Genus Power Infrastru Q4 FY25 earnings call
In brief
Genus Power Q4 FY25 revenue ₹937 cr (+123%); FY26 target ₹4,000 cr (~60%) at 18% margin; NCLT sanctions demerger.
- Management's tone
- Confident
- What was said
- Leaned positive
- Guidance
- Guidance raised
- Analyst pushback
- Low
- Stock, next session
- +6.06% (Nifty 50 −0.14%)
- Q4 FY25 standalone revenue ₹937 cr (+123% YoY, +55% QoQ); EBITDA ₹208 cr (+276%) at 22.3% margin (+905 bps); PAT ₹129 cr (4x YoY).
- FY26 targets top line of ₹4,000 cr (~60% YoY growth) at 18% EBITDA margin; expects to install 7-8 million meters.
- Order book ₹30,110 cr (net of taxes) with 8-10 year concessions covering multiple AMISP SPVs and the GIC Platform.
- Capacity expanded to 15 million meters (from 10 million); FY25 capex ~₹150 cr covering capacity, automation and in-house software.
- Tender pipeline of ~₹27,300 cr open from MP, Tamil Nadu, Haryana expected to convert to orders in 3-6 months.
An AI read of the company's transcript · the filing
The numbers
The quarter, Q4 FY25
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹937 cr | +123.0% | +55.0% | |
| EBITDA (excl. other income) | ₹196 cr | +262.3% | +111.2% | 21% (12.9% a year ago) |
| Net profit | ₹0 cr | — | — | 0% (5.8% a year ago) |
| EPS (₹) | ₹4.46 | +395.6% | +117.6% |
From the company's filed results for the quarter ended 31 Mar 2025 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.
Where management's figures differ from the filing
- Q4 FY25 EBITDA: said ₹208 cr, margin 22.3%; filed ₹196.33 cr, margin 21.0% (excl. other income). Management figure appears to include part of other income (₹20.78 cr) while filed is EBITDA excluding other income; gap ~5.9%.
What moved the numbers, as management explained it
- Q4 EBITDA margin expanded 905 bps YoY to 22.3% on operating leverage from 2× revenue scale, cost controls and favourable product mix.
- Backward integration of software (HES, MDM) and forward integration providing end-to-end AMISP solution lifted margins beyond the earlier 15-16% band.
- Q4 gross margin ~40.6% vs 9M average above 44% reflects meter-type mix that shifts quarter-on-quarter.
- Depreciation rose on capitalisation of Guwahati and other plant capex; prior-quarter other expenses carried a notional loss. (accounting)
- Filed consolidated net profit to owners for Q4 FY25 is ₹0 cr vs standalone ₹129 cr quoted; suggests a one-off/write-off in consolidated SPV/platform accounts not explicitly explained. (one-off)
The numbers management led with
- Order book: INR30,110 crores (net of taxes)
- Open tender pipeline: INR27,300 crores open tenders (quoted in next 3–4 months)
- Meter capacity: 15 million meters per annum (up from 10M at end of FY24)
- FY25 capex: INR150 crores (capacity + automation + in-house software)
Guidance
Guidance on this call
| What | For | What management said | Filed |
|---|---|---|---|
| FY26 top line | FY26 | FY26 top line target INR4,000 crores (~60% YoY growth) | ₹4,751 cr, above the figure guided |
| FY26 EBITDA margin | FY26 | FY26 EBITDA margin guidance 18% | 19.2%, above the figure guided |
| FY26 meter installations | FY26 | At least 7 million to 8 million meters to be installed in FY26 | — |
| Net debt/equity ceiling | — | Net debt to equity will not go more than 1:1 | — |
| FY26 capex | FY26 | FY26 capex around last year's level (FY25 capex ~₹150 cr) | — |
| Manufacturing capacity | — | Annual capacity at 15 million meters; to be enhanced as required | — |
| FY27 top line | FY27 | FY27 will be better than FY26; specific guidance to be given after 1-2 quarters | — |
Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.
Guided on earlier calls, and what was filed
| What | For | Guided | Filed |
|---|---|---|---|
| FY25 total revenue | FY25 | ₹2,500 cr (on the Q4 FY24 call) | ₹2,442 cr, below the figure guided |
| FY25 EBITDA margin | FY25 | 15–16% (on the Q4 FY24 call) | 17.8%, above the range |
| Stated revenue target | FY25 | ₹2,500 cr (on the Q1 FY25 call) | ₹2,442 cr, below the figure guided |
| Expected EBITDA margins | FY25 | 15–16% (on the Q1 FY25 call) | 17.8%, above the range |
| FY25 revenue guidance | FY25 | ₹2,500 cr (on the Q3 FY25 call) | ₹2,442 cr, below the figure guided |
| Average EBITDA margin | FY25 | 15–16% (on the Q3 FY25 call) | 17.8%, above the range |
| Next financial year revenue growth | FY26 | 30–35% (on the Q3 FY25 call) | 94.5%, above the range |
| Next-year revenue increase | FY26 | 30–40% (on the Q3 FY25 call) | 94.5%, above the range |
| FY26 EBITDA margin | FY26 | 15–16% (on the Q3 FY25 call) | 19.2%, above the range |
Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.
The business
By business
Smart Metering (manufacturing, supply, installation)
Core business delivered record Q4 revenue ₹937 cr (+123% YoY); installed 1.5 million meters in Q4; produced 3 million meters in Q4 including conventional. Industry has installed only ~2 crore of 12 crore awarded meters under RDSS.
Q4 revenue ₹937 cr · FY25 revenue ₹2,442 cr · Q4 EBITDA ₹208 cr at 22.3% margin · FY25 EBITDA ₹470 cr at 19.2% margin · Q4 meters installed 1.5 million · Q4 production 3 million meters · Capacity 15 million meters
Outlook: FY26 revenue ₹4,000 cr at 18% margin; install 7-8 million meters; enhance capacity as required.
GIC Platform / AMISP SPVs
Order book primarily from AMISP Platform; 60-70% of trade receivables are from the Platform; NCLT Allahabad sanctioned demerger of Strategic Investment Business into Genus Prime Infra Limited.
FY26 GIC equity infusion USD 25-30 million · FY25 infusion ~₹25 cr · 60-70% of trade receivables from Platform
Outlook: Demerger to unlock value; FY26 equity infusion USD 25-30 million planned; SPV financials not to be published.
Balance sheet, capex and funding
- Net debt/equity currently ~0.5-0.6; will not exceed 1:1 even as absolute debt may rise with revenue.
- FY25 capex ~₹150 cr for capacity, automation and in-house software; FY26 capex around similar level per management.
- Trade receivables ~₹1,365 cr (60-70% from GIC Platform); inventory ~₹850 cr.
- Working capital elongated during ramp-up; debtors targeted to improve by 20-30 days in coming quarters.
- FY26 equity infusion into GIC Platform planned at USD 25-30 million; FY25 infusion was ~₹25 cr.
The industry, as management sees it
Smart meter adoption is positioned as a necessity for India's electricity sector given growing generation across multiple sources and the inability to store power at scale. Management sees long runway — only ~50% of the RDSS opportunity has been awarded (~12 crore of ~25 crore meters; ~2 crore installed), with 13–14 crore meters yet to be tendered. Southern states (Tamil Nadu, Karnataka, Kerala, Telangana) and West Bengal expected to drive the next wave of tender activity.
Risks management named
- Initial payment hiccups at some state utilities post Operational Go-Live
- Working capital elongation tied to simultaneous multi-state project ramp-up
- Geopolitical/political delays could slow smart meter adoption timeline
- Sensitivity of electricity as a politically charged consumer-facing subject
- Net debt expected to rise in absolute terms even as % to revenue falls
Q&A
Q&A was dominated by working capital concerns and order pipeline visibility. Management faced repeated pushback on debtor days (currently ~50% of revenue) but maintained a steady tone, promising quarter-on-quarter improvement starting June quarter. Several analysts probed the conservatism of FY26 margin guidance (18% vs Q4 FY25 exit of 22%), with management explicitly preferring to commit only to numbers they were sure of. The lone sensitive topic — the prior-year ED raid — was met with a status-quo response ('no further communication from any department or court') and a strong assertion that it had not affected operations.
Not answered directly
- Exact FY26 debt peak levels (deferred by 1–2 quarters)
- GIC Platform equity infusion split / SPV financials (won't be published separately)
- Exact FY25 full-year meters installed and Assam plant share (to be shared via IR)
- Order inflow ballpark number for FY26 (no specific figure)
- Quarter-on-quarter revenue cadence (management refused, citing weather/election/festival volatility)
Asked for a number, answered without one
- FY26 order inflow value: Said will continue to maintain historical market share but declined to give a number.
- Peak debt level: Said very difficult to state; net debt to revenue ratio will fall but absolute may rise; clarity in 3-6 months.
- FY26 capex exact figure: Stated both 'INR25 crores' and 'around last year's capex' (~₹150 cr); no firm figure.
- FY26 supply to other AMISPs volume: Said don't have those numbers and don't want to comment.
- Investment in SPVs till date: Said don't have exact numbers; will revert later.
Every question, with its answer
1. Tender pipeline
Aditya Welekar, Axis Securities
Question. On the new tendering or order pipeline — you expect it to pick up in the medium term especially from southern states. Can we expect this pipeline to increase by FY26 and are you seeing tailwinds emerging?
Answer, Jitendra Agarwal, Joint Managing Director. Tenders worth INR27,300 crores are already open and will be quoted in the next 3–4 months. Major tenders currently from Madhya Pradesh, Tamil Nadu and Haryana; West Bengal, Telangana, Kerala and Karnataka also expected to come up. RDSS program is moving at a rapid pace and it takes 3–6 months for tenders to convert into orders.
Follow-up. On margin guidance — previously you guided 15–16% margins, now confident of 18%. What has changed?
Answer. Major driver has been cost control. Backward integration of software and forward integration of end-to-end solution, combined with volume increase, is enabling the higher guidance.
2. Installation volumes
Ashwani, Unknown
Question. Can you share the number of meters Genus installed in FY25 and in Q4?
Answer, Jitendra Agarwal, Joint Managing Director. Q4 installations approximately 1.5 million meters at Genus. FY25 — exact number not recalled.
Follow-up. In terms of volume, how many meters for the INR4,000 crore target?
Answer. Expect at least 7 million to 8 million meters to be installed in FY26.
Partly answered.
3. Order inflow
Darshil Pandya, Finterest Capital
Question. What kind of order inflow are you expecting this year? Any ballpark given market share?
Answer, Jitendra Agarwal, Joint Managing Director. Few states have come out with large tenders to be decided in 3–6 months. Expect to maintain historical market share. No specific ballpark number given.
Follow-up. On interest cost and debt for FY26 — will debt increase or how should we model?
Answer. Kailash Agarwal: Debt will increase but not in the same ratio as revenue (revenue +60%). Exact figures not given — expecting improvement in working capital over next 1–2 quarters before quantifying.
Not answered directly.
4. Debt levels
Nikhil Jain, Galaxy International
Question. Would FY26 be the year of peak debt, or will debt keep rising as execution picks up?
Answer, Kailash Agarwal, Vice Chairman. Very difficult to say for sure. Next 3–6 months will give clarity on working cycle and debtors. Expect debt-to-revenue ratio to come down even if absolute debt rises.
Follow-up. Experience on payment receipt from utilities post go-live — any hiccups?
Answer. Jitendra Agarwal: Initial hiccups at some utilities but generally as per expected timeline. RDSS is a Central Government scheme with regular review; no major problem expected in the longer run.
Partly answered.
5. ED raid update
Nikhil Jain, Galaxy International
Question. Any update on the ED raid that happened last year?
Answer, Kailash Agarwal, Vice Chairman. Status quo — no communication received from any department or court or summons since the search. Any new information will be shared with investors and exchanges first. Emphasised the matter has not affected the company's working — visible in Q4 results and forward outlook.
6. Production & installation
Bhavin Chheda, Enam Holdings
Question. What were smart meter production and installation numbers for FY25 and Q4?
Answer, Jitendra Agarwal, Joint Managing Director. Q4 installations ~1.5 million meters at Genus. Country-wide ~22 million smart meters installed (ballpark, multiple programs). FY25 full-year Genus installation number not available — to be shared via IR.
Follow-up. Debtors doubled to INR1,365 crores; inventory INR850 crores; working capital ~75% of annualised sales. Steps to bring this down and what number should we model going forward?
Answer. Kailash Agarwal: Inventory likely to stay at similar levels given 25–26 projects in different areas. Debtor days to improve — expecting 10–15% improvement from current 75% over coming quarters, starting Q1 FY26. Quarter-on-quarter improvement, not a step change.
Partly answered.
7. GIC Platform equity infusion
Bhavin Chheda, Enam Holdings
Question. FY26 equity infusion into the GIC Platform — what is the expected number?
Answer, Kailash Agarwal, Vice Chairman. Broad estimate USD25 million to USD30 million from Genus Power standalone balance sheet into the Platform. Cumulative till date was around INR25 crores.
8. Revenue recognition breakup
Chandresh Malpani, Niveshaay Investments
Question. On 1.5M meters installed in Q4 — what is the average selling price and component breakup (meter, HES, communication, installation)?
Answer, Jitendra Agarwal, Joint Managing Director. 1.5 million is meters installed. Supply volumes are much larger. Two revenue streams: (a) supply-and-install to the Platform and (b) supply to other AMISPs/electricity boards (conventional). When supplying to the Platform, it includes meters + HES + software + installation.
Follow-up. On INR1,300 crores trade receivables, how much is from the Platform?
Answer. Kailash Agarwal: Roughly 60–70% of trade receivables are from the Platform. Exact numbers to be provided via SGA.
Partly answered.
9. Other expenses
Chandresh Malpani, Niveshaay Investments
Question. On other expenses — last quarter had a notional loss impact; how should we view this going forward?
Answer, Kailash Agarwal, Vice Chairman. Other expenses are at almost the same absolute level; the apparent reduction is only as a % of revenue, not absolute.
Follow-up. Depreciation increased — was it related to commercialisation of the Guwahati plant?
Answer. Kailash Agarwal: Yes, depreciation reflects the capex on Guwahati and other plants.
10. Industry opportunity size
Deepanshu, Hem Securities
Question. Industry scenario — out of 25 crore meters under RDSS, how much is installed/awarded/yet to be awarded?
Answer, Jitendra Agarwal, Joint Managing Director. Out of 25 crore target, ~12 crore awarded so far; out of awarded, ~2 crore installed. Remaining 13–14 crore yet to be awarded. Total opportunity has also grown with country growth.
Follow-up. Execution cycle for the INR30,000 crore order book?
Answer. Jitendra Agarwal: 8–10 years (supply + install + service + maintain). Kailash Agarwal: 55–60% of revenue to come in next 3 years, balance over 8–10 years.
11. Order book mix
Deepanshu, Hem Securities
Question. Out of INR30,000 crore order book, how much is from the AMISP Platform?
Answer, Jitendra Agarwal, Joint Managing Director. Primarily from the AMISP Platform. Did not want to give a specific %.
Follow-up. Current capacity is 10M meters — plans to expand to 15M in FY26 as per last concall. Are plans intact?
Answer. Jitendra Agarwal: Plans intact; already producing more than 10M. Capacity has reached 15M. Will enhance as needed. Kailash Agarwal: Capex is also going into automation and software/technology, not just capacity.
12. Peak execution timing
Abhilasha, Quantum AMC
Question. When will Genus reach peak execution on the current order book? What is the roadmap?
Answer, Jitendra Agarwal, Joint Managing Director. Jitendra Agarwal: Peak execution of current order book expected in next calendar year. Kailash Agarwal: With the current order book, peak revenue run-rate may be reached in FY27 or FY28 — subject to how the remaining 13 crore meter opportunity is tendered. Specific FY27 numbers will be given after 6 months.
Follow-up. Working capital target — can we expect to reach below 200 days in next 3–6 months?
Answer. Kailash Agarwal: Inventory won't improve much. Debtors (currently ~50% of revenue) can see improvement of 20–30 days, gradually quarter-on-quarter.
Partly answered.
13. Capex
Mahesh Patil, ICICI Securities
Question. FY25 capex incurred? Given 7–8M installations vs 15M capacity (~60% utilisation), will there be capex in the near term?
Answer, Kailash Agarwal, Vice Chairman. FY25 capex was almost INR150 crores — covering capacity, automation and in-house software development. Genus is no longer purely a metering company; significant tech/software investment is being made. Same pattern to continue in FY26.
Follow-up. What was capacity at end of last year (before expansion)?
Answer. 10 million meters at end of FY24; 15 million at end of FY25.
14. AMISP supply volumes
Mahesh Patil, ICICI Securities
Question. Apart from the 7M, there is AMISP supply also. Any quantification for FY26?
Answer, Kailash Agarwal, Vice Chairman. Exact numbers not available; do not want to comment on those numbers.
Not answered directly.
15. Quarterly revenue cadence
Raj, Finvestor
Question. Industry installation speed has gone from 40,000/day to 85,000/day in early FY26 — should we see revenue beat each quarter? Or should we benchmark year-on-year / half-yearly?
Answer, Jitendra Agarwal, Joint Managing Director. Quarter-on-quarter is very difficult to guide on — installation depends on weather, elections, festivals. Better to compare half-yearly or year-on-year.
Follow-up. Q4 installations 1.5M, FY26 target 7–8M (5x). Why is margin guidance only 18% if scale is increasing? Are we being too conservative?
Answer. Kailash Agarwal: From the last quarter, FY26 guidance is ~4.5x. We want to stick to a particular guidance at the EBITDA level. May look conservative but management prefers to stay where they are confident.
16. Capex guidance
Darsh Solanki, Axis Securities
Question. Capex estimate for FY26 and FY27 — was INR150 crores in FY25.
Answer, Kailash Agarwal, Vice Chairman. Kailash said 'around like INR25 crores only, almost a little — maybe on a lower side, not on a higher side, but it will be around last year's capex.' (Likely verbal error — INR25 crores is inconsistent with the stated aim of 'around last year's capex' of INR150 crores; needs clarification.)
Follow-up. No top-line guidance for FY27 yet?
Answer. Kailash Agarwal: FY27 will be better than FY26 but the number will be shared at the Q2 FY26 concall.
Partly answered.
17. Production split
Darsh Solanki, Axis Securities
Question. How many meters were produced in Q4 and what was the contribution of the Assam plant?
Answer, Jitendra Agarwal, Joint Managing Director. Q4 production ~3 million meters (smart + conventional). Assam plant contribution: do not have an updated number; will come back with it.
Follow-up. View and outlook on water meters and gas meter orders?
Answer. Jitendra Agarwal: Water and gas meter work ongoing for 2 years; gas meter is conventional-style, water meter has many pilot projects. Revenue contribution currently negligible; significant numbers only after 2–3 years.
Partly answered.
18. Gross margin walk
Nikhil Abhyankar, UTI Mutual Fund
Question. Gross margin in Q4 (~40.6%) is significantly below the 9-month average (>44%) — any specific one-offs or is this purely execution-related? Is this the reason for lower FY26 EBITDA guidance?
Answer, Kailash Agarwal, Vice Chairman. No particular one-off — gross margin depends on the type/mix of meters supplied in that quarter and varies quarter-to-quarter.
Follow-up. Total investment in SPV till date? And on working capital — confident of operating cash flows in coming years given the INR4,000 crore revenue target? Will SPV financials be published?
Answer. Kailash Agarwal: Exact SPV investment number not available; will check. Will be operating cash flows positive — debtor days will reduce. SPV financials: No, will not be published separately.
Partly answered.
19. Upside to guidance
Rohit Ladda, Intelligent Capital
Question. Based on installation numbers on the government portal in April–May '25, FY26 guidance of INR4,000 crores looks conservative. Is there a chance to go beyond?
Answer, Jitendra Agarwal, Joint Managing Director. There is definitely a good chance to go beyond — we want to be conservative. Portal numbers can show sudden spikes from operational go-live catching up on earlier installs, so portal may not give the absolute picture.
Follow-up. What was the capacity in FY24 and the peak capacity-wise machinery?
Answer. Kailash Agarwal: FY24 capacity was 10 million meters; end of FY25 it is 15 million.
20. Supply chain risk
Rohit Ladda, Intelligent Capital
Question. Supply chain risk — given geopolitical situation, is there a risk on chips/components for smart meters?
Answer, Jitendra Agarwal, Joint Managing Director. No risk seen currently. Genus has always maintained multiple component suppliers across geographies — even during COVID, impact was limited. May have some challenges but nothing significant.
21. Order book in meter terms
Ashwani Sharma, Emkay Global
Question. The INR31,000 crore order book — how many meters does that represent?
Answer, Jitendra Agarwal, Joint Managing Director. Ballpark figure of 30 million meters (includes supply + installation).
22. O&M revenue, leverage, pledge
Smita Mohta, Kredent InfoEdge
Question. How much is O&M revenue currently as % of total? What debt-to-equity is comfortable? Will pledged shares come down?
Answer, Kailash Agarwal, Vice Chairman. O&M revenue currently negligible — meters are still being installed and going online. Net debt-to-equity at 0.5–0.6; will not go above 1:1. On pledge — there is no promoter pledge on Genus shares; what appears as pledge is actually a commitment to the GIC Platform that promoter shareholding will not fall below a certain level (exchange software artefact).
Follow-up. Is the INR4,000 crore target for FY26 or FY27? Current market share?
Answer. Kailash Agarwal: FY26. Jitendra Agarwal: Market share ballpark ~27% — exact definition difficult under AMISP model.
23. Key risks
Nikhil Jain, Galaxy International
Question. What are the key constraints or risks that could derail the growth story?
Answer, Jitendra Agarwal, Joint Managing Director. Electricity is a politically sensitive subject — direct consumer interaction is a risk, along with weather. Smart meters have to happen (necessity, not optionality). Beyond that, can't see major risk; geopolitical/political reasons could cause delays but not derailment.
24. Export markets
Anurag Agarwal, Multify Wealth
Question. Is Genus doing anything to diversify the market — entering export markets for long-term sustainability?
Answer, Jitendra Agarwal, Joint Managing Director. Yes — been working on strategically important markets for 2–3 years. Two segments: (a) countries transitioning from conventional to smart meters and (b) developed countries going into Phase 2/3 (e.g., Italy has reached end-of-life of first-gen meters). Significant revenues expected 2–3 years out. Did not name specific countries.
What was said
Topic by topic, in the order it was spoken
Q4 FY25 Standalone Performance · Kailash Agarwal (Vice Chairman)
- Q4 FY25 standalone revenue INR937 crores, +123% YoY and +55% QoQ, driven by accelerated execution and improved smart meter offtake.
- Q4 EBITDA INR208 crores, up 276% YoY; margin expanded 905 bps to 22.3% on operating leverage, cost discipline and favourable product mix.
- Q4 PAT INR129 crores — more than 4x Q4 FY24.
- Sharp uptick validated end-to-end model — in-house manufacturing, software integration, and early capex investments.
FY25 Full-Year Standalone Performance · Kailash Agarwal (Vice Chairman)
- FY25 revenue more than doubled to INR2,442 crores from INR1,201 crores in FY24.
- EBITDA surged 247% YoY to INR470 crores; EBITDA margin improved 797 bps to 19.2%.
- FY25 PAT grew nearly 4x to INR298 crores.
- Results highlight sharp operating leverage embedded in the business model.
Order Book, Working Capital & Demerger · Kailash Agarwal (Vice Chairman)
- Order book of INR30,110 crores (net of taxes) covering multiple SPVs and GIC Platform; concession tenures 8–10 years.
- New tender activity has moderated temporarily — viewed as a natural pause with resumption expected from southern states.
- Working capital saw temporary elongation during ramp-up; expected to normalise as projects move to stable operational phase.
- NCLT Allahabad Bench sanctioned demerger of Strategic Investment Business into Genus Prime Infra — expected to enhance focus, capital allocation and unlock shareholder value.
FY26 Outlook & Guidance · Kailash Agarwal (Vice Chairman)
- FY26 revenue target of INR4,000 crores — ~60% YoY growth from FY25.
- FY26 EBITDA margin guided at 18% (vs FY25 actual 19.2%); confidence driven by execution pipeline and projects moving to OPEX.
- Positioned as forward-integrated, technology-enabled AMISP with HES and MDM capabilities.
- Continued investments in innovation, people and infrastructure to support sustained long-term value creation.
In their words
We want to maintain this 18%. We want to commit what we are sure of.
After that search and all, we haven't received any communication from — either from the department or from the — any court or any summons and all. So, we are at the status quo.
Smart meter has to happen. It's a necessity for the country and not only for the country, for the world.
To check next time
What management committed to on this call, or the dates they gave.
- Quarter-on-quarter debtor days reduction (targeting 20-30 days improvement) as projects move to operational go-live.
- Status of remaining project go-lives in Uttaranchal, Uttar Pradesh and Rajasthan within 2-3 months.
- Award outcomes from ₹27,300 cr tender pipeline (MP, Tamil Nadu, Haryana) over next 3-6 months.
- Q1 FY26 revenue run rate vs ₹4,000 cr annualised target.
- Update on GIC Platform equity infusion of USD 25-30 million during FY26.
Transcript
We have not transcribed this call's recording. Read the company's transcript (PDF).
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Mon 2 Jun 2025 | ₹419.35 | +6.06% | −0.14% |
| 5 sessions Fri 6 Jun 2025 | ₹393.10 | −0.58% | +1.02% |
| 20 sessions Fri 27 Jun 2025 | ₹373.65 | −5.50% | +3.58% |
From the close of Fri 30 May 2025, ₹395.40: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.
Genus Power Infrastru's other calls
- Q2 FY27Thu 19 Nov 2026Tone: Mixed
- Q2 FY27Mon 16 Nov 2026Tone: Mixed
- Q4 FY26Tue 19 May 2026Tone: Confident
- Q3 FY26Wed 18 Feb 2026Not read
- Q3 FY26Wed 11 Feb 2026Not read
- Q2 FY26Fri 7 Nov 2025Tone: Confident
- Q1 FY26Mon 11 Aug 2025Tone: Confident
- Q3 FY25Fri 14 Feb 2025Tone: Mixed
- Q2 FY25Wed 30 Oct 2024Tone: Confident
- Q1 FY25Wed 31 Jul 2024Tone: Confident
- Q4 FY24Thu 30 May 2024Tone: Confident