Hitachi Energy India Q1 FY26 earnings call

Wed 30 Jul 2025POWERINDIA

In brief

Hitachi Energy India Q1 FY26: record orders Rs.11,339 cr (+365% YoY) on Bhadla-Fatehpur HVDC; revenue +15.3%, op EBITDA margin 11.1%.

Management's tone
Confident
What was said
Leaned positive
Guidance
None given
Analyst pushback
Medium
Stock, next session
+5.23% (Nifty 50 +0.14%)
  • Q1 FY26 orders hit all-time high of Rs.11,339.2 cr (+365% YoY) driven by the Bhadla-Fatehpur HVDC order from Adani Energy Solutions.
  • Order backlog rose to all-time high of Rs.29,135 cr, providing revenue visibility for several quarters.
  • Revenue grew 15.3% YoY to Rs.1,529.8 cr with operational EBITDA margin of 11.1%; PAT of Rs.131.6 cr.
  • Services BU (live from April 1, 2025) saw order growth of 90% YoY and contributed high single digit to order book.
  • HVDC pipeline: 1-2 more projects expected to be finalised by March 31, 2026; Bhadla-Fatehpur is 6,000 MW, 800 kV bi-pole over 950 km.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q1 FY26

This quarterA year agoLast quarterMargin
Revenue₹1,479 cr+11.4%−21.5%
EBITDA (excl. other income)₹155 cr+223.4%−34.9%10.5% (3.6% a year ago)
Net profit₹132 cr+1163.0%−28.4%8.9% (0.8% a year ago)
EPS (₹)₹29.53+1100.4%−31.6%

From the company's filed results for the quarter ended 30 Jun 2025 (standalone), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

Where management's figures differ from the filing

  • Revenue (Total income vs Revenue from operations): said Revenue Rs.1,529.8 cr (total income including other income); filed Revenue from operations Rs.1,478.90 cr. Management quoted total income (revenue from operations + other income of Rs.50.94 cr). Gap = other income component.
  • Operational EBITDA: said Operational EBITDA Rs.170.2 cr, margin 11.1%; filed EBITDA excl other income Rs.154.90 cr, margin 10.5%. Stated 'operational EBITDA' uses a different definition/aggregation than filed EBITDA (excl other income). Difference ~Rs.15.3 cr / ~60 bps margin.

What moved the numbers, as management explained it

  • Q1 orders +365% YoY to Rs.11,339.2 cr were driven primarily by the Bhadla-Fatehpur HVDC win (6,000 MW, 800 kV bi-pole, 950 km) - a single large order, not a run-rate. (one-off)
  • Revenue growth of 15.3% YoY supported by effective execution of high-margin orders and a good product mix.
  • Operational EBITDA margin at 11.1% (up ~650 bps YoY) aided by material cost of 53.8% of total income and operational efficiency; other expenses 22.7% (vs 23.6% YoY).
  • Q1 P&L absorbed an exchange and commodity loss of Rs.9.4 cr; finance cost fell to Rs.4 cr as there were no short-term borrowings. (one-off)
  • Depreciation rose to Rs.25 cr vs prior year on capitalisation of capex projects under the Rs.2,000 cr plan. (accounting)

The numbers management led with

  • Q1 FY26 order intake: Rs 11,339.2 crores (+365% YoY)
  • Closing order backlog: Rs 29,135 crores (all-time high); HVDC forms 55-60%
  • Operational EBITDA margin: 11.1% (up 650 bps YoY)
  • Order growth by segment: Transmission +625% YoY; Rail & Metro +845% YoY; Data Centers +98% YoY; Industries +23%; Renewable -25% YoY
  • Capex plan: Rs 2,000 crores; expected asset turnover 3-4x to 4-5x; phased capacity over 18 months

Guidance

Guidance on this call

WhatForWhat management said
Operational EBITDA margin (sustainable)—we are looking at a very sustainable margins, double-digit margins, and that's what we are in a road map
FY26 EBITDA margin improvement over FY25FY26this year also, on an overall basis, we will improve higher than last year
HVDC pipeline finalisationFY26one to two projects finalized in this financial year on or before 31 March, 2026
Capex planFY26-FY30we are investing Rs. 2,000 crores of CAPEX
Export revenue mix (Exports)next couple of years25% is what I see in the next couple of years, plus/minus a few percentage points this way or that
Bhadla-Fatehpur HVDC bi-pole completion (HVDC (Bhadla-Fatehpur))—48 months is we have to complete the bi-pole one and 54 months is a bi-pole two
Mumbai HVDC (Adani) commissioning (HVDC (Mumbai))—we may be around six months is the one where we are looking at to commission that, six to nine months

What changed since the Thu 15 May 2025 call

WhatOn the Thu 15 May 2025 callOn this call
Order backlog (raised)Record order backlog of Rs.19,245 cr at FY25-endHighest ever order backlog of Rs.29,135 cr at end-Q1 FY26
HVDC projects in portfolio (raised)3 HVDC projects in portfolio (incl. Marinus Link, Mumbai VSC, plus Bipole I/II)Bhadla-Fatehpur won; 1-2 more expected to be finalised in FY26
Q1 FY26 EBITDA margin (achieved)Double-digit EBITDA to be maintained on FY26 basis; slow start in Q1 FY26 then rampQ1 FY26 operational EBITDA margin 11.1% already in double-digit
FY26 EBITDA margin trajectory (restated)Double-digit EBITDA to be maintained on FY26 basisthis year also, on an overall basis, we will improve higher than last year
Capex plan (held)Approximately Rs.2,000 crores over 4-5 years; step-up to roughly 4-5x FY25's Rs.130 cr per yearRs.2,000 crores of CAPEX; phased execution across transformer, high-voltage, grid automation and HVDC
Services BU order run-rate target (held)Target Rs.2,000 cr per year over 3-4 year horizon from current Rs.500-600 cr baseService orders grew 90% YoY; contributed high single digit to order book (target reaffirmed implicitly)
Export strategy framing (restated)Exports grew 77% YoY in FY2525% of revenue mix in next couple of years, plus/minus a few percentage points

The business

By business

HVDC (Bhadla-Fatehpur)

Won 6,000 MW, 800 kV bi-pole bidirectional HVDC project from Adani Energy Solutions covering 950 km from Bhadla (Rajasthan) to Fatehpur; consortium with BHEL.

6,000 MW · 800 kV bi-pole · 950 km

Outlook: 1-2 HVDC projects expected to be finalised in FY26 (on or before 31 March 2026); project needs 48 months for bi-pole 1 and 54 months for bi-pole 2

Transmission

Led Q1 order book; included POWERGRID order for 30 units of 765 kV 500 MVA single-phase transformers and several 400 kV/220 kV GIS orders.

Q1 order growth 625% YoY · 30 units 765 kV 500 MVA single-phase transformers

Outlook: Management sees need for 2-3 HVDCs per year over next couple of years; pipeline very strong

Rail & Metro

Sharp 845% YoY order growth in Q1; included Scott transformers, automation and CRP SCADA projects.

Q1 order growth 845% YoY

Outlook: Very robust swing in rail and metro demand; short-cycle execution (6-18 months)

Data Center

Orders almost doubled at 98% growth YoY after a lull previous quarter; AI-ready data center demand re-emerging.

Q1 order growth 98% YoY

Outlook: Customers relooked at AI-ready data center requirements; coming back very strongly; short-cycle

Industries

Sustained 23% YoY order growth including GIS and transformer orders for semiconductor manufacturing factories in Chennai.

Q1 order growth 23% YoY

Outlook: Short-cycle projects; demand stable to growing

Renewable (Wind & Solar)

Q1 orders declined 25% YoY vs industry growth of 23%; management views this as temporary and timing-related.

Q1 order decline 25% YoY · Industry growth 23%

Outlook: Expected to recover as PPA issues get resolved; short-cycle orders

Exports

Contributed ~24.7% of order book (ex-HVDC); orders from Europe, South America and Asia across capacitors, filters, circuit breakers, grid automation.

~24.7% of order book ex-HVDC

Outlook: Target to maintain ~25% of revenue mix over next couple of years (±few percentage points)

Services

New 5th business unit live from April 1, 2025; service orders grew 90% YoY in Q1; contributed high single digit to overall order book.

Q1 service order growth 90% YoY

Outlook: Scale-up continues; all BUs working closely with Services to maximise reach; Rs.2,000 cr/year order run-rate target (reaffirmed from prior call)

Balance sheet, capex and funding

  • No short-term borrowings in Q1; finance cost at Rs.4 cr (down YoY).
  • Rs.2,000 cr capex plan over 4-5 years, in phased execution across transformer, high-voltage, grid automation and HVDC.
  • Q1 depreciation at Rs.25 cr, up YoY on capitalisation of capex projects.
  • QIP proceeds to be used: ~2/3 for capex expansion, 25% for general corporate purposes, 10% for working capital (FY26 onward).
  • First phase of transformer capacity (small expansion) already underway; next phases to follow; capacity additions expected in next 18 months.

The industry, as management sees it

Management sees an 'energy super cycle' in India and globally, driven by the National Energy Plan (Rs 1 lakh cr+ spend on interstate transmission over two years), data center build-out (98% order growth in Q1), rail/metro expansion, and DISCOM privatisation (Uttar Pradesh). Expects 2-3 HVDC projects per year to be required to manage network complexity, with 25-30 STATCOM projects over the next four years per CEA's National Electricity Plan.

Risks management named

  • US tariff uncertainty — impact on India and Hitachi Energy yet to be fully ascertained
  • Renewable (wind/solar) orders declined 25% YoY, described as a temporary timing issue
  • Exchange and commodity loss of Rs 9.4 cr in Q1 FY26
  • Royalty / technology access fee of ~4% of sales paid to parent — non-negotiable per management
  • Depreciation rose YoY due to ongoing capex capitalisation, weighing on reported PBT

Q&A

Q&A was dominated by questions on margin trajectory and benchmarking vs peers (GE T&D India), particularly the ~4% royalty to parent. Management pushed back firmly on the royalty comparison as short-termist, defending it as the price of accessing world-leading HVDC and grid technology. The other major theme was the HVDC pipeline — management indicated 1-2 of the three projects in pipeline would finalise in FY26 but refused to share export ex-HVDC order book value or pipeline growth numbers. Several friendly clarifying questions on segment growth and capex were answered directly. The pushback was constructive but pointed; no analyst pushback went unanswered on substance.

Not answered directly

  • HVDC project value/quantum
  • Project-level (HVDC) gross margins
  • Export ex-HVDC order book breakdown
  • Bid pipeline numbers for export and domestic
  • Mumbai-Ahmedabad HSR timeline and opportunity size

Asked for a number, answered without one

  • Ex-HVDC order value: we will not quantify the exact value of HVDC, but you can guess what kind of number; growth without HVDC is in the double-digit range, in the range of 20-plus percent
  • HVDC project gross margins: We will not talk about our project level margin
  • Export and service split in order book: we do not split there how much is exports and service
  • Bid pipeline growth number: We have not shared so far, Mr. Subramaniam. But when we share we will share it with you.
  • Mumbai-Ahmedabad HSR tender timeline: we do not have a visibility, we are still discussing with our customers. We do not have any timeline for that.
  • Service component in HVDC project: service component will be there everywhere. We are not able to quantify service

Every question, with its answer

  1. 1. HVDC order mix and execution timeline

    Mohit Kumar, ICICI Securities

    Question. Can you share the value of ex-HVDC orders in Q1 or the growth in orders ex-HVDC? And second, how is execution progressing on the Bhadla-Fatehpur HVDC project won in September/October 2024?

    Answer, N. Venu, Managing Director & CEO. On ex-HVDC orders, growth was 20-plus percent in double digits; company will not quantify HVDC value separately. On execution, HVDC projects are long-tenor — 48 months for bi-pole one and 54 months for bi-pole two. Revenue contribution starts from next financial year; year one is minimal.

    Not answered directly.

  2. 2. Margin gap vs peers and core order trajectory

    Bhalchandra Shinde, Motilal Oswal

    Question. Margin profile — peers have raised margins significantly but ours, though improved, hasn't kept pace. Is there a path to reach peer-level margins? And on core order inflows, should we expect this trajectory to continue?

    Answer, N. Venu, Managing Director & CEO. Management is focused on long-term, not short-term; the addressable domestic market remains very strong, justifying the Rs 2,000 crore capex investment. EBITDA margins improved 650 bps YoY and will continue to improve. On core orders, the pipeline across renewable, industries, data centers and rail is very strong; HVDC pipeline also robust with 2-3 projects per year needed for India's network complexity.

    Partly answered.

  3. 3. Gross-to-EBITDA margin bridge and HVDC pipeline timing

    Umesh Raut, Nomura

    Question. Despite gross margins of ~44%, EBITDA margin is stuck at 10-11% with other expenses at ~24% of sales. Related party transactions (royalty, management fees, trademark fees) are eating 8-9% of sales — how will these decline? And timeline for the three HVDC projects in the pipeline (Khavda, Barmer, Leh-Ladakh)?

    Answer, N. Venu, Managing Director & CEO. On margins: royalty is non-negotiable for accessing Hitachi Energy's global technology; some expenses are fixed in nature and will taper as a percentage of revenue as volumes grow. CFO added other expenses were ~20% at year-end and should moderate as revenues scale. On HVDC pipeline: management expects 1-2 projects to be finalised in FY26 (by 31 March 2026), with potential for a second.

  4. 4. Order book composition and HVDC margin profile

    Parikshit Kandpal, HDFC Securities

    Question. Out of the Rs 29,000 cr order book, what is the ex-HVDC base? Of that, how much is export and services? And on HVDC gross margins, what dilution should we expect?

    Answer, N. Venu, Managing Director & CEO. HVDC is 55-60% of the order book; rest is non-HVDC. Company will not split further between exports and services — service is just picking up and the HVDC vs non-HVDC distinction is artificial since HVDC itself contains transformers, GIS and grid automation. On HVDC GPM, management will not comment on project-level margins; reiterated focus on sustainable double-digit margins and that the company has 'entered much ahead of our own target'.

    Not answered directly.

  5. 5. HVDC execution, Leh project, GPM sustainability and export pipeline

    Renu Baid, IIFL Capital

    Question. Update on the first Adani HVDC (~Rs 2,000 cr) — how far from formal completion? Insights on Leh HVDC where Hitachi has reportedly not bid? Is GPM of ~45% sustainable given current backlog mix? Any specific export pipeline regions?

    Answer, N. Venu, Managing Director & CEO. Adani HVDC: 6-9 months from commissioning. Leh: still in discussion stage on technology; probability of converting to AC transmission is very low. GPM sustainability: will not comment quarter-on-quarter; structurally the company is fine and fixed-cost conversion to percentages as volumes grow will improve margins. Exports: three-pronged strategy — global products, market allocation, feeder components; do not want to spike exports at the cost of domestic market; targeting ~25% export mix.

  6. 6. Export positioning, intra-group competition, segment demand

    Rajesh Kothari, AlfAccurate Advisors

    Question. How is the Indian company positioned to capture global demand given Rs 2,000 cr capex and what should be the export share 3-5 years out? Who competes with Hitachi Energy India within the group? Will revenue mix remain 25-27% exports even as domestic revenue scales? Demand outlook for data centers and metros?

    Answer, N. Venu, Managing Director & CEO. Capex is for domestic demand primarily; exports are on top of that and 25% is the rough steady-state target, +/- a few percentage points. Within the group, market allocation is governed by clear guidelines across 68+ countries and approvals; no internal free-for-all. New capex coming online in ~18 months will keep 25% mix intact even at higher revenue. On segments: industries +23%, data centers ~98% (rebounding on AI-ready demand), rail/metro very robust; all short-cycle (6-18 months) except HVDC.

  7. 7. Business unit split and capex capacity expansion

    Shirom Kapur, Jefferies India

    Question. Can you give colour and rough share across the five business units (transformers, high-voltage, grid integration, grid automation, services)? And quantification of the Rs 2,000 cr capex — by how much will capacity expand and current utilisation that warrants this spend?

    Answer, N. Venu, Managing Director & CEO. Will not split business units but directionally: transformer is highest, followed by grid integration, then high-voltage, then grid automation and services. Most end-segments (transmission, industries, data centers) need 2-4 BU product portfolios. On capex: phased across transformer, high-voltage, grid automation and HVDC; once complete, asset turnover expected at 3-4x to 4-5x. Will not quantify exact current capacity utilisation; high in large power transformers, GIS and insulation; available in automation.

    Partly answered.

  8. 8. Export ex-HVDC order share and pipeline

    Subramaniam Yadav, SBI Life Insurance

    Question. What is the export orders ex-HVDC in the order book and how do margins compare with domestic? And pipeline numbers for domestic and export ex-HVDC?

    Answer, N. Venu, Managing Director & CEO. Export share of order backlog ex-HVDC is in the same range — ~20%. On pipeline, company does not share numbers; only commentary that ex-HVDC pipeline is very strong across industry, transmission, renewable, data centers, rail and exports. Will not share growth number vs last year.

    Not answered directly.

  9. 9. HSR opportunity and STATCOM localisation

    Harshit Patel, Equirus Securities

    Question. Update on the Mumbai-Ahmedabad HSR electrical package — when will it be tendered and what is the opportunity size? And has STATCOM manufacturing/assembly started in India? Overall STATCOM opportunity size?

    Answer, N. Venu, Managing Director & CEO. On HSR: company has received some transformer orders but overall visibility and timeline is not there; still in discussions with customers. On STATCOM: everything is done in India — valves, transformers, engineering; complete localisation. Opportunity size: 25-30 STATCOM projects in next 4 years per CEA's National Electricity Plan.

    Not answered directly.

  10. 10. Execution delays in Q1

    Pratik Singh, Helios Capital Management

    Question. Was there any execution miss in Q1 or potential delays? Ex-other income, the core top line growth looks softer at 11-12%.

    Answer, N. Venu, Managing Director & CEO. No major execution delays in any project. With a large portfolio, one or two delays are always there but nothing material. Revenue growth of 15% YoY was reported; the analyst's ex-other-income growth calculation differs but underlying execution is on track.

  11. 11. HVDC vs non-HVDC project differentiation and outlook

    Abhijeet Singh, Systematix Group

    Question. How does HVDC differ from non-HVDC transmission in terms of products, services, and execution? Can you quantify service component in HVDC? You mentioned expecting 2-3 HVDC projects per year — confirm? And segment growth numbers on slide 10 are Q1 order inflow growth?

    Answer, N. Venu, Managing Director & CEO. From equipment supply standpoint, HVDC requires heavy system studies, design and engineering, taking much longer than a vanilla 400/220 kV project. Service component cannot be quantified separately — HVDC also has higher service intensity but not materially so. On outlook, 2-3 HVDC projects per year are needed to manage India's network complexity; NEP itself supports ~2 per year. Slide 10 numbers are Q1 order inflow growth.

  12. 12. Royalty payout and admin cost benchmarking

    Dhavan Shah, AlfAccurate Advisors

    Question. Royalty payout is ~4% vs GE T&D India at ~1% — can the company reduce royalty and step up dividend payout since Hitachi parent holds 75%? Admin cost is also higher at 4-5% vs peers' 1-2% — any room to improve?

    Answer, N. Venu, Managing Director & CEO. On royalty: company does not do 'financial engineering' on short or medium term. The 4% royalty buys access to world-leading technology — HVDC, energy storage, synchronous condensers, automation — that would be impossible to develop independently. Hitachi Energy India has localised a lot of technology; royalty supports continuous access. Margins are improving and will continue to. On admin cost: some items are fixed in nature and will convert to a lower percentage as revenue scales in coming years.

    Partly answered.

What was said

Topic by topic, in the order it was spoken

Safety, ESG and Sustainability · N. Venu (MD & CEO)

  • Safety framed as 'licence to operate'; incident frequency rate kept within defined corridor, multiple customer appreciation letters received in Q1 FY26
  • CO2 emissions reduced 84% and waste 69% versus 2019 base year in own operations
  • 100% renewable electricity used across all Indian sites; freshwater reduction target now 25% (up from 18%)
  • Continued focus on zero harm, zero fatality, and integrity incidents; women-in-engineering batch expanded with students from Gujarat

India Macro and Sector Context · N. Venu (MD & CEO)

  • India ranked 4th largest economy; June 2025 inflation at 6-year low of 2.1%
  • Manufacturing PMI at 14-month high of 58.4 in June 2025 reflecting policy-driven growth
  • National Energy Plan implies Rs 1 lakh cr+ spend on interstate transmission over next 2 years to meet 2027 targets
  • DISCOM privatisation flagged as positive — Uttar Pradesh moving to privatise two of its four power distribution companies

Q1 FY26 Headline Performance · N. Venu (MD & CEO)

  • All-time-high order intake of Rs 11,339.2 cr (+365% YoY); revenue at Rs 1,529.8 cr (+15.3% YoY)
  • Key wins: 30 units of 765 kV/500 MVA transformers from POWERGRID; 400 kV GIS for renewable solar; 220 kV/33 kV GIS for semiconductor facility in Chennai; multiple rail transformers and SCADA automation projects
  • Order growth strong across segments except renewable which declined 25% YoY — described as timing-driven, not demand erosion

Bhadla-Fatehpur HVDC Project · N. Venu (MD & CEO)

  • Adani Energy Solutions awarded the project to the Hitachi Energy India and BHEL consortium
  • Scope: 6,000 MW, 800 kV bi-pole, bidirectional HVDC over 950 km from Bhadla (Rajasthan) to Fatehpur
  • Delivery includes converter transformers, AC/DC control & protection, thyristor valves, 765 kV/400 kV grid connections and auxiliary systems
  • Execution timeline: 48 months for bi-pole one and 54 months for bi-pole two — revenue contribution from next financial year

Order Mix, Service Carve-out and Exports · N. Venu (MD & CEO)

  • Ex-HVDC, projects share of order book rose; products continue to be the largest sub-mix followed by projects and services
  • Service business formally carved out from 1 April 2025; service orders grew 90% YoY contributing high single-digit to order book
  • Exports maintained at ~25% of order book (ex-HVDC) — orders this quarter from Europe, South America and Asia across capacitors, filters, breakers, grid automation
  • Service business objective: intensify life-cycle engagement across utilities, industries and new-age customers

Q1 FY26 Financial Walkthrough · Ajay Singh (CFO)

  • Order backlog closed at all-time high of Rs 29,135 cr — provides multi-quarter revenue visibility
  • Operational EBITDA at Rs 170.2 cr with 11.1% margin; PBT Rs 176.9 cr; PAT Rs 131.6 cr (PAT margin 8.6%)
  • Cost mix: material 53.8%, personnel 9.5%, other expenses 22.7% (vs 23.6% YoY); finance cost fell to Rs 4 cr on absence of short-term borrowings
  • Reported exchange and commodity loss of Rs 9.4 cr; depreciation rose to Rs 25 cr on capitalisation of ongoing capex

Strategic Priorities for FY26 · N. Venu (MD & CEO)

  • Dual focus: maintain growth momentum and enhance efficiency across all operations
  • Lead in core segments (renewable, utilities, HVDC, industries, infrastructure); deepen play in data center, service, export and digital
  • Leverage large order backlog for revenue and margin accretion; deploy QIP capital on capex in line with announced timelines
  • Long-term, sustainable strategy — investment in technology, workforce upskilling, and operational footprint for future growth

In their words

We are looking for long-term strategy and long-term growth and sustainable strategy.
N. Venu (MD & CEO, Hitachi Energy India)
we do not do any financial engineering on a short-term or midterm basis. The technology what we are developing, we are by far the world leader and that technology is available at a 4% cost. If you want to develop that, that's not possible.
N. Venu (MD & CEO, Hitachi Energy India)
What we are in, what we call, an energy super cycle. Super excited about the growth opportunities both locally and globally.
N. Venu (MD & CEO, Hitachi Energy India)

To check next time

What management committed to on this call, or the dates they gave.

  • Bhadla-Fatehpur HVDC execution progress; revenue contribution expected to start from FY27.
  • Awarding of 1-2 HVDC projects by 31 March 2026 (Khavda South Ulapada, Barmer-South Kalamb, Leh-Ladakh).
  • Mumbai HVDC (Adani) commissioning timeline; guided at 6-9 months.
  • Services BU order run-rate progression towards Rs.2,000 cr/year target.
  • Sustainability of operational EBITDA margin in Q2 FY26 after Q1's 11.1%.
  • Phased capex execution and capacity commissioning (next 18 months).

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Wed 30 Jul 2025₹20,825.00+5.23%+0.14%
5 sessions Tue 5 Aug 2025₹21,345.00+7.86%−0.69%
20 sessions Thu 28 Aug 2025₹19,590.00−1.01%−1.29%

From the close of Tue 29 Jul 2025, ₹19,790.00: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

Hitachi Energy India's other calls

  • Q2 FY27Wed 18 Nov 2026Not read
  • Q2 FY27Thu 12 Nov 2026Tone: Confident
  • Q4 FY26Tue 26 May 2026Tone: Confident
  • Q3 FY26Thu 5 Feb 2026Tone: Confident
  • Q2 FY26Fri 7 Nov 2025Tone: Confident
  • Q4 FY25Thu 15 May 2025Tone: Confident
  • Q3 FY25Thu 30 Jan 2025Tone: Confident
  • Q2 FY25Tue 29 Oct 2024Tone: Confident
  • Q1 FY25Thu 25 Jul 2024Tone: Mixed
  • Q4 FY24Wed 22 May 2024Tone: Confident