GE Power India Q1 FY25 earnings call
In brief
- Management's tone
- Confident
- What was said
- Leaned positive
- Guidance
- First guidance issued
- Analyst pushback
- Low
- Stock, next session
- +0.38% (Nifty 50 −0.08%)
- Q1 FY25 orders at Rs 1,038 cr, up 443% YoY, led by Rs 775 cr FGD EP win from Jaypee Nigrie and Jaypee Bina
- Backlog rose to Rs 3,917 cr vs Rs 3,309 cr QoQ; loss before tax narrowed to Rs 11 cr from Rs 136 cr YoY
- Management targets double-digit EBITDA within 2 years via services + EP-FGD focus, Durgapur breakeven, and hydro+gas carve-out
- Carve-out unlocks Rs 252 cr net liability reduction and Rs 700 cr of non-funded bank limits; working capital cycle targeted to fall from 10 years to 2-3 years
- FGD market sized at Rs 60,000 cr / 90 GW; GEPIL will participate only as EP (~30% of project value) targeting 1-2 orders / Rs 300-500 cr per year
An AI read of the company's transcript · the filing
The numbers
The quarter, Q1 FY25
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹430 cr | +1.5% | +10.1% | |
| EBITDA (excl. other income) | ₹-29.5 cr | — | — | -6.9% (-31.2% a year ago) |
| Net profit | ₹0 cr | — | — | 0% (0% a year ago) |
| EPS (₹) | ₹-1.42 | — | — |
From the company's filed results for the quarter ended 30 Jun 2024 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.
The numbers management led with
- Q1 FY25 order intake: Rs 1,038 cr (vs Rs 191 cr in Q1 FY24, +443% YoY)
- FGD order from Jaypee Nigrie and Jaypee Bina: Rs 775 cr (EP / supply scope)
- FGD market opportunity (India): ~Rs 60,000 cr / 90 GW across retiring (2027) and non-retiring (2026) units
- Durgapur underutilisation drag: Rs 25-40 cr annual margin hit currently
- Working capital cycle target: Reduce from average ~7 years (vs historical 10 years) to 2-3 years
- Bank non-funded limits to be unlocked post carve-out: Rs 700 cr; also avoids Rs 500 cr working capital requirement over 2 years
Guidance
Guidance on this call
| What | For | What management said |
|---|---|---|
| EBITDA margin | 2 years from Q1 FY25 (i.e. by ~Q1 FY27) | Double-digit EBITDA targeted within 2 years from now |
| FGD order intake | Annual run-rate | 1-2 orders per year, Rs 300-500 cr per year, EP-only participation |
| FGD market share (gigawatt basis) | Ongoing | Target 5-7% gigawatt share; historical 8-9% under EPC, but will exit EPC |
| Durgapur service load | FY25 and beyond | Target 200,000-250,000 hours of service load to take out Rs 25-40 cr underutilisation drag; FY25 target ~175,000 hours |
| Working capital cycle | Medium-term | Reduce average working capital cycle from current ~7 years to 2-3 years |
| Slump sale proceeds (gas business) | On completion of carve-out | Rs 44 cr consideration for gas business; total transaction also delivers Rs 214+38 cr net liability reduction |
| Bank non-funded limits to be unlocked | Post carve-out completion | Rs 700 cr of non-funded bank limits to be unlocked post carve-out; avoids Rs 500 cr working capital requirement over 2 years |
Said on the Q1 FY25 call, not repeated on this one (4)
- Path to debt-free and double-digit EBITDA: Target to become debt-free and deliver double-digit EBITDA within ~2 years, with quarterly free cash flow available for dividends
- Net worth impact from slump sale: Positive Rs. 296 crores excluding taxes (refined in closing to Rs. 214 cr + Rs. 38 cr = Rs. 252 cr net liability reduction, plus Rs. 44 cr gas consideration), subject to shareholder approval
- Non-funded limit unlocking: Slump sale unlocks Rs. 700 crores of non-funded limits as of 31 March 2024 tied to hydro and Rs. 500 crores of cash consumption limit needed for hydro over next 2 years
- Coal emission intensity: Target to reduce unit emissions from 996 grams/unit today to 500-600 grams/unit by 2030 via services, upgrades, biomass and methanol/ethanol/ammonia co-firing
The business
The industry, as management sees it
Global electricity demand is set to grow ~4% in both 2024 and 2025 — the fastest pace in two decades, driven by heat waves and a solar PV surge. India's power sector is balancing an aggressive renewables build with maintaining thermal capacity, while a near-term FGD compliance cycle (90 GW by Dec 2026/2027) is expected to draw industry bid for extension.
Risks management named
- FGD regulatory timeline (Dec 2026/2027) may be extended by industry, deferring the 90 GW order wave
- FGD market is 90 GW but ordering pace is uncertain given EPC vs EP cycle mismatch
- Durgapur factory currently hits margins by Rs 25-40 cr due to underutilisation
- Cryogenic / pressure vessel ramp is in wave 1 (fabrication only); technology tie-ups still future
- Slump sale of hydro and gas remains subject to shareholder and regulatory approvals
- Net worth repair is needed to support credit ratings, tender eligibility and bank funding
Q&A
Only two analysts asked questions across the entire Q&A — Tushar Bhavsar (single question on FGD market share) and Nilesh Doshi, who dominated with multiple follow-ups spanning FGD EP vs EPC split, the impossibility of meeting FGD deadlines, Durgapur boiler manufacturing, cryogenic technology and Durgapur hours. Management answered each question with reasonable directness; the only notable deflection was on Durgapur revenue potential, which was reframed as a margin / drag-removal story. There was no adversarial pushback, and the broader tone was constructive, consistent with the friendly nature of the call.
Not answered directly
- Durgapur revenue potential (reframed as a margin / underutilisation-removal story rather than a top-line number)
Every question, with its answer
1. FGD market size and market share
Tushar Bhavsar, Cognizance 4D
Question. Heard in a conference that the FGD market is ~Rs 60,000 cr over the next 2-3 years. What market share does GEPIL expect in that space?
Answer, Prashant Jain, Managing Director. Confirms ~Rs 60,000 cr market; ~90 GW up for grabs across retiring (2027) and non-retiring (2026) units. GEPIL will not participate in EPC and will partner with EPC players as EP. Historical gigawatt share was 8-9%; going forward, gigawatt share may be 5-7% depending on which projects get finalised. Annualised plan is 1-2 orders per year of Rs 300-500 cr each — embedded in the business case for double-digit EBITDA in 2 years. Industry likely to seek extension, which could favour ordering spurt later.
2. FGD compliance timing
Nilesh Doshi, Green Lantern Capital LLP
Question. 90 GW of FGD with 2026/2027 deadlines but EPC cycle is 5-8 years — isn't it practically impossible to complete within 3 years?
Answer, Prashant Jain, Managing Director. Agreed — practically impossible. GEPIL anticipates developers will place orders in time and then petition regulators / Government for an exception to avoid penalty. The Company does not see a sense of urgency in ordering today and views the timeline as a court / regulator-dependent issue.
Follow-up. So they will have to get all these orders placed within next 3 months? Hypothetically if they do within…
Answer. Practically, you are right. It's practically impossible. We anticipate developers will order within the timeline and then apply to the regulators for an extension to avoid penalty.
3. FGD EP vs EPC split
Nilesh Doshi, Green Lantern Capital LLP
Question. Bifurcation between EP and C in the Rs 60,000 cr FGD opportunity — what is the EP share?
Answer, Prashant Jain, Managing Director. Roughly 30% of project value is the EP scope that GEPIL would like to bid on; can be slightly up or down customer by customer.
4. FGD go-to-market and customer mix
Nilesh Doshi, Green Lantern Capital LLP
Question. Jaypee order is also EP from GEPIL's side, right? Has it been ordered by Jaypee directly to GEPIL — is that the new norm for FGD?
Answer, Prashant Jain, Managing Director. Yes, Jaypee is a supply / EP portion with a large supply component. FGD contracting is customer-specific: some customers have in-house EPC, others prefer to deal with an EPC. GEPIL prefers private IPPs and is selective on state utilities; project-by-project tie-ups with EPCs since there is no single dominant EPC player in the full market.
5. Durgapur strategy and boiler manufacturing
Nilesh Doshi, Green Lantern Capital LLP
Question. Is GEPIL contemplating getting back into boiler manufacturing at the Durgapur facility?
Answer, Prashant Jain, Managing Director. No. Durgapur plan today: capacity right-sized to 200,000 hours (from 800,000); service load up from 10,000 to 170,000 hours; FY25 target 175,000 hours. Focus is services in India, parts supply to 13 countries outside India, and pressure vessels / cryogenic. First pressure vessel lot dispatched yesterday for LMP IOCL (~Rs 6 cr). Cryogenic factory certification valid for 3 years; 3 qualified customers vs 1 earlier. Cross 200,000 hours and the Company should deliver low-risk, high-margin, high-cash, double-digit EBITDA within 2 years.
6. Cryogenic technology and capability
Nilesh Doshi, Green Lantern Capital LLP
Question. On the cryogenic side, does GEPIL have the technology (beyond fabrication) for insulation etc.?
Answer, Prashant Jain, Managing Director. Phased 3-year plan. Wave 1 (FY25-27): competency build, certification, team, pilot projects. KPMG engaged for business study. Wave 1 is fabrication only; technology (insulation etc.) via strategic tie-ups is planned in later waves. CAPEX for entry is in current-year budget. Better visibility expected in ~6 months; Company will update every quarter.
Partly answered.
7. Durgapur revenue / margin contribution
Nilesh Doshi, Green Lantern Capital LLP
Question. In revenue terms, what can the Durgapur facility generate?
Answer, Prashant Jain, Managing Director. Not commenting on Durgapur as a top-line play. Durgapur is a margin story: underutilisation is hitting the Company by Rs 25-40 cr per year. Crossing 200,000 hours takes this loss out of the system and adds some margin — short-cycle, low-risk, high-margin business. So Durgapur is about removing the drag, not driving revenue.
Follow-up. In Q1 how many hours would we have clocked?
Answer. Q1 was about 40,000 hours.
Not answered directly.
8. Durgapur Q1 hours
Nilesh Doshi, Green Lantern Capital LLP
Question. [Implicit follow-up] In Q1 how many hours were clocked at Durgapur?
Answer, Prashant Jain, Managing Director. Q1 was about 40,000 hours.
What was said
Topic by topic, in the order it was spoken
Global and Indian Macro / Power Sector Context · Prashant Jain (MD)
- Global GDP growth remained robust in Q1 despite geopolitical tensions; UNCTAD cautious on trade exceeding 2022 levels
- IEA projects global energy sector growth at fastest pace in two decades, driven by heat waves and solar PV
- Global electricity demand forecast to grow ~4% in 2024 (up from 2.5% in 2023) and again ~4% in 2025
- India: government continues to expand renewables while maintaining thermal capacity; budget allocates capital for solar rooftop
- FGD compliance deadlines: retiring units 31 Dec 2027, non-retiring units 31 Dec 2026; industry watching these timelines closely
Q1 FY25 Executive Summary and Strategic Developments · Prashant Jain (MD)
- Strong quarter for core services and FGD orders; Rs 775 cr FGD order from Jaypee Nigrie and Jaypee Bina
- 10 July 2024: Board approved slump sale of hydro and gas power businesses (subject to approvals)
- 25 July 2024: GE Vernova ended its de-promoterization plan; will continue as promoter; supports management turnaround strategy
- 8 August 2024: GEPIL response to GE Vernova hydro global strategy — anticipates decline in CoE demand and no new hydro bids, reinforcing carve-out rationale
- Strategy summarised: margin-accretive + cash-accretive; working capital cycle from 10 years to 2-3 years; double-digit EBITDA in 2 years
Q1 FY25 Financial Performance · Aashish Ghai (CFO)
- Orders booked: Rs 1,038 cr in Q1 FY25 vs Rs 191 cr in Q1 FY24 — 443% increase
- Backlog: Rs 3,917 cr as on 30 June 2024 vs Rs 3,309 cr as on 31 March 2024
- Revenue from operations: Rs 430 cr (vs Rs 424 cr YoY) — favourable mix shift toward higher-cal service business
- Loss before tax (standalone): Rs 11 cr in Q1 FY25 vs Rs 136 cr loss in Q1 FY24
- Company committed to executing existing backlog safely under right risk-reward profile
Durgapur Factory and Cryogenic / Pressure Vessel Plan · Prashant Jain (MD)
- Durgapur capacity right-sized from 800,000 hours to 200,000 hours; service load up from 10,000 hours to 170,000 hours; FY25 target 175,000 hours
- Currently underutilisation costs Rs 25-40 cr annually; breakeven target is 200,000-250,000 hours
- First pressure vessel dispatch to LMP IOCL (~Rs 6 cr); cryogenic/pressure vessel factory certification valid 3 years; 3 qualified customers vs 1 earlier
- KPMG engaged for 3-year cryogenic business study; phased capability build across FY25-FY27; wave 1 is fabrication only, technology tie-ups planned later
- Evaluating 128 potential areas; top segments: parts & services, pressure vessels & cryogenic, waste heat recovery / industrial boilers
In their words
Therefore, the strategy of the Company to focus on margin accretive, cash accretive service business and upgrade business to focus on lower risk EP projects in the FGD… sets the Company towards a positive trajectory with more certainty, also with an end on the current depromoterization program, also GE Vernova to continue as the promoter.
We now have a strategy for the Company which is margin accretive, cash accretive to focus in improving the working cycle capital of the Company from an average of 10 years to 7 years today to a future of an average working capital cycle of about 2 to 3 years.
It's practically impossible. We don't see that sense of urgency anywhere today. We do see there is interest yes, but we anticipate… that they would order within the timeline and then they would apply to the regulators saying that 'okay' you've ordered it and now please grant an extension and avoid penalty.
Transcript
We have not transcribed this call's recording. Read the company's transcript (PDF).
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Mon 12 Aug 2024 | ₹464.30 | +0.38% | −0.08% |
| 5 sessions Mon 19 Aug 2024 | ₹433.95 | −6.18% | +0.84% |
| 20 sessions Mon 9 Sept 2024 | ₹397.25 | −14.12% | +2.33% |
From the close of Fri 9 Aug 2024, ₹462.55: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.
GE Power India's other calls
- Q2 FY27Mon 16 Nov 2026Tone: Mixed
- Q1 FY27Fri 10 Jul 2026Tone: Confident
- Q1 FY27Mon 6 Jul 2026Tone: Confident
- Q4 FY26Tue 12 May 2026Tone: Confident
- Q3 FY26Tue 17 Feb 2026Tone: Confident
- Q2 FY26Fri 14 Nov 2025Tone: Confident
- Q4 FY25Fri 30 May 2025Tone: Optimistic
- Q3 FY25Thu 13 Feb 2025Tone: Mixed
- Q1 FY25Tue 30 Jul 2024Tone: Defensive
- Q1 FY25Thu 18 Jul 2024Tone: Mixed
- Q4 FY24Wed 22 May 2024Tone: Cautious