Deccan Gold Mines Q1 FY27 earnings call
In brief
Deccan Gold transitions to producer in Q1 FY27; Jonnagiri adds ₹6.35 cr PAT, Kyrgyzstan dore output begins
- Management's tone
- Confident
- What was said
- Leaned positive
- Guidance
- Guidance held
- Analyst pushback
- Low
- Stock, next session
- −0.43% (Nifty 50 −0.15%)
- Jonnagiri sold 59 kg gold in Q1 FY27, generating ₹87 cr revenue and ₹6.35 cr PAT contribution to Deccan from its 26% stake.
- Kyrgyzstan commenced dore bar production via Merrill-Crowe system; gravity circuit commissioned, leaching circuit added; larger circuit commissioning "very soon".
- Board approved ₹137 cr fundraise via CCDs, equity shares and warrants with HNIs and management participating; majority to fund critical-mineral drilling.
- Jonnagiri FY27 production guided to 500-600 kg range (vs prior 600 kg); FY28 target tempered to 750-800 kg from 800 kg; one quarter's data needed.
- Bhalukona Ni-Cu-PGE drilling crossed 2,500 m across 15 holes; 1.3 km mineralized zone identified; mining lease application planned for next year.
An AI read of the company's transcript · the filing
The numbers
What moved the numbers, as management explained it
- Only 59 kg of the 90 kg bullion produced at Jonnagiri was sold in Q1 FY27; ~80 kg equivalent gold (40 kg bullion + 60 kg dore) sat in inventory at quarter-end, depressing reported revenue and Deccan's share of profit.
- Higher gold prices in Q1 (~₹1,50,000 per 10 g vs prior quarter) created an arbitrage incentive to hold stock for sale in Q2, amplifying the timing mismatch.
- Jonnagiri was officially inaugurated only on 24 June 2026, compressing selling days in the quarter and adding one-off ramp-up expenses that held EBITDA margin below the steady-state 65-75% target. (one-off)
- Deccan books Jonnagiri only via 26% associate accounting, so the ₹6.35 cr contribution is the entire consolidated profit inflow from gold in Q1 FY27; Kyrgyzstan had no commercial revenue yet. (accounting)
The numbers management led with
- Jonnagiri Q1 gold sold: 59 kg sold for Rs 87 cr revenue; Rs 25 cr PAT; Deccan share Rs 6.35 cr
- Jonnagiri Q1 dore/bullion production: 112 kg dore bar produced, yielding 90 kg bullion (~1 kg/day run-rate)
- Capital raise (immediate): Rs 137 cr via CCDs + equity shares + equity warrants (Board approved, pending shareholder approval)
- Government critical-mineral support: Rs 40-44,000 cr National Critical Mineral Mission; Rs 16,000 cr NMET corpus for overseas exploration
The company's filed results for this quarter are not on file with us yet; these are management's own figures from the call.
Guidance
Guidance on this call
| What | For | What management said |
|---|---|---|
| Jonnagiri FY27 production (Jonnagiri Gold) | FY27 | Jonnagiri FY27 production 500-600 kg |
| Jonnagiri FY28 production (Jonnagiri Gold) | FY28 | Jonnagiri FY28 production 750-800 kg |
| Kyrgyzstan FY27 production (Kyrgyzstan Altyn Tor) | FY27 | Kyrgyzstan FY27 production 150-160 kg |
| Kyrgyzstan FY28 production (Kyrgyzstan Altyn Tor) | FY28 | Kyrgyzstan FY28 production 300-350 kg |
| Total critical-mineral capex requirement (Critical minerals portfolio) | — | ~₹2,000 cr capex across critical-mineral projects (Bhalukona, Spain, Mozambique, Finland) |
| Bhalukona plant capex (Bhalukona Ni-Cu-PGE) | — | Bhalukona 3,000 TPD plant capex ~₹650-700 cr (3-4 years out) |
| Altyn Tor underground capex (Kyrgyzstan Altyn Tor) | — | Altyn Tor underground mining capex ~₹150-200 cr in 3-4 years |
| Jonnagiri next-block underground capex (Jonnagiri Gold) | — | Jonnagiri underground next-block capex >₹400 cr in 4-5 years |
| Finland drilling programme (Kalevala Gold (Finland)) | Q2 FY27 | 1,500 m drilling at Finland starting ~Sep 15, 2026 |
| Spain Dehesa full drill results (Logrosan Tungsten (Spain)) | Q2 FY27 | Full Dehesa drill results by mid-September 2026 |
| Spain preliminary resource model (Logrosan Tungsten (Spain)) | Q2 FY27 | Preliminary resource modeling of Dehesa by early October 2026 |
| Mozambique processing plant commissioning (Mozambique Li-Ta) | FY28 | 200 TPD concentrate plant by end-2027 or Q1 FY28 |
| Mozambique drilling programme (Mozambique Li-Ta) | Q2 FY27 | 1,500-2,000 m drilling in Mozambique starting mid-late September 2026 |
| Bhalukona mining-lease application (Bhalukona Ni-Cu-PGE) | FY28 | Bhalukona mining-lease application planned next year |
| Bhalukona process flow-sheet (Bhalukona Ni-Cu-PGE) | FY28 | Bhalukona process flow-sheet design by mid next year |
What changed since the Tue 19 May 2026 call
| What | On the Tue 19 May 2026 call | On this call |
|---|---|---|
| Jonnagiri FY27 production (cut) | 600 kg refined gold in FY27 (point target) | 500-600 kg in FY27 (range, pending one more quarter) |
| Jonnagiri FY28 production (cut) | 800 kg in FY28 (point target) | 750-800 kg in FY28 |
| Kyrgyzstan FY27 production (cut) | 160 kg in FY27 (point target) | 150-160 kg in FY27 |
| Kyrgyzstan commissioning (delayed) | Full production by August 2026; inauguration Aug 15 or 31, 2026 | Gravity + leach circuits live, dore bar produced; larger commissioning "very soon"; MD visiting next week |
| Bhalukona mining-lease application (delayed) | To be submitted by April 2026 | Application planned for next year (FY28); drilling at 2,500 m / 15 holes, 1.3 km mineralized zone |
| Total capex through 2030 (raised) | ₹800-1,000 crore total (Bhalukona ~₹400 cr + Spain ~₹500 cr) | ~₹2,000 crore across critical-mineral projects; Finland and Mozambique now also included |
| Near-term funding (restated) | ₹100 cr outer limit (₹60 cr minimum) needed in next 3 months to complete Kyrgyzstan | ₹137 cr via CCDs / equity shares / warrants approved; aimed at critical-mineral drilling |
| Strategy scope (new) | Two-project focus: Jonnagiri gold + Kyrgyzstan gold | Five-asset critical-mineral programme added (Bhalukona, Logrosan, Mozambique, plus Finland and graphite); two clear verticals now |
The business
By business
Jonnagiri Gold (Geomysore, 26% associate)
Q1 FY27 was first full production quarter post June inauguration. 112 kg dore and 90 kg bullion produced; only 59 kg sold at strong prices. ~1 kg/day run-rate achieved.
112 kg dore produced · 90 kg bullion produced · 59 kg sold · ₹87 cr revenue · ₹25 cr project PAT · ₹6.35 cr Deccan share · 40 kg gold + 60 kg dore in stock (~80 kg)
Outlook: 500-600 kg production in FY27; 750-800 kg in FY28; processing facility to scale from 1,010 TPD to 2,500 TPD; ~2 t/yr peak around 2029-30.
Kyrgyzstan Altyn Tor Gold
Dore bar produced via Merrill-Crowe smelting test; gravity and leach circuits operational; larger circuit and tailings dam near completion; MD visiting next week.
0.6 mt tailings · ~780 kg gold in tailings · ~1 mt low-grade stockpile · 200 local jobs · 30 engineers from India · >₹300 cr invested to date
Outlook: 150-160 kg production FY27; 300-350 kg FY28; commissioning and inauguration "very soon"; revised mine plan by October 2026.
Kalevala Gold (Finland)
Focus shifting to Finland with drilling planned from ~Sep 15. Kuikka and Pahkalampi clusters hold ~3 t identified gold at 3.5-5+ g/t grade.
27.36 sq km licensed area · ~1 t gold at Kuikka (>5 g/t) · ~2 t gold at Pahkalampi (~3.5 g/t) · $1-2 m to reach 51%
Outlook: 1,500 m drilling starting ~Sep 15; resource target ~4 t; feasibility by 2027; production commencement 2028-2029.
Ganajur Gold
Mining-lease project in Karnataka courts. Hearings delayed; management cites favourable recent judgments including Gadchiroli iron-ore precedent to argue restoration of prior rights.
Outlook: If mining lease granted, ~1 t/year gold production possible within 2-3 years; full focus on Ganajur; Hutti deferred.
Bhalukona (Ni-Cu-PGE, Chhattisgarh)
Composite-license critical-mineral project. 15 drill holes / 2,500 m completed; ~1.3 km mineralized zone with ~700 m proven; sulphide core logged.
30 sq km composite license · 2,500 m drilled across 15 holes · 1.3 km mineralized zone · 700 m proven mineralization
Outlook: Mining-lease application next year (FY28); process flow-sheet by mid next year; 3,000 TPD plant envisaged; capex ₹650-700 cr.
Logrosan Tungsten (Spain)
Phase-1 Dehesa drilling complete at 3,000 m; deepest hole 626 m; tungsten-tin mineralization to surface. Maria phase commencing end-August.
37 sq km granted + 30 sq km pending · 3,000 m drilled · 626 m deepest hole · Best grades 0.88% and 1.21% WO3 · 0.29% WO3 over 7.5 m
Outlook: Full Dehesa drill results by mid-September; preliminary resource model early October; 1,000 TPD plant target; ~3 mt overall resource.
Mozambique Lithium-Tantalum-Cesium
150 sq km across three contiguous licenses; geological mapping and soil sampling done; 4-5 pegmatite zones identified; project lagged due to Kyrgyzstan focus.
150 sq km across 3 licenses · 4-5 pegmatite zones identified · 8 parallel pegmatites with high tantalum in Area 2
Outlook: 1,500-2,000 m drilling from mid-late September; 200 TPD concentrate plant by end-2027 or Q1 FY28; first critical-mineral production targeted 2028.
Balance sheet, capex and funding
- Company debt-free; ₹315 cr rights-issue proceeds used to fully repay ₹219 cr debt (per prior call).
- Board approved ₹137 cr raise via CCDs, equity shares and equity warrants; awaiting shareholder approval.
- Capital to be deployed mainly on critical-mineral drilling (Bhalukona, Logrosan, Mozambique, Finland), not on Kyrgyzstan which is near completion.
- Future critical-mineral capex estimated at ~₹2,000 cr; funding to combine debt, equity and possible off-take arrangements with battery/end-users.
- Underground-mining capex reserved for Altyn Tor (~₹150-200 cr, 3-4 yrs) and Jonnagiri next block (>₹400 cr, 4-5 yrs), to be funded from internal accruals.
The industry, as management sees it
Management is bullish on critical/battery minerals — views the Rs 40-44,000 cr National Critical Mineral Mission plus NMET overseas-exploration support, waiver of public hearings, and prohibition of additional state taxes as major policy tailwinds. Tungsten (+622%), tantalum (+196%) and lithium (+108%) price moves in the last year are cited as validation of the critical-mineral bet. Demand for battery storage in India (Adani-scale projects cited) is expected to remain the dominant pull for nickel and lithium.
Risks management named
- Ganajur mining-lease litigation unresolved; hearings delayed post-summer vacation; recent judgments (Gadchiroli iron-ore) cited as favourable but not binding
- Critical-mineral projects still in drilling/feasibility stage — capex and timeline guesstimates remain tentative
- Kyrgyzstan tailings dam and underground mining require further drilling to extend life beyond initial 4-5 years
- Jonnagiri EBITDA margin currently below guided 65-70%; expected to normalise over next 1-2 quarters but execution-dependent
- 80 kg of unsold gold/dore sitting in inventory at quarter-end — realisations sensitive to gold price
Q&A
Q&A was friendly and investor-led (mostly individual investors plus a handful of boutique analysts). Management was forthcoming on operational specifics — Jonnagiri margins, Altyn Tor timeline, capex per project — and used the session to confirm maintained FY27/FY28 production guidance. The only meaningful deflection was on Tannay Soni's right-issue question, where Modali redirected to the broader QIP strategy. The discussion underlined that the larger Rs 2,000 cr capex will be funded via a combination of off-take arrangements (for critical minerals, Musk-style), debt, and a future QIP — not the immediate Rs 137 cr raise.
Not answered directly
- Specific Bhalukona funding instrument (right issue at Rs. 80?)
- Inventory realisation schedule on balance sheet
Asked for a number, answered without one
- Dividend cash flow from Geomysore: Only via Geomysore Board dividends; expansion capex needs likely defer any dividend this year, possibly next year; cannot commit.
- Jonnagiri EBITDA margin guidance: Margin to stabilise at 65-70% over next 1-2 quarters as stock is monetised and grade rises; declined to give a number now.
- FY28 production volumes from mines other than Jonnagiri and Kyrgyzstan: Asked for one more quarter of data before giving year-level guidance for non-producing assets.
- Capex funding mix (debt vs equity): Stated mix will vary by project: critical-mineral projects may use off-take financing with end-users; gold projects likely 40:60 to 50:50 equity-debt; no firm ratio.
- Strategic partner / change-of-control: Not decided at this stage; current path is professional team with Hira Group support; may revisit post drill results.
- Hutti Gold Mine timeline: Hutti is only a prospecting licence (vs Ganajur's mining lease); fully focused on Ganajur; Hutti deferred pending policy developments.
Every question, with its answer
1. Jonnagiri cash flow + strategic partner
Nikunj Devpura, Individual Investor
Question. How will cash flows/dividends be received from the Jonnagiri associate (Geomysore)? Given the substantial funding pipeline ahead, is management looking to bring in a large promoter group or will it remain professionally managed?
Answer, Dr. Hanuma Prasad Modali, Managing Director. Cash can only come as dividend from Geomysore — a Board decision there. With processing plant expansion and land acquisition consuming cash, dividend unlikely this fiscal; possibly next year but no guarantee. On promoter: no decision yet; professional technical team has driven the company for last 3-4 years with Hira Group/promoter support; will stay this way as long as projects deliver — strategic partner is a future question, not now.
Partly answered.
2. Jonnagiri margin guidance + Kyrgyzstan outlook
Hitesh Gupta, Individual Investor
Question. Jonnagiri profit margin (~30% EBITDA vs prior 65% guidance) looks much lower than expected. Any guidance for revenue/profit from Kyrgyzstan and Jonnagiri for this financial year?
Answer, Dr. Hanuma Prasad Modali, Managing Director. Only 59 kg of gold sold in Q1 (80 kg of equivalent gold remains in inventory); ramp-up is on track at ~1 kg/day. EBITDA/PAT margins to normalise to 65-70% over next 1-2 quarters once stock is sold and one-time expenses roll off. Will give clear FY27 production and PAT margin guidance at end of next quarter. Altyn Tor ~150-160 kg production confidence for FY27, 300-350 kg FY28.
Partly answered.
3. Altyn Tor production + dore bar refinery + capex
Aniket Gogate, CRK Research
Question. Three questions: (1) Altyn Tor production for current year and next year? (2) Do dore bars need a refinery and is the refinery setup complete at Altyn Tor? (3) Total capex ballpark for Spain, Bhalukona, Mozambique, Finland, Ganajur (~Rs 2,000-2,200 cr)? Funding mix — 50:50 debt-equity?
Answer, Dr. Hanuma Prasad Modali, Managing Director. FY27 Altyn Tor ~150-160 kg, FY28 ~300-350 kg (tailings-fed, high confidence). Dore bar is the standard industry final product — in Kyrgyzstan we must by law deliver to government refinery at LBMA settlement; in Jonnagiri we set up a small in-house refinery (~Rs 4-5 cr) to refine and sell to jewellers. Capex: each ~1,000 TPD plant ~Rs 400-500 cr; Bhalukona 3,000 TPD plant Rs 650-700 cr; total ~Rs 2,000 cr. Funding: critical-mineral projects via off-take arrangements (Musk-style battery-maker funding); gold projects via 40-60 or 50-50 equity-debt; combination once drill results and bank appetite firm up.
Follow-up. How does the capex requirement change if we proceed into underground mining?
Answer. Altyn Tor underground capex Rs 150-200 cr, 3-4 years out, from internal accruals. Jonnagiri next block (underground with 500-600 m deep shafts) could need Rs 400+ cr in 4-5 years, also from internal accruals.
4. Bhalukona funding structure
Tannay Soni, KTPL
Question. Is Bhalukona funding going to be another right issue at Rs. 80/share as done a few months ago?
Answer, Dr. Hanuma Prasad Modali, Managing Director. Not addressed point-blank; Modali reiterated in the broader funding discussion that a larger QIP placement is being planned once drill results inform the quantum — not specifically a Rs. 80 right issue.
Not answered directly.
5. Confirmation of prior production guidance
Hardik Jain, Whitestone PMS
Question. Prior guidance of 600 kg Jonnagiri FY27 (Rs 900-1,000 cr topline) and 800 kg next year; Kyrgyzstan 160 kg FY27 (Rs 300 cr topline) and 350 kg FY28 — does this guidance remain unchanged? Volumes expected from other mines in FY28?
Answer, Dr. Hanuma Prasad Modali, Managing Director. Maintained. Jonnagiri FY27: 500-600 kg (range vs prior 600 kg); FY28: 750-800 kg. Kyrgyzstan FY27: 150-160 kg (range vs prior 160 kg); FY28: 300-350 kg. Other mines not contributing in FY28 — that is why company pursuing inorganic gold assets to fill the gap and target 2027-28 production from new assets.
6. Pipeline revenues + strategic partner + Ganajur timing
Pranay Jain, DealWealth Capital
Question. Three questions: (1) Revenue expectations from the project pipeline vs the 2030 numbers shared earlier. (2) Strategic partnership with larger players to help develop the pipeline? (3) Ganajur — is it really 2-3 years away or closer?
Answer, Dr. Hanuma Prasad Modali, Managing Director. Project-level revenue/capex numbers for Jonnagiri and Kyrgyzstan are stable; for other projects remain tentative until drilling and feasibility complete — will respond to detailed list via email. Strategic partnership: no decision yet; once four projects' drill results are good, may explore — but not now. Ganajur: court hearings stalled post-summer; if mining lease granted, 2-3 years to ~1 ton/year production.
Follow-up. What is the status of Hutti Gold Mines legally — similar to Ganajur or more tedious?
Answer. Hutti is a prospecting license (not mining lease like Ganajur); strategically deprioritised until Ganajur outcome — but if Ganajur precedent is favourable, Hutti also stands a good chance.
Partly answered.
7. Inventory realisation timing
Shashwat Vijay, SIC Wealth Management
Question. FY2026 consolidated balance sheet inventory of ~Rs 522 mn — when will this be realised? No change in inventory per the P&L this quarter.
Answer, Dr. Hanuma Prasad Modali, Managing Director. Modali briefly acknowledged the cost of metal component; full answer deferred to email response along with Nikhil Gohil's detailed queries.
Not answered directly.
8. Capex financing strategy
Kunal Shah, Heartwood Financial Services
Question. How is the capex going to be financed?
Answer, Dr. Hanuma Prasad Modali, Managing Director. See Q&A 3 — combination of off-take arrangements for critical minerals, debt-equity mix for gold projects, with a larger QIP placement planned once resource positions firm up.
9. Physical AGM request
Imran Ghani, Individual Investor
Question. Request: please conduct a physical AGM (representing ~100 friends who are DGML investors).
Answer, Dr. Hanuma Prasad Modali, Managing Director. Guaranteed — physical AGM to be held in Mumbai this year. Acknowledged the importance of meeting shareholders given growth and increasing market interest.
10. Government funding support + Uzbekistan exploration
Sunder Padmanabhan, Individual Investor
Question. How much is the Government of India supporting funding for these projects? Any news on Uzbekistan offering critical mineral mining to India?
Answer, Dr. Hanuma Prasad Modali, Managing Director. Government support: no funding for gold projects so far — self-funded. For critical minerals: ~Rs 40-44,000 cr National Critical Mineral Mission, Rs 16,000 cr NMET corpus for overseas exploration (capped ~US$1 mn per project), public hearings waived for critical-mineral projects, no additional state taxes, and tax incentives for Li/Ni/Co. Uzbekistan: Modali visited Tashkent; team also visited this year — early-stage discussions, no concrete projects or data exchange yet; logical to consider Uzbekistan and Kazakhstan given existing Kyrgyzstan establishment.
What was said
Topic by topic, in the order it was spoken
Three Takeaways from Q1 FY27 · Dr. Hanuma Prasad Modali (Managing Director)
- Quarter has firmly established the company as a producer — both at Jonnagiri and (newly) at the Kyrgyzstan Altyn Tor project
- Two distinct verticals have crystallised: gold (now producing) and critical/battery minerals (drilling underway, resources being built)
- Clarity now allows precise, separate expansion plans for each vertical
Capital Raise and Board Changes · Dr. Hanuma Prasad Modali (Managing Director)
- Board approved Rs 137 cr raise via CCDs, equity shares and equity warrants — pending shareholder approval; HNAs and management participating
- Proceeds earmarked for exploration across projects other than Kyrgyzstan (which is already near full-scale production)
- Pandarinathan Elango (ex-CEO Cairn Energy; founder of HOEC) elevated to Chairman; Jade Devenish (ex-MD Geomysore Services 2012-22) joins as Non-Executive Non-Independent Director; Kailasam and Deepthi retired
Gold Portfolio Overview · Dr. Hanuma Prasad Modali (Managing Director)
- Jonnagiri (India): now in production; Kyrgyzstan/Altyn Tor: in production; Kalevala (Finland): next focus area; Tanzania and Ganajur under review/court
- Company pursuing organic growth (Finland drilling) and inorganic growth — due diligence ongoing on three new gold projects targeting production by 2027-28
- Kyrgyzstan government offered an additional ~10-ton gold project for partnership given successful community engagement
Jonnagiri Project Deep Dive · Dr. Hanuma Prasad Modali (Managing Director)
- Inaugurated June 2026 by the Chief Minister of Andhra Pradesh with land-acquisition support and Bhumi Puja for expansion
- Q1 production: 112 kg dore bar → 90 kg bullion (~1 kg/day run-rate); 59 kg sold for Rs 87 cr revenue and Rs 25 cr PAT; Deccan share Rs 6.35 cr
- Inventory at quarter-end: 40 kg gold + 60 kg dore (~80 kg gold equivalent) — to be sold in Q2 FY27 at favourable prices (gold ~Rs 1,50,000/10 g)
- Ramp plan: 1,010 TPD processing → 2,500 TPD (target ~2 tons gold/year by FY29-30); drilling to grow resource to 40 tons for 25+ year mine life
- Project employs ~1,000 on-site plus another ~1,000 in the local backward/drought-prone area; water treatment plants commissioned
Kyrgyzstan / Altyn Tor Project · Dr. Hanuma Prasad Modali (Managing Director)
- Total invested >Rs 300 cr; Merrill-Crowe system demonstrated operational viability with first dore bar poured
- Tailings feedstock: ~0.6 mn tons of old tailings at 1.3 g/t (~780 kg gold) plus ~1 mn tons low-grade stockpile — enough for 4-5 years
- Larger leach circuit and 10-year-life tailings dam under construction; full commissioning planned within ~1 week; underground drilling to start in September
- Revised mine design and life-of-mine plan due October 2026; underground resource expected to exceed 5 tons (adding 6-7 years of life)
- Employment scaling from ~200 to ~350; 30 engineers from India being deployed; additional ~10-ton Kyrgyz government gold project under due diligence
Kalevala Gold Project (Finland) · Dr. Hanuma Prasad Modali (Managing Director)
- 27.36 sq km licensed area acquired in 2023 across Archean greenstone belt; two clusters — Pahkalampi and Syrjala (incl. Kuikka)
- Kuikka: ~1 ton at 5 g/t, target to expand to 4 tons via drilling; ~70 kg open-pittable; mining lease and EC applications being expedited
- Pahkalampi: ~2 tons historic resource at 3.5 g/t; combined target >5-6 tons to support centralised ~800 TPD flotation circuit by 2028-29
- Plan: invest $1-2 mn ($1 mn takes stake to 51%) in Q2 FY27; 1,500 m drilling from Sept 15 to validate/increase resources; feasibility by 2027
Ganajur and Hutti Status · Dr. Hanuma Prasad Modali (Managing Director)
- Ganajur: mining-lease matter in court; hearings stalled post-summer vacation; favourable recent judgments cited (e.g. Gadchiroli iron-ore case restoring pre-2015 rights)
- If mining lease granted, 2-3 years to ~1 ton/year gold production; government sympathetic given project's readiness
- Hutti: prospecting license (not mining lease); strategically deprioritised until Ganajur outcome; could revive if Ganajur precedent favourable
- Tanzania assets: results unsatisfactory, only two areas retain hope, deprioritised in the queue
Critical Minerals: Bhalukona (Ni-Cu-PGE, Chhattisgarh) · Dr. Hanuma Prasad Modali (Managing Director)
- 30 sq km composite license acquired 2025; 15th drill hole underway; ~2,500 m drilled; ~1.3 km mineralised zone identified
- Sulfide-bearing cores contain nickel, copper, palladium; off-take potential with Indian smelters (Adani, Vedanta, Birla); neighbour Vedanta also exploring
- Tentative plan: 3,000 TPD processing plant (bigger than Jonnagiri); capex and feasibility details pending process flowsheet work by mid-FY28
- Mining lease application targeted for next year; large-scale drilling and metallurgical test-work in parallel
Critical Minerals: Logrosan (Tungsten, Spain) · Dr. Hanuma Prasad Modali (Managing Director)
- 77 sq km granted + 30 sq km pending (first-in-time applicant); two targets — Dehesa (drilled, 3,000 m completed) and Las Brujas; tin also intersected
- Best intercepts: 0.88% and 1.21% WO3; hole extended to 626 m showing continuous mineralisation to ~600 m depth; widths up to 7.5 m at 0.29% WO3
- Phase 1 Dehesa drilling complete; Maria (with gold) drilling to start end-August; preliminary resource estimate due early October
- Target plant: ~1,000 TPD with 300,000 t/year input, ~3 mn ton overall resource for 10-year project; larger mining lease application by mid-FY28
Critical Minerals: Mozambique (Li-Cs-Ta) · Dr. Hanuma Prasad Modali (Managing Director)
- 150 sq km across three contiguous licences; geological mapping and soil sampling done; 4-5 pegmatite zones identified
- Area 2 shows high tantalum (pegmatites at >500 ppm Ta) — standalone tantalum mineability; lithium 0.5-1% LiO2 upgradeable to 4% concentrate
- Plan: 1,500-2,000 m drilling from mid-September; aim for 200 TPD concentrate plant by end-2027 or Q1 FY28; expand to 1,000 TPD targeting ~3 mn ton resource
- Project previously lagged due to Kyrgyzstan focus; new funding expected to fast-track — likely first critical-mineral revenue in 2028
Battery-Metals Strategy and Graphite · Dr. Hanuma Prasad Modali (Managing Director)
- Strategic focus on battery metals (Ni, Li) plus tungsten (defense/space); complementary graphite project in Africa under due diligence — every battery contains ~50% graphite in anode
- Critical-mineral price appreciation cited: tungsten +622%, tantalum +196%, lithium +108% in last year; even graphite +5% despite synthetic competition
- MoU signed with CECRI (CSIR electrochemical research institute, Karaikudi) for Li-ion battery prototype work — Deccan to supply Li/Ni/graphite concentrates, gain technology transfer
- MoU with XTerra for beach-sand critical-mineral blocks in eastern India — technical support partnership
Funding Strategy and Government Support · Dr. Hanuma Prasad Modali (Managing Director)
- Immediate: Rs 137 cr raise via CCDs/equity/equity warrants for drilling commitments over next 3-4 months
- Larger QIP placement planned once drill results inform the right funding quantum and project priorities
- Critical-mineral funding model: off-take arrangements (e.g. Musk-style battery-maker funding of mines) being pursued; preliminary discussions with Indian smelters
- Government support: Rs 40-44,000 cr National Critical Mineral Mission; Rs 16,000 cr NMET corpus for overseas exploration; public hearings waived; state-level additional taxes prohibited; tax incentives for Li/Ni/Co
In their words
In the March quarter we have shown some production and June quarter has clearly established us as the producer and then that is mainly from Jonnagiri but then subsequently you have seen we have started producing dore bar from Kyrgyzstan as well. So I think that is the biggest take away that has happened in the Company.
If you actually see, we are one of the first ones who have stepped out and got the licenses… tungsten is something which has grown by 622% in last one year… tantalum increased by 196% and lithium has gone up by 108%.
In terms of funding, substantial amount of funds are required going forward in these projects… around 2,000 Crores… my belief is going forward for these kind of projects, the funding will come through a kind of off-take arrangement.
To check next time
What management committed to on this call, or the dates they gave.
- Jonnagiri Q2 FY27 sales volume from ~80 kg opening stock plus fresh production at ~1 kg/day.
- Jonnagiri EBITDA margin trajectory toward the guided 65-70% steady-state.
- Kyrgyzstan full-circuit commissioning and formal inauguration date after MD's next-week visit.
- Logrosan full Dehesa drill results by mid-September and preliminary resource model by early October.
- Finland (Kalevala) drilling start around Sep 15; first resource-update signals for Kuikka and Pahkalampi.
- Bhalukona 15th drill-hole assays and progress toward next-year mining-lease application.
Transcript
We have not transcribed this call's recording. Read the company's transcript (PDF).
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Wed 12 Aug 2026 | ₹220.35 | −0.43% | −0.15% |
| 5 sessions Tue 18 Aug 2026 | ₹244.05 | +10.28% | −1.29% |
| 20 sessions Tue 8 Sept 2026 | ₹223.22 | +0.86% | −3.42% |
From the close of Tue 11 Aug 2026, ₹221.31: the last close before the call, which began at 11:00 IST. Adjusted daily closes; the move includes everything else that happened in those sessions.