheets and capital estimates.

Every question, with its answer

  1. 1. Funding and Ganajur timeline

    Ashwin Koti, Individual Investor

    Question. How will Deccan fund the cash-flow needs of Swarnagiri and other projects if the mine does not contribute direct cash or dividend, and has the Supreme Court set a deadline for the Ganajur case?

    Answer, Dr. Hanuma Prasad Murali, Managing Director. Management said the ₹137 crore raise will fund exploration at Finland, Balukona, Spain and Mozambique. Mine capex will be sized after drilling; successful projects may require market funding through debt or equity, while critical-mineral offtake partners are already being approached. Management said the Supreme Court has given no deadline; counsel expects perhaps four or five hearings and possibly clarity in the next months or so, but this was only an opinion.

    Not answered directly.

  2. 2. Consolidated losses and inventory

    Jayprakash Dargad, Jnanan Science College, Latur

    Question. Why did consolidated H1 FY27 remain loss-making despite stronger standalone and associate profitability? When can consolidated operations become consistently profitable, and will the large inventory convert into profit in Q2 or Q3?

    Answer, Unidentified Company Executive, Company Executive. Management attributed consolidated losses to Swarnagiri being an associate, while other tied projects and subsidiaries continue to incur losses and capex until commercial production. It said consolidated losses were narrowing as Swarnagiri's contribution rose. Inventory was carried at production cost across ROM, in-circuit gold, doré and bullion, with festive-season sales intended to convert it in Q3; no FY27 or FY28 consolidated PAT forecast was provided.

    Follow-up. What consolidated PAT does management expect for FY27 and FY28, and what assumptions underpin those estimates?

    Not answered directly.

  3. 3. Kyrgyzstan shipment and Balukona timing

    Avinash Mule, Individual Investor

    Question. Why was only 1.2 kg of doré shipped from the Kyrgyzstan project against an annual target of about 180 kg, and when could Balukona begin production?

    Answer, Dr. Hanuma Prasad Murali, Managing Director. The 1.2 kg was a first test shipment containing gold plus copper, silver and other metals; it was being refined, with bullion expected at the National Bank within about a week. Management called 180 kg the FY27 Kyrgyzstan target but said the first full winter run required 15-20 days of operating data before firmer guidance. Balukona production was seen in FY29, with a possible FY28 pilot sale pending metallurgical results.

    Not answered directly.

  4. 4. Project commercialization and revenue estimates

    Viraj Mahadevia, MoneyGrow

    Question. When could Balukona, Finland, Spain and Mozambique generate actual sales, what lifetime revenue might each produce, and is Kyrgyzstan still expected to ramp from 180 kg to 300 kg and then 600-800 kg?

    Answer, Dr. Hanuma Prasad Murali, Managing Director. Management said full plants for Balukona, Finland, Spain and Mozambique could take until FY29-FY30, while smaller-scale Mozambique or Balukona output might begin in FY28. It declined lifetime-revenue estimates until grades, recoverability and opex are established; indicative project capex was ₹400-600 crore. Kyrgyzstan remained at about 180 kg for FY27, 300 kg next year and 600+ kg later, but the current-year target awaited winter data.

    Not answered directly.

  5. 5. Kyrgyzstan winter operations and cash proceeds

    Imran Ghani, Individual Investor

    Question. Will Kyrgyzstan operate at full planned capacity through winter, and when will the company receive proceeds from the 1.2 kg doré test shipment?

    Answer, Dr. Hanuma Prasad Murali, Managing Director. Management said this was the plant's first winter operating period, so it could not assure 100% capacity and needed 15-20 days to assess challenges. The 1.2 kg doré was already at the refinery; management expected refined bullion at the National Bank and cash settlement in roughly a week.

  6. 6. Inventory, governance and Swarnagiri stake

    Shri Gopal Bajaj, Trade Hi-Fi Stock Broking Private Limited

    Question. Why is Swarnagiri inventory retained rather than sold immediately, how does the board participate in policy, and does management intend to exit or continue its 26% Triveni Swarnagiri stake?

    Answer, Dr. Hanuma Prasad Murali, Managing Director. Management said inventory was held to capture Indian festival pricing and that substantial October-November sales should appear in Q3. The board approves broad policies rather than individual sales. Deccan has no current exit plan; management floated a possible operating-company listing in two to three quarters and said the stake could gain value if resources rose from 12 tonnes toward 30 tonnes and output exceeded one tonne annually.

    Follow-up. Will Deccan disclose monthly production and sales for Swarnagiri and Altyn? If Ganajur is won, when would operations start and what revenue could follow?

    Answer. Altyn monthly production will be announced; management will try to obtain monthly Swarnagiri data. Even if the lease arrives in March 2027, six months of clearances plus at least 18 months of construction and land work points to around March 2030. A 1,000 tpd plant could produce 3.2-3.3 kg per day, roughly one tonne annually, with possible EBITDA margins of 70-75% or up to 80% depending on gold price.

  7. 7. PLI support and Ganajur legal strategy

    Hitesh Gupta, Individual Investor

    Question. How much PLI support and in what timeframe could the nickel and lithium projects receive, and does tying Ganajur to the Indosil case weaken Deccan's distinct legal position?

    Answer, Dr. Hanuma Prasad Murali, Managing Director. Management described a scheme exceeding ₹2,000 crore that primarily supports downstream advanced-material processing, while concentrate projects may also seek support; once a process flow sheet and capital estimate exist, Deccan may apply, and management informally estimated 20-30% of capital support. On Ganajur, the Karnataka High Court matter was put in abeyance pending the Supreme Court's Indosil decision; Deccan joined as an intervener and will argue that prior approvals and exploration history distinguish its stronger case.

    Follow-up. Will management increase analyst and investor outreach, and is a stronger or additional mining promoter expected to join the promoter group?

    Answer. Management said it would resume analyst meetings before December 15 and continue investor outreach. It acknowledged Indian investors often expect a stronger mining promoter and said the group was exploring possible participation by a well-known promoter, but gave no concrete transaction or timeline.

    Not answered directly.

  8. 8. Swarnagiri stake and brownfield commercialization

    Krish Salot, AG Ventures LLP

    Question. Can Deccan increase its profitable Swarnagiri stake, and could brownfield projects be commercialized faster than the company's current development pipeline?

    Answer, Dr. Hanuma Prasad Murali, Managing Director. Management said there is no current plan for further equity infusion into Swarnagiri because its profits can fund requirements, with debt possible if needed. For brownfield assets, open-pit projects such as Mozambique and Balukona can be commercialized faster through smaller plants; production could begin in FY28-FY29, subject to beneficiation test work, while underground projects require more development.

  9. 9. Kyrgyzstan costs and resource grades

    Pratik Kotari, CR Kotari and Sons Stock Broking

    Question. What is Kyrgyzstan's all-in sustaining cost, and has the reported 0.99 g/t stockpile grade or 1.69 g/t in-situ grade been revised downward?

    Answer, Unidentified Company Executive, Company Executive. Management reiterated expected PAT margins of about 30-35%, potentially 40%, but said precise EBITDA, PAT and all-in costs must await another quarter's results. It denied a resource-grade revision: 0.99 g/t is the combined grade of roughly 1 million tonnes of low-grade stockpile at 0.78 g/t and 0.6 million tonnes of tailings at 1.29 g/t; the in-situ pit grade remains 1.69 g/t and underground grades are expected higher.

    Not answered directly.

  10. 10. Exploration technology and revenue mix

    Ashit Koti, Individual Investor

    Question. How much do satellite imaging and hyperspectral analysis improve exploration coverage and cost efficiency, and could critical minerals contribute more than gold within two years?

    Answer, Dr. Hanuma Prasad Murali, Managing Director. Management said hyperspectral and satellite screening can narrow a 1,000 sq km search area to roughly 200 sq km and reduce exploration expenditure by about 10-15%, but ground work remains essential. It still expects about 60% of revenue to come from gold over the next five years because most critical-mineral value accrues downstream; Deccan is considering lithium hydroxide and advanced graphite materials for Indian battery makers.

    Follow-up. Are existing promoters increasing their ownership, and is Deccan also trying to increase its stake in the Kyrgyzstan project?

    Answer. Management said it is pursuing increased participation by one existing promoter but cannot confirm it. It also said acquiring additional Kyrgyz project stakes from other shareholders is possible and under active discussion; no transaction or valuation was disclosed.

  11. 11. Swarnagiri production attribution

    Rajiv Agrawal, Sterling Capital

    Question. Are the 150 kg and 135 kg production figures for Swarnagiri the mine's total output or only Deccan Gold's attributable share?

    Answer, Unidentified Company Executive, Company Executive. The 150 kg and 135 kg figures were total Swarnagiri mine production, not Deccan's share. Deccan owns 26% of the operating company and recognizes its share of profit after tax.

  12. 12. Kyrgyzstan ownership structure

    Chetan Shah, Prime Corporation

    Question. What is Deccan's ultimate net economic stake in the Kyrgyzstan gold project, and who are the other shareholders in the project vehicle?

    Answer, Dr. Hanuma Prasad Murali, Managing Director. At the project level, the government company Kyrgyz Altyn receives 17% of revenue and Avalon Partners receives 83%. Deccan owns 60% of Avalon; Hira Group holds 26% and Meditio 14%, making Deccan's effective net economic stake about 49%.

  13. 13. Consolidated accounting and gold-price sensitivity

    Sagar Parekh, Renaissance Investment Managers

    Question. Why is standalone revenue higher than consolidated revenue, what are the revised Swarnagiri and Kyrgyzstan volume and profit expectations, and how would lower gold prices affect guidance?

    Answer, Unidentified Company Executive, Company Executive. Management said standalone revenue includes ₹276 crore of loans to Kyrgyzstan at 18% interest plus consultancy income that is eliminated on consolidation. Swarnagiri sold about 100 kg in H1 but production plus inventory exceeded 250 kg, supporting FY27 output near 500 kg within the prior 500-600 kg range; Kyrgyzstan held 30-35 kg in 30,000 tonnes of material but needed 15 more days of winter data. At ₹4,000 cost per gram and sustained lower gold prices, Swarnagiri EBITDA margin could fall from about 70% to 65-67%.

    Not answered directly.

  14. 14. Project funding and dilution

    Abhishek Lika, Nest Wealth LLP

    Question. Now that Deccan has stronger funding, should it avoid diluting Chhattisgarh, Mozambique, Spain and other projects by bringing in strategic or offtake partners, or develop them wholly on its balance sheet?

    Answer, Dr. Hanuma Prasad Murali, Managing Director. Management said offtake arrangements, with potential funding from partners, are preferred over project-level dilution for critical minerals. It is separately seeking to increase its Kyrgyzstan stake. Management had no divestment plan, but said it would consider standalone balance-sheet development of other projects and discuss the tradeoff internally.

    Partly answered.

What was said

Topic by topic, in the order it was spoken

Opening Validation and Execution Record · Dr. Hanuma Prasad Murali (Managing Director)

  • The call was delayed because management was awaiting a court hearing on a key project.
  • Management said Q2 growth validated Swarnagiri's gold-mining profitability and the technical team's execution.
  • Kyrgyzstan project commissioning on September 12 demonstrated execution across multiple jurisdictions.
  • Management said it identified a large critical-minerals portfolio roughly five years earlier despite competition overseas.

Swarnagiri Operating Validation · Dr. Hanuma Prasad Murali (Managing Director)

  • Swarnagiri produced about 135 kg in Q2 FY27 versus 89 kg in Q1, implying roughly 40 kg monthly output.
  • The plant achieved 90-95% gold recovery, supporting management's prior production and margin expectations.
  • New approvals were expected to lift output toward almost one tonne annually.
  • Management presented the quarter as validation of both technical capability and project execution.

Kyrgyzstan First Doré Shipment · Dr. Hanuma Prasad Murali (Managing Director)

  • Deccan dispatched a first 1.2 kg gold doré consignment from Kyrgyzstan to the government-owned refinery.
  • The route is doré to refinery to bullion sale to the National Bank, followed by cash settlement.
  • The small shipment was explicitly a test to validate the full proceeds circuit before routine doré shipments.
  • Unlike Swarnagiri's in-house refinery, Kyrgyzstan's doré must use the sole available government refinery.

₹137 Crore Exploration Funding · Dr. Hanuma Prasad Murali (Managing Director)

  • Deccan raised about ₹137 crore after board approval in August and an EGM in September.
  • BSE approval arrived recently and management was collecting the funds, targeting closure within three to four days.
  • Most funds were earmarked for exploration in Finland, Balukona, Spain and Mozambique.
  • The financing was intended to restart or accelerate drilling across the critical-minerals pipeline.

From Explorer to Global Producer · Dr. Hanuma Prasad Murali (Managing Director)

  • Management described the company as evolving from an India-focused, exploration-led gold business into a global producer.
  • Swarnagiri began production in July 2026 and the Kyrgyzstan project in September 2026.
  • Critical minerals were presented as a third and potentially larger growth platform.
  • Gold and critical-mineral assets now span India, Central Asia and Europe, with Mozambique added.

Swarnagiri Production and Inventory · Dr. Hanuma Prasad Murali (Managing Director)

  • Swarnagiri's operating grade was about 1.4-1.5 g/t; Q2 production was 135 kg and 50.4 kg of refined bullion was sold.
  • H1 FY27 bullion sales totaled about 109 kg.
  • About 133 kg of doré and bullion remained in inventory, with ₹134 crore shown at production cost.
  • Management said festive-season price expectations drove the build and that October-November sales should appear in Q3.
  • Inventory includes run-of-mine ore, gold in circuit, doré and bullion, all valued at production cost rather than sale price.

Swarnagiri Production Outlook · Dr. Hanuma Prasad Murali (Managing Director)

  • Swarnagiri's minimum target of 90 kg per quarter was already exceeded in Q2.
  • Management previously projected at least 450 kg for FY27 and now expects output close to 500 kg.
  • With further approvals, annual production was targeted at at least 1,000 kg.
  • Once all resources are identified, the mine could produce around two tonnes per year.

Kyrgyzstan Commissioning and Revenue Split

  • Merrill-Crowe leaching began and the full processing plant was being commissioned during winter.
  • About 30,000 tonnes of ROM and semi-processed material were available to test and stabilize the circuit.
  • Management planned to process low-cost tailings for the next two to five years before underground mining.
  • Kyrgyz Altyn receives 17% of revenue; Avalon Partners receives 83%.
  • Deccan owns 60% of Avalon Partners; Hira Group owns 26% and Meditio 14%.

Kyrgyzstan Resource and Underground Plan

  • In-situ Kyrgyz resource was estimated at 4.5 tonnes at 1.69 g/t, with 1.09 tonnes in tailings and low-grade stockpiles.
  • Available gold totaled about 5.67 tonnes before deeper underground expansion.
  • Initial drilling below the current pit indicated continuity and a potential additional three tonnes.
  • Underground grades could be 2.5-3 g/t, supporting potential output of 700-750 kg.

Finland Gold Project

  • Kuika and Pakalanpi hold attractive grades; Pakalanpi was described at around 3.5 g/t.
  • Management planned 1,000-1,500 metres of drilling once funds and BSA approvals were available.
  • The eventual aim was an 800 tpd plant producing 2-2.5 kg per day, or roughly 700-800 kg annually.
  • Finland's 2.5% royalty and about 20% corporate tax were presented as more favorable than India.
  • Management acknowledged stricter environmental approvals but viewed compliance and limited European competition positively.

Ganajur Resource and Economic Potential

  • Ganajur held about nine tonnes of gold with an average open-pit grade near 3.8 g/t.
  • The grade compared with roughly 1.4 g/t at Swarnagiri and implied lower mining cost per unit.
  • A 1,000 tpd operation could potentially produce around one tonne of gold annually.
  • Management said the project could add a major third production pillar, subject to legal clearance.

Ganajur Supreme Court Process

  • The Supreme Court heard connected matters on November 17 and said it would consider the cases holistically.
  • Deccan is an intervener in the connected batch; its underlying application remains before the Karnataka High Court.
  • The next hearing was scheduled for December 1 after a Union of India request for more time.
  • Management engaged senior counsel and said it would actively pursue the matter at every stage.

Ganajur Legal Merits

  • Management argued Deccan progressed seamlessly from reconnaissance permit to prospecting licence and mining lease.
  • The Karnataka government recommended the project in 2010 and the Ministry of Mines granted prior approval in 2015.
  • A 2017 Ministry direction reaffirmed approval and told the state to proceed with lease execution.
  • Management said this history supports vested rights, while acknowledging that courts may take time.

Critical Minerals Portfolio Setup

  • Deccan's critical-minerals platform comprises Balukona nickel-copper-PGE, Spain tungsten-tin and Mozambique lithium-tantalum.
  • Two projects were already being drilled; the third was awaiting funds and approvals.
  • Management cited price increases of 108% for lithium, 100% for tantalum, 622% for tungsten and 10% for nickel.
  • Demand was linked to energy storage, EVs, batteries, semiconductors and Indian defense manufacturing.

Balukona Nickel-Copper-PGE

  • Balukona had completed 2,000 metres of diamond drilling and traced mineralization over more than 1.3 km.
  • Large-resource drilling and metallurgical flow-sheet work were planned after the monsoon.
  • Management planned to lodge a mining-lease application in H1 2027.
  • The current conservative estimate was four million tonnes of economic ore at 0.24% nickel equivalent.
  • A future processing plant was discussed at up to 3,000 tpd, twice Swarnagiri's scale.

Spain Tungsten and Tin

  • About 5,400 metres had been drilled in the tungsten project, with holes reaching depths of 600 metres.
  • Every completed hole reportedly intersected potential economic tungsten and tin mineralization.
  • The current 2.3 million tonne ore base represented roughly two years at a one-million-tonne annual rate.
  • Maria drilling targeted gold and antimony, with first antimony results near 1,000 ppm.
  • At Hesa, eight holes totaling 553 metres showed tungsten mineralization, also visible under ultraviolet light.
  • Spain offered zero tungsten royalty, export of concentrate and roughly 25% corporate tax.

Mozambique Lithium-Tantalum

  • The lithium-tantalum license covered about 150 sq km with multiple pegmatite zones.
  • Management planned 1,500-2,000 metres of drilling after delayed funding and approvals.
  • The team would evaluate hard-rock lithium and tantalum in regolith, alongside artisanal production at Inchocha.
  • Management saw commercial production as possible from 2028, though not in the next few months.
  • Mozambique's lithium royalty was described as below 3%.

New Project Pipeline and Graphite Option

  • Three acquisition targets were under due diligence: two gold projects and one graphite project.
  • A Finnish gold project covered 45 sq km and had about six tonnes of gold plus nine tonnes of silver.
  • A brownfield gold project near Terex had 3.3 tonnes in C1/C2 categories and potential above ten tonnes.
  • The graphite project had 1 km drilled, a 5-metre mineralized zone and 94% flotation recovery in flaky graphite.
  • Management proposed bringing lithium and graphite concentrate to India for advanced-material and battery supply.
  • It noted India had shifted from net graphite exporter to net importer.

Closing Strategy and Execution Commitment

  • Management set the ambition of building a globally relevant Indian mining company.
  • It described two operating gold projects, advanced gold assets and a growing critical-minerals portfolio.
  • Management argued continuous asset acquisition was necessary because prospective ground cannot be recovered once lost.
  • Management acknowledged delays and frustrations outside its control but committed to steady delivery.
  • The prepared remarks ended with confidence in the next phase of growth and shareholder returns.

In their words

We will increase the production at least a thousand kilos per annum, and the long term, once all the resources are identified, it could produce around two tons per annum.
Dr. Hanuma Prasad Murali (Managing Director, Deccan Gold Mines Ltd.)
Our actual case is in High Court. So as an intervener, we, our voice also should be heard.
Dr. Hanuma Prasad Murali (Managing Director, Deccan Gold Mines Ltd.)
Deccan Gold is no longer just an exploration, exploring for resources, but it is building a global mining business.
Dr. Hanuma Prasad Murali (Managing Director, Deccan Gold Mines Ltd.)

To check next time

What management committed to on this call, or the dates they gave.

  • Capital-raise closure, which management expected within 3-4 days.
  • Altyn Tor's first 1.2 kg doré consignment at the national bank, targeted for the following week.
  • Altyn Tor winter commissioning data over 15-20 days, ahead of firmer production guidance.
  • Q3 FY27 reporting of the Swarnagiri inventory sold during October-November.
  • The Supreme Court's December 1 hearing on the Ganajur case.
  • Finland and Mozambique drilling starts after the capital raise closes.

Transcript

Read along with the recording

The whole call, 436 lines from 22 speakers over 2:04:02. Click any line to hear it, jump to the Q&A, or find a word. Free with an account.

Sign up freeLog in

The stock after the call

No session has closed since the call yet.

From the close of Thu 19 Nov 2026, ₹184.60: the last close before the call, which began at 11:00 IST. Adjusted daily closes; the move includes everything else that happened in those sessions.